GLAST I&T January 29 2004 T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up
2
GLAST I&T January 29 2004 T Borden 2 Outline Tracker Tower Mock-Up Test Fixtures Hardware Modifications Schedule Concerns Conclusions Mini Tower
3
GLAST I&T January 29 2004 T Borden 3 Tracker Tower Mock-Up Why have two Tracker mock-ups? One-mock up needed for I&T at a minimum Second mock-up (Tracker EM) can be used for Vibration test and I&T Identify multi Tower installation issues (pointing, alignment, clearance) Allows first mock-up to be available in early April for I&T EM Tracker available mid April, with help from INFN, for Vibration test then ship to SLAC for I&T Two Tracker Tower mock-up plan: EM Tower – Remove bottom tray from EM Tower in Italy and modify at SLAC – Reassemble EM Tower in Italy and vibration test at Alenia – Ship EM Tower to SLAC “New” Tracker mechanical model from prototype parts – Second EM Bottom Tray modified at SLAC – COI side walls at SLAC – Prototype trays at SLAC and INFN (need these shipped back to SLAC) – All other small parts available at SLAC
4
GLAST I&T January 29 2004 T Borden 4 Test Fixtures Drawings of Grid and Tracker – required to start 1 X 1 Grid fixture – For integration or Mini Tower? Updated interface for integration or use 1X4? Use for mini Tower 1 X 4 Grid – from Mechanical in flight configuration For integration testing? For Flight Tower testing? Alignment fixtures Purpose design? Both mock-ups can be used to align Towers All interface parts and fasteners – make set for I&T Lifting fixture – from Tracker or I&T?
5
GLAST I&T January 29 2004 T Borden 5 Hardware Modifications Bottom Tray modification Tooling 1 X 1 Top ring Mini Tower Support Track 1 X 4 completion for on time delivery
6
GLAST I&T January 29 2004 T Borden 6 Schedule Start February 2 nd See attached schedule Inputs needed Drawings from Tracker and Mechanical subsystems Parts from Tracker subsystem – Bottom Tray and inspection criteria for repair – Mid span flexures and bonding process – Sidewalls – Fasteners – Cables – Who supplies lifting fixture? Parts from Mechanical subsystem – 1 X 4 Grid Agreement on complete Tower test plan and fixtures
7
GLAST I&T January 29 2004 T Borden 7 Concerns Can Resources be made available in a timely manner, both workforce and funding No full time designer available until February 16th Can Tracker and Mechanical subsystems provide needed materials and support
8
GLAST I&T January 29 2004 T Borden 8 Conclusions Build up two Tracker mock-ups I&T mock-up for integration EM Tracker for vibration test and I&T needs
9
GLAST I&T January 29 2004 T Borden 9 Mini Tower Design Sidewalls and top tray simulator ring Flight Lifting fixture can be used Design and fabricate test stand parts as needed (need test stand requirements) Assemble Mini Tower with 5 th tray