UK Costs Beam & Infrastructure Coils Tracking Detector
2
Historical Cost Summary Vat: 17.5% Inflation 3% pa (from 2002) Contingency 30% on everything 2.3:1 Beam & Infrastructure Tracker detector Focus coils Decay Solenoid Replacement } UK bid
3
Historical Detail Raw Costs £k
4
B&I Cost Saving on Solenoid: –Decay Solenoid Replacement –£2M (raw)… in the budget for this £3.2M –How much do we need to keep? –Solenoid itself - £1M possible £1.5M saving £2.4M
5
Cost estimate for B&I £4.5 M £7.5M capital spend £0.8M Staff cost £1.1M £8.6M total – B&I Only –May not have always taken the cheapest option – some trimming to do Cooling plant costs Shielding costs Refine what we need to do for the solenoid £M - figures in blue – raw figures £M - figures in red include VAT, inflation & Contingency
6
…exclude PSI decay solenoid New target & decommissioning Beam line power supplies Beam Line Stands Shielding Refrigerator (£1M) etc..... Compressor building Civil work in hall Cooling plant room 500kW Chiller
7
other UK contributions estimate of the coils: –£1.7M + staff £2.8M + staff (£0.8M) estimate of the tracker & software development: –£0.74M + staff £1.2M + staff (£2.4M) estimate of the RF contribution: –£0.65M £1.1M –£0.4M for staff costs (installation) £0.53M ? Travel etc –£0.9M ~ 6 years Oversight – RAL project staff ~ 4 years –£1.1M ~ 2.5 SY/pa historical
8
Summary Total of ~£19.4M; (£15M w/o contingency) –further savings in cost of B&I £? –Savings on Tracker £? –Savings on Coils £? –In kind contribution for RF system £? –Scrutinise travel costs £? –Separation out of running costs £? –these “£?” Need to be quantified! –We have started to review our costs…. 14 th October MICE Project Board