Presentation is loading. Please wait.

Presentation is loading. Please wait.

Push and Pull Systems: Lecture 12

Similar presentations


Presentation on theme: "Push and Pull Systems: Lecture 12"— Presentation transcript:

1 Push and Pull Systems: Lecture 12
MRP and push systems Kanban and CONWIP Push and pull

2 MRP and Push Systems Demands for chairs are given as follows
Week chair How do we schedule the production, given its BOM? chair frame 4 legs seat

3 Information Part Chair Leg Seat Frame On-hand 340 900 300 500
Leadtime Lot size L4L Safety stock

4 MRP Mechanism week 1 2 3 4 5 6 Chair (340) 200 250 220 300 500
250 220 300 500 Net demand 110 Leg (900) 440 880 1200 2000 order 800 1020 Seat (300) 400 480 Frame (400) Netting demands Offsetting leadtimes

5 MRP Record for the Leg week 1 2 3 4 5 6 7 8 MRP record for the Leg 440
Gross Requirements 440 880 1200 2000 800 1880 360 Scheduled. Receipt Project balance (900) 460 380 200 Planned order release 1020 LS = 800, LT = 1 week, SS = 200

6 MRP Record for the Seat week 1 2 3 4 5 6 7 8 110 220 300 500 200 470
Gross Requirements 110 220 300 500 200 470 90 Scheduled. Receipt Project balance (300) 190 370 70 50 250 350 280 Planned order release 400 480 LS = 400, LT = 1 weeks, SS = 50

7 MRP Record for the Frame
week 1 2 3 4 5 6 7 8 Gross Requirements 110 220 300 500 200 470 90 Scheduled. Receipt 400 Project balance (100) 390 170 270 370 310 Planned order release LS = 400, LT = 2 weeks, SS = 100

8 MRP Terms Gross requirement is the anticipated future usage during a period Scheduled receipt is order placed before and will arrive at the beginning of a period Projected available balance is the inventory status at the end  of a period Planned order release is order to be released at the beginning of a period Net demand of the end product is the amount that should be available at the beginning of the period

9 Connecting Records Now that each frame needs 4 rivets to put together. For rivets, leadtime= 1 wk, safety stock = 400, lot size = Current on-hand is 412 chair frame 4 legs seat rivet (4)

10 frame/week 1 2 3 4 5 6 7 8 Gross Requirements 110 220 300 500 200 470 90 Scheduled. Receipt 400 Project balance (100) 390 170 270 370 310 Planned order release MRP record for rivet Gross Requirements Scheduled. Receipt 1600 Balance (412) Planned order release LS=1600, LT=1, SS=400

11 Rolling-Horizon: Week 1
2 3 4 5 6 7 8 9 10 11 25 36 27 26 28 30

12 At the Beginning of Week 2
1 2 3 4 5 6 7 8 9 10 11 25 36 27 26 28 30 23

13 At the Beginning of Week 3
1 2 3 4 5 6 7 8 9 10 11 25 36 27 26 28 30 23 31

14 At the Beginning of Week 4
1 2 3 4 5 6 7 8 9 10 11 25 36 27 26 28 30 23 31

15 Exercise 1 Fill the following MRP table week . Part A 1 2 3 4 5 6 .
Gross req Scheduled rec Project available balance (21) Planned order release Q=20; LT=1; SS=0 During week 1, the following occur: find 12 additional units in inventory; actual requirement is 15 units; wk 3 and wk 4 requirements reduced to 16 and increased to 14, respectively; wk 7 requirement is 15

16 Exercise 1 Continues Fill the following MRP table week .
Part A Gross req Scheduled rec Project available balance ( ) Planned order release Q=20; LT=1; SS=0 During week 1, the following occur: find 12 additional units in inventory; actual requirement is 15 units; wk 3 and wk 4 requirements reduced to 16 and increased to 14, respectively; wk 7 requirement is 15

17 MRP Based Control Forecast demand generate time phased plans
Planned orders FG demand machine buffer Parts

18 Push Production Systems
Forecast or anticipate demand Translate forecasts into production plan Convert production plan into schedules of lower level components in a top-down fashion Executing schedules in a bottom-up fashion

19 Comments on MRP MRP started a new way for factory management and is one of the most important manufacturing management paradigms MRP process can be easily computerized, this led to the earliest MRP system by an IBM team led by Orlicky MRP was the first major industry application of computer and has been the core (engine) of the information backbone systems MRP logic is flawed. The fundamental weakness is the constant leadtime assumption, which amounts to the assumption of infinite processing capacity and no uncertainty in the system

20 MRPII: A Push Planning Framework
Figure 1 Low level planning BOM. Routing Inventory Status Execution

21 Kanban and CONWIP Toyota production system
Continuous improvement Smooth production Eliminate wastes How do we create a smooth (stable) production flow so that production matches demand and wastes in production process are minimized?

22 Kanban Control Scheme Kanban control ensures that parts are not made except in response to a demand. FG machine buffer Parts Kanban

23 Dealing with Interruptions
Don’t produce defect Don’t pass defect Don’t accept defect FG machine buffer Parts Kanbans

24 Kanban Calculus (1) Work Station
throughput rate Work Station A single server queue with a base stock control policy

25 CT-100 Assembly (service rate )
Example CT-100 Kanban System. Orders arrive 250 per month on average, and assembly capacity is averaged 300 per month. Suppose that a Kanban system is used to produce CT Determine total number of Kanbans allowed in the system, given a Kanban safety factor of 0.2 and container size of 5. Estimated flow time = 0.2 months CT-100 Assembly (service rate ) throughput demand

26 CONWIP Constant work in process
Keep a fixed level of WIP (CONWIP). One finished part triggers a new part released to the first machine. FG machine buffer Parts Cards

27 Card Count in CONWIP Stable line speed and WIP level
Characterize the line with - Practical production rate, RP - Minimum practical leadtime, TP By Little’s law, the CONWIP level IC is IC= RPTP (2) TP includes all (reasonable) detractors include setups, failures, etc.

28 Kanban Versus CONWIP CONWIP Kanban
MPS generates a backlog in front of a line backlog can be sequenced a card releases the first job to the line requires a stable volume but can tolerate more of the product mix changes-- shifting bottleneck Kanban card for each station and part number requires a stable product mix and volume

29 Variations of CONWIP Tandem CONWIP: a long line separated to two or more sections CONWIP with shared resource: two CONWIP controlled lines share a common machine Pull from bottleneck: for a line with a stable bottleneck, control only the upstream section from the bottleneck

30 Push and Pull Push demands Pull Push: schedules the release of works based on (forecasted) external demands Pull: authorizes the release of work based on system status

31 CONWIP and MRP: Observability
Control throughput and observe WIP demand --- throughput fluctuation --- congestion Control WIP and observe throughput Observability - WIP is easy to observe and easy to control - TH is tied with capacity, when effective capacity changes, it is hard to control

32 CONWIP and MRP: Efficiency
For a given level of throughput, a push system will have more WIP than an equivalent CONWIP A CONWIP system can be modeled as a closed queueing network in which the number of customers is a constant A MRP control system can be approximately seen as an open queueing network in which each machine has fixed workload

33 Efficiency Example A line with 5 identical exponential single-machine stations with µ=1 job/hour For CONWIP control with a fixed w (WIP): Throughput rate TH = w µ /(5/µ+ w – 1)=w/(4+w) For MRP, no control after release. The line behaves like 5 independent stations ρ = TH/ µ for every station The total

34 Hierarchical Planning in a Pull System
Marketing Parameters FORECASTING Product/Process Parameters CAPACITY/FACILITY PLANNING WORKFORCE PLANNING Labor Policies Capacity Plan Personnel Plan AGGREGATE PLANNING Aggregate Plan Strategy WIP/QUOTA SETTING Customer Demands Master Production Schedule DEMAND MANAGEMENT WIP Position SEQUENCING & SCHEDULING Tactics REAL-TIME SIMULATION Work Schedule Work Forecast SHOP FLOOR CONTROL Control PRODUCTION TRACKING

35 Push and Pull in Supply Chains
Extend the idea of pull beyond production control to supply chain: produce or make product available only when demand is received Make-to-order instead of make-to-stock The overall leadtime is often too long under the current competitive environment Assemble-to-order make-to-stock for some upstream supply chain and make-to-order for the lower stream supply chain

36 A Hybrid Push-Pull System
supermarket suppliers Item 1 Inbound Logistics (pull/push) Assembly (pull/push) delivery Item n Mixed Layout in Supermarket Manufacturing

37 Today’s Takeaways MRP is an important manufacturing paradigm and provides the basis for push systems Kanban and CONWIP are pull control with a theoretical basis in queueing theory, i.e., equations (1) and (2) Push schedule job release while pull control the workload, and is more efficient and robust MRP is easily computerized


Download ppt "Push and Pull Systems: Lecture 12"

Similar presentations


Ads by Google