HF Video MeetingDec 2002E. Hazen HF Electronics PMT Readout Update E. Hazen, J. Rohlf, E. Machado Boston University
2
HF Video MeetingDec 2002E. Hazen Status of Prototypes ● Two skew-clear 5m cables due any day now... ● New QIE HF boards: – Bare PCBs due end of this week – Stuffed PCBs (10) due end of January ● Patch panel / ROBOX cables – Connectors and tooling in hand – Patch panel quick-turn PCBs ready next week ● (can use two patch panels with existing QIE boards as a starting point to test skew-clear cable)
3
HF Video MeetingDec 2002E. Hazen LED Pulser Tests ● We studied briefly the performance of the Iowa pulser, and it does indeed work as advertised
4
HF Video MeetingDec 2002E. Hazen 7ns fwhm Input to LED pulser (clipped)Output from LED Pulser PMT Signal (~100pe) PMT Signal (average) 10ns fwhm 5ns risetime 10ns fwhm
5
HF Video MeetingDec 2002E. Hazen Task List