Download presentation
Presentation is loading. Please wait.
1
Target: K. Long, 21Dec2009
2
Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel delivery expected 23 December To progress in January 2010: – Checking forces generated with mis-aligned coils using OPERA model (PS, TB) – Devising magnetic QA rig (GB + Shf) – Devising concept for winding coils that is more precise Schedule T3: – Machining of parts (except plastic) done – Coils for T3 prepared in Sheffield: » Will consider whether to use new coils or present coils based on: magnetic analysis; Magnetic QA on T2 stator
3
T3 schedule: – Now awaits completion and test of T2#3 Which is ready except for plastic bearing inserts and assembly Looks like this work will start in the New Year
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.