Download presentation
Published byConstance Moore Modified over 9 years ago
1
Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening)
4/17/ :55 AM
2
Reasons to Reduce Project Durations:
To realize incentive pay To fit within the contractually required time (influences Bid price). To avoid paying Liquated Damages/Damage for delay causes (or avoid damaging the company’s relationship). To complete a project early & move on to another project (Although the Job-specify profit may reduce, company profile may increase). To complete a project when weather conditions make it less expensive (Avoid temporary Heating, avoid completing site work during raining season). Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
3
Methods to reduce durations:
Have the existing crew work overtime. This increase the labor costs due to increase pay rate and decrease productivity. Bring in additional workers to enlarge crew size. This increases labor costs due to overcrowding and poor learning curve. Use better/more advanced equipment. This will usually increase costs due to rental and transport fees. If labor costs (per unit) are reduced, this could reduce costs. Add subcontracted labor to the activity. This almost always increases the cost of an activity unless the subcontracted labor is for more efficient. Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
4
Project Costs Definitions
Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
5
Practices to Estimate the Project cost
Some company assigns Overhead office as % of direct cost. Most companies don’t consider profit as a cost of the job. Instead, analysis are completed by using Direct costs + Indirect costs + Company overhead vs. Budgeted (estimated costs). Similar to each activity, the project as a whole has an ideal (Lease expensive) Duration. Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
6
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
7
Accelerating the Critical and Noncritical path
Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
8
Network Compression Algorithm
Determine Normal project duration, and cost. Identify Normal duration Critical Path. For large network, using CRITICALITY THEORM to eliminate the noncritical paths that do not need to be crashed. Compute the cost slop : Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
9
Network Compression Algorithm
shortening the CRITICAL ACTIVITIES beginning with the activity having the lowest cost-slope Determine the compression limit (Nil) Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
10
Network Compression Algorithm
Organize the data as in the following table: Update the project network Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
11
Network Compression Algorithm
When a new Critical path is formed: Shorten the combination of activity which Falls on Both Critical Paths, OR Shorten one activity from each of the critical paths. Use the combined cost of shortening both activities when determining if it is cost effective to shorten the project. At each shortening cycle, compute the new project duration and project cost Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
12
Network Compression Algorithm
Continue until no further shortening is possible Tabulate and Plot the Indirect project Cost on the same time-cost graph Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
13
Network Compression Algorithm
Add direct and indirect cost to find the project cost at each duration. Use the total project cost-time curve to find the optimum time. Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
14
cost for expediting the contract . um
Example 1: The durations and direct costs for each activity in the network of a small construction contract under both normal and crash condition are given in below Tabl e. Establish the least cost for expediting the contract . Determine the optim um duration of the contract assuming the indirect cost amounts to SR 125/week. Normal Crash Activity Preceded by Duration (weeks) Cost ( ) A — 12 7000 10 7200 B 8 5000 6 5300 C 15 4000 4600 D 23 E 5 1000 4 1050 F 3000 3300 G E,C 20 6000 6300 H 13 2500 11 2580 I , G, H 3140 å 36 , 500 38470 Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
15
12 A 27 5 32 29 2 34 F 15 C 8 20 14 22 B 23 43 24 4 47 D 25 E G 59 I 13 45 H ES L S LF Activity Crash limit Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
16
2@70 Cycle # Activity to Shorten Can Be Shortened Nil Days Cost per
12 A 27 5 32 F 15 C 8 20 14 2 22 B 23 43 45 D 25 E 18 G 57 55 I 13 H ES L S LF Activity Crash limit Cycle # Activity to Shorten Can Be Shortened Nil Days Cost per Week Cost for Total Cost Project Duration - 36 , 500 59 1 G 5 2 60 120 620 57 I 70 140 760 55 Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
17
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
18
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
19
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
20
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
21
Project Optimal Duration
Spring 2008, King Saud University Time-Cost-Trade-off Dr. Khalid Al-Gahtani
22
Spring 2008, King Saud University
Time-Cost-Trade-off Dr. Khalid Al-Gahtani
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.