1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa
2
2 Installation of FECs and Backplanes Jan ’05 - Mar ’06 electrical and functional test of each FEC test of the connection between FECs and pad plane test of the connection between FECs and readout backplane PHASE I Installation of RCUsMay – Aug ’06 Comprehensive test of all (216) readout partitions: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required) PHASE III Characterization of the whole system with RCUsMar – May ’06 Characterization of 1 readout partition at a time: noise, gain, width, baseline, time offset, temperature, voltages and currents PHASE II Electronics Installation and Commissioning Schedule
3
3 FE Cards Installation 1/2 Organization and schedule 2 installation crews (3 people / crew) Installation started on the 30 th January Installation rate: ~ 1 sector / day Status Installation of FECs completed (on March 15), with exception of 1 sector on C side Installation of Readout &Control backplanes completed by end of March, with exception of 1 sector on C side The electronics of 1 sector (A09), equipped with the LV bus rods and cooling, was characterized (pedestals, noise, gain) The electronics of sector A08 is under test
4
4 Measurement of VCC A, VCC D, I A, I D and T Measurement of the FEC Identifier FE Cards Installation 2/2 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) U2F Card Readout of trigger related data (pulser) Connection to the pad plane
5
5 FE Cards Installation highlights
6
6 TPC A Side (17 th February ’06)
7
7 Characterization of Sector A09 Sector A09 equipped with backplanes cooling circuit LV power rods LV PS + cables (4 x 40m) Sector A09 equipped with backplanes cooling circuit LV power rods LV PS + cables (4 x 40m)
8
8 sum of charges sum of charges, pad row 46 baseline noise rms (ADC counts) Characterization of Sector A09 - IROC
9
9 sum of samples baseline rms Characterization of Sector A09 - IROC baseline (PASA noise 2 + ADC noise 2 ) = 0.70 ADC counts
10
10 sum of chargessum of charges, pad row 11 Characterization of Sector A09 - OROC baseline noise rms (ADC counts)
11
11 sum of samples Characterization of Sector A09 - OROC baseline rms sum of samples
12
12 Power Regulators RCU status and plans … Readout Control Unit 1/2 DCS CARD SIU CARD
13
13 Readout Control Unit 2/2 Mass Production (240 units including 10% spares) completed November ‘05 Mass Test completed December ’05 Delivery of tested DCS cards Mar ‘06 Delivery of tested SIU cards (DAQ project): 1 st lot (108 units)Mar ’06 2 nd lot (108 units)May ‘06 Assembly and final test of RCU + SIU + DCS: Apr – Jun ‘06 Installation and commissioning of RCUs: May – Aug ‘06 Production, test, installation and commissioning
14
14 Preparing for Commissioning Phase III RCU Lab - setup I Final assembly and test of RCU + SIU + DCS 25 FECs (readout partition) + Backplane + RCU 1 DAQ PC (PCALD23) + single-channel RORC 1 DCS PC (local network DHCP server, DIM Server) + Ethernet Switch Local Trigger Crate (SBC, LTU, TTvi, TTCex) + TTCoc RCU Lab - setup II TPC FEE + DAQ + HLT Integration 2 x Readout Partitions 1 DAQ PC (EPAITBEAM02) + dual-channel RORC 1 HLT PC + 1 HRORC P2 SXL2 – Test of the electronics, 1 Sector at a time 1 x Readout Partition 1 DAQ PC (ALDAQPC021) + dual-channel RORC
15
15 Conclusions Installation of FECs almost complete (97% done) The complete electronic chain of one TPC sector has been characterized gain, baseline and noise distributions well within specifications Installation of backplanes was completed by Mar ’06 Installation and commissioning of RCUs in May - Aug ‘06