South Kitsap School District High School Stadium Project June-August 2015 Tom O’Brien Facilities Director May 19, 2015 "The strength of the pack is the.

Similar presentations


Presentation on theme: "South Kitsap School District High School Stadium Project June-August 2015 Tom O’Brien Facilities Director May 19, 2015 "The strength of the pack is the."— Presentation transcript:

1 South Kitsap School District High School Stadium Project June-August 2015 Tom O’Brien Facilities Director May 19, 2015 "The strength of the pack is the wolf......and the strength of the wolf is the pack."

2 Project Scope Synthetic Turf Field Installation Soccer Football Track and Field Events Band Physical Education Program Community Use

3 Project Scope 400 Meter Running Track Restoration Track “D” Area Apron Long and Triple Jump High Jump and Pole Vault

4

5 Project Approach Fast Track Line Item Pricing Using a National Buying Cooperative (NJPA – National Joint Powers Alliance) Design/Build Project Strategy

6 Project Team Owner: South Kitsap School District Contract: National Joint Powers Alliance (NJPA) Design Engineer: AHBL Tacoma, WA General Contractor: Hellas Construction, Austin, TX

7 Hellas Business Model Vertical Integration Leading to Total Project Control Fiber Manufacturing in Alabama Turf Manufacturing in Georgia Coating Manufacturing in Texas Project Sales and Design all in-house Construction using Hellas crews

8 Project Priorities Safety Field Performance and Playability Sustainability

9 New exclusive formulas Sustainable manufacturing process Non petroleum based products No solvents, heavy metals, mercury or other toxic materials EPIQ S-200 Track Resurfacing

10 Monofilament fibers in two different shapes and colors. This provides: Temperature reduction Superior traction Minimal infill splashing Increased longevity System stability Excellent light deflection Matrix Turf Fiber

11 Permanently paved in place 30 years of safety Retains shock absorption over the years Flexible & Resilient Improved Drainage Truer Planarity Recycled Materials Cushdrain

12 100% organic coconut fibers and cork 100% recycled materials Cooler infill alternative Attracts and retains ambient moisture 40º F cooler than that of traditional crumb rubber infill systems

13

14 Why Geo-Plus for South Kitsap? SAFETY Excellent GMAX Fewer Head Injuries/Concussions Better Than Natural Turf and Most Rubber Fields Better Foot Stability Than Crumb Rubber Rivals Natural Turf in this Safety Category Reduces ACL Injuries, High Ankle Sprains and Turf Toe

15 100% Organic, Natural Product o Odor Free o Recyclable Prevents Environmental Damage caused by leaching into water runoff Allows SKSD to sidestep the Crumb Rubber “Issue” Why Geo-Plus for South Kitsap? SUSTAINABILITY

16 Flour Bluff ISD in Corpus Christi, TX ecstatic about field performance FIFA-2 Certification for sister fields in NE and CA Provides the first ever all weather, year round playing venue in South Kitsap Will reduce “stress” caused by overuse on our natural turf playing surfaces. Why Geo-Plus for South Kitsap? PLAYABILITY

17 Project Cost Field:$1,275,157 Track:$ 137,350 WSST:$ 122,888 Total:$1,535,395

18 Project Partners are the Key to our success Opportunity presents itself as a door to a new level of success. One can knock and knock and never get past the obstacle. Only with the proper key can we open the door to new opportunities. Our community partners have been that key, taking us to places we never thought possible. Thank you for opening the door! "The strength of the pack is the wolf......and the strength of the wolf is the pack."

19 Project Partners Our partners made this project possible. South Kitsap School District thanks Kitsap Bank and the Macomber family. Macomber Family- Wayne, Ted, Debbie, Jody, (Jenny) Adele

20 Helen Langer Smith Vice-Chairman of the Board South Kitsap High School Class of 1946 Steve Politakis Chief Executive Officer Tony George President & Chief Operating Officer

21 Kitsap County Bank Established in 1908 at the corner of Bay and Frederick Streets in Port Orchard. Now 20 locations in six counties and nearly $1 billion in assets, Kitsap Bank employs over 250 people—including many South Kitsap Alum!

22 Macomber Family Dale was a member of the track team while at South Kitsap High School, lettering all four years.

23 Macomber Family It means so much to know that we can help fuel this passion in future generations of South Kitsap Students.

24 Project Timeline May 15 Engineering Design Completed May 19 School Board Presentation June 3Purchase Order/Notice to Proceed June 15Construction Start Date July 15Subsurface/Drain System Complete July 31E-layer and Track Complete/Turf Installation Begins Aug 31Substantial Completion Sept 4First Home Varsity Football Game

25 Kitsap Bank Stadium opening September, 2015