Cost Until end 2000:negligible 2001:3 kDM per irrad  Problem –Cyclotron split in commercial and research part. Irradiation facility still a commercial.

Similar presentations


Presentation on theme: "Cost Until end 2000:negligible 2001:3 kDM per irrad  Problem –Cyclotron split in commercial and research part. Irradiation facility still a commercial."— Presentation transcript:

1 Cost Until end 2000:negligible 2001:3 kDM per irrad  Problem –Cyclotron split in commercial and research part. Irradiation facility still a commercial part  expensive. Future:From Oct.2001 beam line for irradiation in research division: 0.5 kDM per Irradiation –Negotiation ongoing; but needs clarifying of procedure (same procedure without changes) This is the main reason why we need full sensors NOW

2 Some facts Beam time is not an issue It looks like Rpoly can stand ~500V  Biasing by bonding is possible (add.manual bonder is always available)

3 More facts related to irrad Bulk damage are in principal not bias dependent, dependent of C, O and N content Full bias at p irrad does not match the LHC conditions: e.g. Very high currents (would maybe blow up the sensor (100mA)) Full bias does not shape the field in the oxide in the right way (surface damage)!

4 Simulated LHC conditions with respect to surface damage! Vbias

5 Procedure 4 sensors stacked plus 20 teststructures in one go (~15min) T= -10°C at beam Humidity: Flow of dry nitrogen For the next irradiation to finalize parameters: –Several different Vbias are planned –On full sensors 1V at backplane to build up field in oxide, with all AC pads to GND (approx. LHC condition) –On teststructures: Vbias= 0, 1, 10, 100V (AC shorted) –One teststructure with Vbias =100V and no shortening of AC. –One teststructure without bias and further X-rays up to 50kGy (nice to know: we have 160 Hamamatsu teststructures)

6 Schedule Pre-measurement of teststructures from ST and Hamamatsu (until June 6) Marcello try to get grade X from Hamamatsu (otherwise 1 of 400  m sensors) Take the worst ST full sensor (with respect to pinholes) Irradiation the week June 6

7 Cost during production 1% of sensors ~270  ~70 Irrad 5% TS  70 Irrad (incl. TS) 35kDM