Download presentation
Presentation is loading. Please wait.
1
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module progress update Wing Lau – Oxford
2
A progress update: Interface scope and responsibility -- defined Interface control via a global reference system -- set up Feasibility study of using Cryo-Coolers -- started Detail design & engineering for module connection -- started Cost estimate and schedule of work -- prepared Response to Safety Review committee’s comments -- drafted Draft Re-baseline document -- prepared R & D issues Window measurement and burst tests KEK Absorber cryostat and mechanical seal tests Welded window tests Detail engineering: Cold Mass support design Coil support tube design
3
SupplierResponsible equip. Scope of supply Oxford / RAL Focus Coil & Module magnet coil, cold leads, cold mass supports, cryostat, radiation shields, helium cooling pipe to the coil, warm bore tube, warm vessel, connecting flange for the Large End Plate and the RHS Safety window (both NIU/IIT supply), entrance nozzles for LH2 & GHe feed pipes. Vessel supports KEK Absorber body & feed pipes Absorber body, facing flange for the windows, bolts and mechanical seals for all the window connection, all the LH2 and GHe feed pipes, support connection for the Absorber body, LH2 spillage sump NIU / IIT Windows and Large End Plate The Absorber and Safety windows, The Large End Plate with mechanical seal and fixing bolts, anchoring arrangement for the Large End Plate, any temporary protection to the thin window during assembly. LBL Bolting & Sealing of Focus & Coupling Coil vessels The design and supply of the flexible flange for sealing between the two vessels. The design & supply of any item that transmit the magnet forces from one vessel to the other. Interface scope & responsibility The total supply of the AFC module falls into the following categories:
4
Oxford / RAL supply
5
SupplierResponsible equip. Scope of supply Oxford / RAL Focus Coil & Module magnet coil, cold leads, cold mass supports, cryostat, radiation shields, helium cooling pipe to the coil, warm bore tube, warm vessel, connecting flange for the Large End Plate and the RHS Safety window (both NIU/IIT supply), entrance nozzles for LH2 & GHe feed pipes. Vessel supports KEK Absorber body & feed pipes Absorber body, facing flange for the windows, bolts and mechanical seals for all the window connection, all the LH2 and GHe feed pipes, support connection for the Absorber body, LH2 spillage sump NIU / IIT Windows and Large End Plate The Absorber and Safety windows, The Large End Plate with mechanical seal and fixing bolts, anchoring arrangement for the Large End Plate, any temporary protection to the thin window during assembly. LBL Bolting & Sealing of Focus & Coupling Coil vessels The design and supply of the flexible flange for sealing between the two vessels. The design & supply of any item that transmit the magnet forces from one vessel to the other. Interface scope & responsibility The total supply of the AFC module falls into the following categories:
6
KEK supply
7
SupplierResponsible equip. Scope of supply Oxford / RAL Focus Coil & Module magnet coil, cold leads, cold mass supports, cryostat, radiation shields, helium cooling pipe to the coil, warm bore tube, warm vessel, connecting flange for the Large End Plate and the RHS Safety window (both NIU/IIT supply), entrance nozzles for LH2 & GHe feed pipes. Vessel supports KEK Absorber body & feed pipes Absorber body, facing flange for the windows, bolts and mechanical seals for all the window connection, all the LH2 and GHe feed pipes, support connection for the Absorber body, LH2 spillage sump NIU / IIT Windows and Large End Plate The Absorber and Safety windows, The Large End Plate with mechanical seal and fixing bolts, anchoring arrangement for the Large End Plate, any temporary protection to the thin window during assembly. LBL Bolting & Sealing of Focus & Coupling Coil vessels The design and supply of the flexible flange for sealing between the two vessels. The design & supply of any item that transmit the magnet forces from one vessel to the other. Interface scope & responsibility The total supply of the AFC module falls into the following categories:
8
NIU / IIT supply
9
SupplierResponsible equip. Scope of supply Oxford / RAL Focus Coil & Module magnet coil, cold leads, cold mass supports, cryostat, radiation shields, helium cooling pipe to the coil, warm bore tube, warm vessel, connecting flange for the Large End Plate and the RHS Safety window (both NIU/IIT supply), entrance nozzles for LH2 & GHe feed pipes. Vessel supports KEK Absorber body & feed pipes Absorber body, facing flange for the windows, bolts and mechanical seals for all the window connection, all the LH2 and GHe feed pipes, support connection for the Absorber body, LH2 spillage sump NIU / IIT Windows and Large End Plate The Absorber and Safety windows, The Large End Plate with mechanical seal and fixing bolts, anchoring arrangement for the Large End Plate, any temporary protection to the thin window during assembly. LBL Bolting & Sealing of Focus & Coupling Coil vessels The design and supply of the flexible flange for sealing between the two vessels. The design & supply of any item that transmit the magnet forces from one vessel to the other. Interface scope & responsibility The total supply of the AFC module falls into the following categories:
10
NIU / IIT supplyKEK supplyOxford / RAL supply
11
Space envelop for the suppliers
12
Distinguishing between a stand-alone item and an interfacing item through drawing convention Stand alone items – in black, blue & red Interface items – those marked in Pink. In the MICE project, the Pink parts will have a different drawing convention. Any changes made will be notified to all the related interface suppliers for consent.
13
Interface control via a global reference system -- introducing the Coat hanger technique The conventional way of assembling the different parts together is by attaching the adjoining parts to a common interface boundary. Where there are multiple interfaces, or where one part joins onto another part and another part and so forth, it would be difficult to define the order of interface. It would also accumulate errors as parts are assembles related to each other only locally and not globally. This makes the checking of interface compatibility extremely difficult.
14
The Coat Hanger technique (continue) The conventional way of assembling the different parts together is by attaching the adjoining parts to a common interface boundary. Where there are multiple interfaces, or where one part joins onto another part and another part and so forth, it would be difficult to define the order of interface. It would also accumulate errors as parts are assembles related to each other only locally and not globally. This makes the checking of interface compatibility extremely difficult. The way to overcome this is to avoid having to assemble parts onto each other. In this new concept, every parts will have a reference centre which coincides with one of the globally registered centres designed to position the magnet modules relatively to the beam line and then to the experimental hall. This reference centre acts like a coat hanger
15
The Coat Hanger technique (continue) The conventional way of assembling the different parts together is by attaching the adjoining parts to a common interface boundary. Where there are multiple interfaces, or where one part joins onto another part and another part and so forth, it would be difficult to define the order of interface. It would also accumulate errors as parts are assembles related to each other only locally and not globally. This makes the checking of interface compatibility extremely difficult. The way to overcome this is to avoid having to assemble parts onto each other. In this new concept, every parts will have a reference centre which coincides with one of the globally registered centres designed to position the magnet modules relatively to the beam line and then to the experimental hall. This reference centre acts like a coat hanger The referencing system works like a global navigation system. Through the reference centres, we can refer the position of each parts to a global coordinate. By hanging the various parts to a globally registered centre, it will automatically assemble the parts to a pre-defined position. Any interface incompatibility will be easily detected as each equipment / parts will have its unique place in the global coordinate system. No two parts should have the same coordinates. We will insist on this centre being retained on all the stand alone and interface drawings.
16
This is how it works on MICE: There are different levels of reference centre, designated to have a similar “level” allocation as the WB packages. The level 1 reference centre is the centre of the experimental hall; The level 2 reference centres are those along the beam line centre for the positioning of each of the modules; The level 3 reference centres are the centres of the individual modules As an example:- The Focus Coil module will have a level 3 reference centre. All the parts associated with the windows and the absorber will be referenced to this level 3 reference centre. The Focus Coil modules, the Coupling Coil, the detector modules and any equipment that are aligned to the beam centre line will be referenced to the level 2 reference centre. The beam line centres will be referenced to the level 1 reference centre etc.
17
These parts will have level 3 reference centre attached The level 3 reference centre on the FC module
18
All the AFC parts will then be hung to the level 3 reference centre at the Focus Coil
31
The hanging of the AFC and Coupling modules
32
Level 2 reference centres Level 3 reference centres
39
Interface compatibility check at a glance
40
Feasibility study of using Cryo- Coolers on the AFC module
41
The kind of a cooler that can be used to cool MICE magnets and absorbers From a practical standpoint the Sumitomo SDRK-415-D GM cooler (1.5 W at 4.2 K) is our the main choice to cool the MICE magnets. A pulse tube cooler from Cryomech is a distant second choice. A two-stage cooler is needed to cool superconducting magnets. A first stage at 40 to 70 K cools the magnet shield, the cold mass support intercepts and the upper leads. The second stage (at 4 K) cools the coils and removes the heat coming down the HTS leads from the first stage. A closed cycle cooler can not be a source of helium gas that can be used to cool gas cooled leads. Both the HTS leads and upper current leads must be conduction cooled. 300 K Attachment Ring Cryocooler First Stage T = 25 K to T = 80 K Cryocooler Second Stage T = 2.5 K to T = 20 K The Sumitomo SDRK 415-D GM Cooler
42
Cooling the Focusing magnet with a coolers One CoolerTwo Coolers First Stage of Cooler MLI Radiation Heat Leak per Cooler (W) 4.82.4 Cold Mass Support Heat Leak per Cooler (W) 3.01.5 Plumbing Heat Leak per Cooler (W) 1.00.5 Instrumentation Heat Leak per Cooler (W) 0.60.3 Current Lead Heat Load per Cooler (W) 42.021.0 Total Heat Load to 1st Stage per Cooler (W) 51.425.7 First Stage Temperature (K) ~63~40 Second Stage of Cooler MLI Radiation Heat Leak per Cooler (W) 0.450.18 Cold Mass Support Heat Leak per Cooler (W) 0.150.06 Plumbing Heat Leak per Cooler (W) 0.250.1 Instrumentation Heat Leak per Cooler (W) 0.120.05 Current Lead Heat Load per Cooler (W) ~0.9~0.3 Total Heat Load to 2nd Stage per Cooler (W) ~1.87~0.69 2nd Stage Temperature (K) > 4.6> 3.5
43
Cooler Connection through a Flexible Strap The temperature drop from the load to the cold head is proportional to the strap length and inversely proportional to the strap area and the strap thermal conductivity. T c = contact resistance T c is usually small. T = T3 - T0
44
Straight Conduction cooling arrangement of the cryocooler
45
Cooler Connection through a Heat Pipe The temperature drop from the load to the cold head is independent of the distance between the load and the cooler cold head. T b = Boiling T Drop T f = Condensing T Drop T c = Contact Resistance These can be made small. T = T3 - T0
46
Adapting a “heat pipe” arrangement for the CryoCooler in the AFC magnet cooling
47
Design & engineering of module connection Several connection schemes have been looked at to simplify the way the outer vessels of each modules are connected. The original thinking was to provide each connection with two “independent” joints; a flexible joint to ensure leak tightness, and a rigid connection to transmit the magnet forces from one to the other. Here are the different schemes being looked at:
48
Design options in the vessel connection Option 1
49
Design options in the vessel connection Bellow type joint Option 2
50
Design options in the vessel connection Concertina type joint Option 3
51
Likely changes in the vessel connection design The original thinking on connecting the vessels was to provide each connection with two “independent” joints; a flexible joint to ensure leak tightness, and a rigid connection to transmit the magnet forces from one to the other. Two things happened since, and they might have a significant effect on the vessel connection design.
52
Likely changes in the vessel connection design The original thinking on connecting the vessels was to provide each connection with two “independent” joints; a flexible joint to ensure leak tightness, and a rigid connection to transmit the magnet forces from one to the other. Two things happened since, and they might have a significant effect on the vessel connection design. The ability to adjust the coil position to fiducially out on the vessel via the new Cold Mass support design means there are now less misalignments for the flexible joint to take up.
53
General Arrangement of the cold mass support system This means the coils can be aligned independently of the vessel position
54
Integrated Tensioning Device/ Anchor on warm vessel End Cap welded to form a vacuum tight joint.
55
Likely changes in the vessel connection design The original thinking on connecting the vessels was to provide each connection with two “independent” joints; a flexible joint to ensure leak tightness, and a rigid connection to transmit the magnet forces from one to the other. Two things happened since, and they might have a significant effect on the vessel connection design. The ability to adjust the coil position to fiducially out on the vessel via the new Cold Mass support design means there are now less misalignments for the flexible joint to take up. The possible reduction in the magnet forces – due to the re-arrangement of the coil positions, Mike Green now believes that the magnet out-of-balance force have been reduced dramatically. It is now feasible to pass these magnet forces to floor via the supports, instead of from module to module. This would mean the elimination of the rigid connection between each module, leaving just a flexible joint for leak tightness.
56
Magnet force in the previous coil arrangement mainly caused by a separation between focus coil and 1 st matching coil of 200 mm Magnet force in the revised coil arrangement mainly caused by a separation between focus coil and 1st matching coil of 600 mm
57
Imbalanced magnet forces Passing the load to the floor
59
Cost estimate & schedule of work – with in-house built
60
Cost estimate & schedule of work – without in-house built
65
Response to Safety Review committee’s comments There are two areas which need further information:- Once these are received, the report will be by the group before it is released for issue. Response to the Safety Review comments ~ draft copy ~ A draft report on our point by point response to the questions raised by the Safety Review Committee has been prepared Clarification + diagram on Hydrogen Safety system Detail descriptions of the Control system
66
Re-baseline document The re-baseline document is 90% complete. The following information is still outstanding: Detail description of the C&I design and arrangement Product details / category of the control instruments applicable in the AFC module Work schedule of the Window test and supply Work schedule of the Absorber body, mechanical seal and other relevant equipment The re- formatting of the Word document as it is nor readable by some Word browsers Re-baseline document on the AFC Module
67
R & D issues Window measurement and burst tests KEK Absorber cryostat and mechanical seal tests Both talks will be covered by Ed Black later Welded Window test Status of test vessels: 1st vessel is waiting to have the threaded bayonet milling. 2nd vessel is having the vacuum and pressure port machined, then milling of the threaded bayonets will be done -- next week. Welding test samples are machined & ready
68
Thermocouple
70
Detail engineering: Cold Mass support design The design is in an advanced stage and details of it will be covered in Rohan’s talk Coil support tube design Both the thermal and stress analyses have now completed. This will be explained in Stephanie’s talk
71
Summary The basic project infrastructure of the work packages within the AFC module is now in an advance stage. We still need further effort in the C&I area which has not been receiving the level of support that we expected The use of Cryo-Cooler is looking promising and further effort is needed to make sure that Safety of the system is not compromised. Following the reduction in the imbalance magnet force, as a result of repositioning the detector coils, it is now feasible to “pass” the magnet forces to the individual module support legs. If proven, this will simplify our module to module connection greatly. Work will continue to ensure that there is no other show The R&D work is progressing, albeit a little slower than planned. Interface with the detector module supplier is progressing and further effort is needed to bring this to a reasonable stage where detail engineering work can start.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.