John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Linac Coherent Light Source Overview 29 October 2007 Project status, effects of continuing resolution Continuing resolution, revised estimate-to-complete Organization Preparation for experiment operations
2
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007
3
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Project Baseline Proposed Baseline May 2005 Change September 2007 TEC $315M, TPC $379M CD-4 3/09 Start of Operations Characterize x-ray flux @ 1.5 Angstroms, in front end enclosure (FEE) Detect X-rays in the Far Experiment Hall TEC $352M, TPC $420M Level 2 DOE milestone 7/09 Start Near Hall Ops Characterize x-ray flux at 1.5 Angstroms, in the Front-end enclosure CD-4 7/2010 Project Complete Detect X-rays in the Far Experiment Hall
4
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Status of Baseline Change Lehman review 7/2007, follow-up 9/2007 EIR 10/2007 Draft report due 10/26/2007 Review went well Approval of new baseline by 12/2007
5
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 FY2008 contingency risks and handling Limited Budget Authority in FY2008 If contingency use in 2008 is too high: Delay start of installation of undulator to “just in time” with respect to schedule for x-ray flux measurement in July 2009 - ~ $3M BA released in FY2008 The risk handling plan reduces the available commissioning time CD-4 achievable on schedule (7/2010) Reduced performance in early operations
6
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Contingency available by year
7
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Handling Plan Delay installations to start of FY2009 Undulator Beam Dump Front End Enclosure >$3M moved out of FY2008 Just-in-time for AMO installation No FEL commissioning 10/2008-3/2009 Two-shift installation to reduce lost commissioning to recover commissioning time Decision Points for delay/go ahead: 12/2007 and thereafter
8
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Cost to Go, scheduled thru 2008
9
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Contingency Mgmt: X-ray speedups Speed up controls and stands for FEE (1000k) Speed up X-ray monitors in FEE (300k) Speed up NEH controls and motors (450k) Speed up XES laser system (340k) Speed up AMO focusing mirrors (115k) If more FY08 funds become available, one could:
10
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Schedule Highlights Early installation in new tunnels December 2007 LCLS Linac installation complete January 2008 Early start of Near Hall Operations 7/2009 End Station Systems delayed to preserve contingency in FY2008
11
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Commissioning Injector All performance goals for the LCLS injector have been met Gun laser - 98% availability in over 3,000 hours of operation in support of commissioning Some work left on BC1, x-band cavity Linac, BC2 Commissioning to begin in January Faulty magnet coil may delay BC2 commissioning Adequate commissioning time available in 2008
12
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Undulator vacuum chamber Al extrusion design Machining tests successful Dimensional tolerance met Internal polishing trials have yielded good results
13
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Undulator Magnetic Measurement 39 undulators are at SLAC. The MMF is in production mode 15 undulators tuned/fiducialized Girder/mover assembly underway at IL vendor Undulator quadrupole accepted Measurements indicate trim winding is compatible with beam-based alignment
14
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Photon Beam Systems XTOD and XES affected significantly by the 2007 CR New plan allows recovery with extended project, phased completion XTOD is in procurement phase, XES still in design Manpower in controls area has been increased Should be ready for early occupancy of expt’l areas Coordination with LUSI is going well
15
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Far Hall XTOD Status Procurements have begun Most design reviews are done Staying on new schedule LLNL team is working well with SLAC Award Low-Energy mirror PO 7-2007 Award High-Energy mirror PO 11-2007 First instrument ready to ship to SLAC 12-2007 Start FEE installation 8-2008
16
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Recent ESS organizational progress Added support in Controls/data acquisition Added G. Haller as CAM for controls/data handling effort for LCLS X-ray groups and for LUSI Shifting people from Accelerator to X-ray area as work progresses Developed integrated installation/commissioning plan Under leadership of R.M. Boyce Involves Accelerator, X-ray, Physics groups
17
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 CR caused delays Now in design phase AMO instrument design going well 2-d detector development going well Controls area was behind, catching up Working with Radiation Physics on PPS items XES Status
18
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 LUSI Project Instrument scientists on board Very successful DOE Conceptual Design Review CD1 approved Continuing Resolution affecting procurements LUSI-LCLS Interface Working Group recent business: Conventional facilities Details of hutch design, rack placement, etc. Controls/Data acquisition Details of data flow, storage, interface to detectors Precisely defining LUSI/LCLS interfaces
19
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Conventional Facilities Start-of-Installation Dates Schedule performance has been good Front End Enclosure DEC07 Central Utility Plant DEC07 Undulator Hall DEC07 Near Experimental Hall DEC07 Beam Dump DEC07 Beam Transfer DEC07 Xray/Diagnostics JAN08 Far Experimental Hall MAR08
20
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Construction Access, X-Ray Transport Tunnel
21
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Far Experiment Hall, Mid-Height Heading
22
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007
23
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Interim 2008 A Very important position to fill ASAP
24
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007
25
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Linac Operations Budget 2008 2/3 HEP – 1/3 BES in 2007 1/3 HEP – 2/3 BES ($65.5M) in 2008 3/3 BES ($96.7M) in 2009 Start LCLS transit to operations in 2008 for Commissioning team CF Laser Group Transit of ASD from PEP Operation to LCLS Operation Begins modestly in 2008 100% in 2009 Persis Drell, Transition Working Group have prepared for this transition throughout FY2007
26
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Instrument Commissioning Responsibility of LCLS & LUSI Instrument Scientists, Supported by Instrument Teams Work to achieve performance requirements for first approved experiments Likely to reach soft x-ray capability first First experiments scheduled thereafter Judicious balance: Operations time for experiments that are less demanding of FEL performance (photons/pulse, timing, pulse duration, etc) Commissioning time for FEL improvement
27
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 First Experiments Instruments will be operated by LCLS, in support of approved experiments “Facility” lasers operated/maintained by SLAC AMO and XR pump/probe available in 2009
28
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Summary Performance of LCLS Injector meets specification for 1.5 Angstrom SASE A long way to go Bunch Compression Undulator tuning and alignment Electron trajectory control Looking forward to seeing the first LCLS experimenters
29
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Summary LCLS Turn-on has gone superbly 2008 is a narrow passage for the Project to pass through Limited $ contingency Scope contingency identified Downstream to upstream 2009 first Near Hall Operations 2008 contingency control is crucial to this goal Revised ETC puts the Project back on track for successful completion LCLS Project organization will transform to LCLS operating organization I will do my utmost to get this transition right
30
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Charge to FAC Undulator system integration- FAC is asked to list risks, with emphasis on Girder setup and testing Vacuum system design OTHER THAN extrusion SLAC/ANL coordination Diagnostics Radiation protection
31
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Charge to FAC LUSI, Photon Systems integration- FAC is asked to list risks, with emphasis on schedule pressure due to Impacts of 2007 CR on LCLS Impacts of 2008 CR on LUSI
32
John N. Galayda LCLS Facility Advisory Committeegalayda@slac.stanford.edu 29 October 2007 Charge to FAC Controls, Data Acquisition and Applications software: identify risks with emphasis on High-speed data acquisition Schedule for development of data archiving Conventional Facilities Conditions at early occupancy Safety on the construction site Contingency burn rate SLAC, Turner Const. Co roles/responsibilities