Presentation is loading. Please wait.

Presentation is loading. Please wait.

William Berg 6.17.08 Beam Loss Monitor LCLS Undulator Systems Beam Loss Monitor Status Report, FAC 6.17.08 William Berg ANL/APS Diagnostics.

Similar presentations


Presentation on theme: "William Berg 6.17.08 Beam Loss Monitor LCLS Undulator Systems Beam Loss Monitor Status Report, FAC 6.17.08 William Berg ANL/APS Diagnostics."— Presentation transcript:

1 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor LCLS Undulator Systems Beam Loss Monitor Status Report, FAC 6.17.08 William Berg ANL/APS Diagnostics Group

2 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Introduction Purpose & Requirements Project Scope Update Global System Status & Schedule –Detector –Interface Module –Link Node Front End Girder Integration Test Devices & Status Concluding Remarks

3 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Purpose h-dn The BLM will be used for Two Purposes: A: Inhibit bunches following an “above-threshold” radiation event. B: Keep track of the accumulated exposure of the magnets in each undulator. Purpose A is of highest priority. BLM will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors. Purpose B is also desirable for understanding long-term magnet damage in combination with the undulator exchange program but requires a large dynamic range for the radiation detector (order of 10 6 ) and much more sophisticated diagnostics hard and software.

4 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Requirements pk Primary function of the BLM is to indicate to the MPS if losses exceed preset thresholds. MPS processor will rate limit the beam according to which threshold was exceeded and what the current beam rate is. *Beam Current threshold determination? The thresholds will be empirically determined by inserting a thin obstruction upstream of the undulator. Simulation of losses and damage in the undulator will proceed in parallel with the present effort.

5 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Project Updates Design review held 1-24-08. Descope March 2008 –Management Directive: no fundamental design modifications (lowest effort costs). –2008 m&s costs reduced 400k to 75k. –FY 2008 BLM Project defined as R&D (not construction). –33 installed units decreased to 5 for mps function only. –FY 2009 funding for remaining detectors pending. –Proceeding with Simulations and Empirical Testing to verify dosimeter function.

6 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Project Status BLM Engineering Specification Document –Broken into 3 ESD’s. Beam Line Detector (ANL, in progress). Interface Module (ANL, completed). Link Node Front End (SLAC, in progress). Global electronic review complete (ready for fabrication pending testing, eric norum 4/16). Global Schematic diagrams, block diagram, and parameter list (archived, Josh Stein, designer assignment?).

7 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Detector Schedule

8 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Status - Detector Beam Line Detector: –Detail and Assembly Drawings: (engineering review and tolerancing). Detector Head. Detector BFW Mounting Bracket. Undulator Motion Tracking Adapter.

9 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Status - Detector All material and components identified. Vendor list compiled. Stock procurements underway. Long lead procurements (5/08). Fabrication quotes and awards (6/08).

10 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Rendering of Detector

11 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Cross Section of BLM Detector

12 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator Inserted Position

13 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Pin Function

14 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Interface Module Schedule

15 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Status – Interface Module (IM) Prototype design complete. Prototype board and enclosures fabricated. Final enclosure design in process (stenciling?) Bench and beam based testing plan.

16 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Interface Module Board

17 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Interface Module Enclosure

18 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Status – Link Node Front End (slac) Design in progress. Procurements started. Prototype boards in fabrication. Bench and beam based test plan.

19 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Beam Loss Monitor - Undulator Hardware (m. brown) In Undulator Hall Long Haul Cables

20 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Integration Interface Module Girder Location. BLM Detector Girder Identification (which five?). Estop/IM Bracket Design (in progress). Cable Plant details (z drops). Power Supply from local control rack (cable length). Installation Procedure. Long haul cables defined and in process. Link Node channels and rack distribution defined.

21 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Interface Module Girder Location

22 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor

23 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Tunnel Cable Drops

24 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Detector Test Devices Thru-put and beam test module –Design Complete –Cerenkov radiator in fabrication –Housing out for quote (qnty 3). –Procurements underway APS Beam Pipe Detector (not tied to FY08 production) –Design Complete. –Detailed and assembly drawing (eng. review/tol.).

25 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Test Module Rendering

26 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Test Module Drawing

27 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Cerenkov Radiator Fabrication

28 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Radiator Blocks (actual uv grade material)

29 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Radiator Blocks (actual uv grade material)

30 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Concluding Comments Overall blm program budget is thin. Timetable is very aggressive. On Schedule for October. Calibration hardware needs to be solidified. Simulation, test, calibration, operation plan. BLM MOU scope FY2009?

31 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Status End of Presentation

32 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Introduction Physics Requirements Document: Heinz-Dieter Nuhn 9-28-07 (prd: 1.4-005-r0 undulator beam loss monitor). Scope Reduction: diagnostic to mps detector. Purpose and Requirements. ANL Budget: M&S (325k detector, ctls interface box 100k). Detector Schedule: (design: nov-dec,drawings: dec-feb,pro/fab/assy: feb-jun,del: july, inst: aug-sep). Organization: 4 groups, Group Definition: (controls, detector, simulation, test & calibration). Design Highlights and System Overview (detectors: dynamic 33, static: 2, r&d fiber:1). Detector design details and focus topics. Funds are limited and efforts need to be focused to minimize costs (h-dn). Simulation of losses and damage in the undulator will proceed in parallel with the present effort (pk).

33 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor ANL Draft BLM Budget 425k M&S Total: 325k Detector Development detectors mounting and slide systems cables and fiber 100k Controls Interface Box

34 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Draft schedule

35 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor LCLS MPS Beam Loss Monitor System Engineer: W. Berg Cost Account Manager: G. PileTechnical Manager: D. Walters Scientific advisor: P. Krejcik * FEL Physics: H. Nuhn * Scientific advisor: B. Yang FEL Physics: P. Emma * Controls/MPS Group Lead (ctls) : J. Stein Lead (mps): A. Alacron * Detector Group Lead: W. Berg Simulations and analysis Group Lead: J. Dooling Testing and Calibration Group Lead: B. Yang M. Brown * R. Diviero J. Dusatko * S. Norum * A. Pietryla A. Brill L. Erwin R. Keithley J. Morgan L. Emery M. Santana * J. Vollaire * B. Yang W. Berg J. Bailey J. Dooling L. Moog * Slac employee

36 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor MPS Beam Loss Monitor Group Functions Controls Group: J Stein, A. Alacron Develop BLM control and mps system: Interface Box and Control. PMT Signal Conditioning. Control and MPS Integration and User Displays. Detector Group: W. Berg Develop Detector and Machine Integration. Simulations and Analysis Group: J. Dooling Provide collaborative blm simulation support and test analysis. Test and Calibration Group: B. Yang Provide beam based hardware testing programs and calibration plan.

37 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor System Design Highlights 33 distributed detectors (one preceding each undulator segment), two static units (up and downstream of undulator hall). One additional channel reserved for r&d fiber based system. MPS threshold detection and beam rate limiting. Single pulse detection and mps action up to max 120Hz beam rep rate via dedicated mps link. Monitoring of real time shot to shot signal levels and record integrated values up to one second. Heart beat led pulser for system validation before each pulse up to full rep rate (pseudo calibration). Remote sensitivity adjust (dynamic range) by epics controlled PMT dc power supply (600-1200V). Calibrated using upstream reference foil (initial use cal will be determined from simulation studies).

38 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Detector Design Highlights Cerenkov Radiation Based (x-ray beam noise immunity). Employs PMT for high sensitivity to beam losses. Dynamic detector (tracks with undulator) 100mm stroke. Undulator position (in/out) detection will be used to set the corresponding mps threshold levels. Manual static insertion option via detachable arm for special calibration and monitoring. Large area sensor (coverage of the full horizontal width of the top and bottom magnet blocks). Fiber Out for low gain upgrade (full integration and dyn range diagnostic), control system expandable to 80 channels. Radiation hard components (materials and electronics).

39 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Interconnect Diagram m. brown

40 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Interface Box Location

41 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Plan View of Short Drift

42 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BFW Pump Out Port Relocation

43 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Removable Pin for Manual Insertion

44 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator Inserted Position

45 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator Retracted Position

46 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Detector Pin Detail

47 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Cerenkov Radiator

48 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Magnet Block Sensor Coverage

49 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Proposed PMT Device -04 (420nm)

50 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Vendor List Radiator Substrate water jet and final polish (lap and flame) (quartz)- VA Optical Radiator AlSi coating – Eddy Company Radiator Material - Corning PMT and Magnetic Shield - Hamamatsu Connectors: SMA Fiber Feed through) -Thor Labs High Voltage Feed through - Kings SMB Signal Fed through - AMP Fiber Optic Cable (heartbeat) Fiber (fused silica) - Stocker Yale Fiber Optics Cable, UV Grade – Coastal Connections Signal Cable – Belden Body Fabrication- M1, High Tech, AJR Industries Miscellaneous Hardware (fasteners, o-rings, flex coupling, spanner wrench) – McMaster-Carr Linear Bearing Assembly – IKO International Spherical Bearing – Aurora Bearing

51 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor UV Grade Fiber

52 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Fused Silica Radiator

53 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM System Support Focus Topics Funding of beam based prototyping and test program. Implementation of upstream calibration foil (alt. profile monitor/halo). BFW prototype tolerance verification (system tolerance in LTT)

54 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Summary Undulator magnets protection is critical for machine commissioning period. BLM system is now defined as a component of the mps (descope) with an upgrade path to a diagnostic (low gain detector). Calibration plan and hardware is vital to proper system operation (threshold detection will use empirically derived levels). Schedule for development of the blm program is very aggressive and funding is limited.

55 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Detector Summary Building a detector based on cerenkov radiation and PMT detection. 36 distributed channels (2 static devices) capable of single pulse detection (up to full rep rate) with rate limiting reaction. Detectors dynamically track with undulator position with manual detach option to remain in a fully inserted static position. Adjustable PMT sensitivity with remotely controlled high voltage power supply. Keep alive system test (led pulser) before each beam pulse. All Vendors have been identified, Quotes in progress, Drawing set being reviewed. Installation does not require access into the vacuum system or removal of other components.

56 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor End of Presentation

57 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor

58 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Parts Animation

59 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator System

60 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM System Support Focus Topics 1.Assignment of Eric Norum to controls design oversight and testing. 2.*Funding of beam based prototyping and test program. 3.Group Leaders to significantly step up direct involvement in system oversight, program implementation, and schedule tracking (controls: n. arnold, diag: g. decker, lcls: g. pile, ops/analysis: m. borland). 4.Active participation in simulations and simulation priority from slac. 5.*Implementation of upstream profile monitor (halo or at min. cal foil). 6.Adequate analysis and shielding of upstream beam dump. 7.Develop long term collaboration plan for the pursuit of determining magnet damage mechanisms and thresholds via empirical methods. 8.Determine need and priority of BLM signal integration (diagnostic). 9.BFW prototype verification (system tolerance LTT)

61 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Summary  Undulator magnets protection is critical for machine commissioning period.  Schedule for development of the blm program is very aggressive and funding is limited.  System design and fabrication must go in parallel with simulation and testing program.  Consider Minimum requirements for first level implementation. Taking advantage of existing mps infrastructure.  BLM system is now defined as a component of the mps with an upgrade path to a diagnostic (low gain detector).  36 distributed channels (2 static devices) capable of single pulse detection and rate limiting reaction.  Detectors track with undulator position with detach option for manual operation.  Calibration plan and hardware is vital to proper system operation (threshold detection will use empirically derived levels).  Quotes in progress  Drawing set being reviewed

62 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Controls Architecture pk The BLM PMT interfaces to the MPS link node chassis. The IO board of the MPS link node chassis provides the ADC & DAC for the PMT. A detector interface box (pmt, led pulser, sig con?) is the treaty point between the MPS and the undulator BLM. There are 5 link node chasses serving up to 8 BLMs along the undulator (expandable from 8 to16 channels).

63 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator Hardware

64 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Beam Loss Monitors with Link Nodes Use Link Node to support analog I/O IndustryPack modules provide analog readouts to control system set threshold levels control HV power supplies control LED Pulser

65 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Segment Design Layout m. brown MPS Link Node

66 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Locking Pin Detail (moves with undulator) Spherical Bearing Flex Joint

67 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Beam Loss Monitors using Link Nodes

68 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Proposed PIC / BLM Timing

69 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Link Node Block Diagram

70 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor

71 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor

72 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Undulator Protection Requirements Inputs to inhibit the e-beam Primary protection from a number of Beam Loss Monitors (BLMs) along the undulator Secondary protection from control system monitoring of BPM orbit Magnet power supply status Magnet mover status Long-term monitoring of the radiation dose Dosimeters attached to the magnets

73 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Rolls Out with Undulator Magnet The BLM is mounted to tightly surround the vacuum pipe near the beam finder wire It is on a linear slide so that it can be moved off the beam when the undulator magnet is rolled out An detachable arm makes the BLM and magnet roll out together The BLM will automatically be less sensitive to beam loss when the undulator is in the out position The BLM can be manually inserted on the beam pipe for special calibration procedures

74 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Specification A single BLM will be placed in each of the gaps between undulator modules. Design is to maximize the sensitivity of the monitor Located as close as possible to the beam axis as the vacuum chamber allows Choose a sensitive Cerenkov medium coupled to a high gain photomultiplier tube The detector will not be segmented to provide transverse position information of the losses

75 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM reliability and self test Each loss monitor is equipped with a LED that flashes between beam pulses. Provides a pre-beam test of the BLM system before beam is sent through the undulator Provides a stay-alive signal for the control system to monitor the BLM system during operation

76 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM dynamic range For simplicity and cost the BLM will be optimized for maximum sensitivity And allowed to saturate the signal if a large loss occurs The trip threshold is still exceeded if the device saturates so the MPS will still trip and protect the undulator Monitoring of the loss signal to integrate the dose received by the undulator will not be valid if the device saturates However, if large losses are anticipated such as when the beam finder wires are inserted, the gain of the PMT will be reduced to prevent saturation.

77 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Signal Monitoring The BLM has a fast, dedicated link to the MPS to shutoff the beam within 1 pulse The local MPS link node chassis also has a ‘slow’ network connection to the control system via channel access Allows monitoring of the BLM level at any time Reads back and controls the PMT voltage Controls the LED test pulse Controls the threshold set point for MPS trips

78 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor BLM Controls Architecture The BLM PMT interfaces to the MPS link node chassis The IO board of the MPS link node chassis provides the ADC & DAC for the PMT A cable interface box is the treaty point between the MPS and the undulator BLM There are 5 (? verify this number) link node chasses serving up to 8 BLMs along the undulator (a diagram would help here)

79 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor Future expansion The link node chassis can handle more than the present number of installed BLMs During commissioning a long fiber BLM will also be tested It is compatible with the link node chassis controls

80 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor MPS Overview (m. brown)

81 berg@aps.anl.gov William Berg 6.17.08 Beam Loss Monitor System Roll


Download ppt "William Berg 6.17.08 Beam Loss Monitor LCLS Undulator Systems Beam Loss Monitor Status Report, FAC 6.17.08 William Berg ANL/APS Diagnostics."

Similar presentations


Ads by Google