3 BUILDING STRONG ® 3 Project Current Conditions  Authorized depth ► 12 feet mlw on main route ► 7 feet mlw in alternate routes  Controlling depths < 4 feet mlw ► Hell Gate 4.0 ft ► Little Mud River 3.0 ft ► Buttermilk Sound 4.0 ft ► Jekyll Creek 4.0 ft centerline only

4 BUILDING STRONG ® 4 Project Usage 2007-2009  Per Waterborne Commerce FY200720082009 Short Tons147,000185,000151,000 Ton-miles9,131,00012,825,0008,746,000 Trips-ton- miles 20,162,00028,858,00028,096,000

5 BUILDING STRONG ® 5 Appropriations Fiscal YearAmount 2008$ 1,870,000 2009 O&M General$ 946,680 2009 ARRA$ 3,807,511 2010$ 876,150 2011 Work Plan$260,073 2012 President/House/Senate$ 0

6 BUILDING STRONG ® 6 FY 2012 Work  Complete updating the NEPA documents to meet current environmental laws started in FY10  Complete Dredge Material Management Plan to comply with the new environmental laws started in FY 10

7 BUILDING STRONG ® 7 Future Needs Funds to execute the plan completed in FY 2012

8 BUILDING STRONG ® 8 Savannah District Atlantic Intracoastal Waterway Questions ?