Chapter 3: The Project Management Process Groups: A Case Study

Similar presentations


Presentation on theme: "Chapter 3: The Project Management Process Groups: A Case Study"— Presentation transcript:

1 Chapter 3: The Project Management Process Groups: A Case Study
Information Technology Project Management, Sixth Edition Note: See the text itself for full citations.

2 Learning Objectives Describe the five project management (PM) process groups, the typical level of activity for each, and the interactions among them Understand how the PM process groups relate to the PM knowledge areas Discuss how organizations develop information technology PM methodologies to meet their needs Information Technology Project Management, Sixth Edition

3 Learning Objectives (continued)
Review a case study of an organization applying the project management process groups to manage an information technology project; describe outputs of each process group; and understand the contribution that effective project initiating, planning, executing, monitoring and controlling, and closing make to project success Information Technology Project Management, Sixth Edition

4 Project Management (PM) Process Groups
Project management can be viewed as a number of interlinked processes A process is a series of actions directed toward a particular result The project management process groups include: Initiating processes Planning processes Executing processes Monitoring and controlling processes Closing processes Process groups can be applied to each phase of the project or to the entire project Information Technology Project Management, Sixth Edition

5 Process Groups and Project Phases
Information Technology Project Management, Sixth Edition

6 Initiating processes Defining and authorizing the project
Prepare project charter Register stakeholder Determine if the project is worth continuing, should be redirected, or canceled May take place at the beginning of each phase Reexamine the business need for the project during every phase of the project life cycle Information Technology Project Management, Sixth Edition

7 Planning processes Scope management plan Schedule management plan
Define the work that needs to be done (requirements) Schedule management plan Schedule activities related to the work Cost management plan Estimate cost for performing the work Quality management plan Product meets written specifications and intended use Procurement management plan Decide what resource to procure to accomplish the work Revise plan during each phase for changes Ensure that the project addresses organization needs Information Technology Project Management, Sixth Edition

8 Execution processes Acquiring project team and resources to carry out various plans and various tasks Produce product, services, or results of the project or phase Perform quality assurance Manage stakeholder expectation Conduct procurement Information Technology Project Management, Sixth Edition

9 Monitoring and controlling processes
Measure progress against all plans Take corrective actions when there is deviation Ensure that progress meet project objectives Ensure that the project meets stakeholders’ needs and quality standards Reporting performance to stakeholders Stakeholder can identify any necessary changes to keep project on track Information Technology Project Management, Sixth Edition

10 Planning, Execution & Contol
Information Technology Project Management, Sixth Edition

11 Closing processes End the project efficiently Archiving project files
Closing out contracts Document lessons learned Receiving formal acceptance of the delivered work from customers Information Technology Project Management, Sixth Edition

12 Percentage of Time Spent on Each Process Group
Information Technology Project Management, Sixth Edition

13 Complete project scope, schedule, cost, quality, procurement plans
Process Group Output (outcomes) initiation Complete project character, complete a business case (the need for the project) planning Complete project scope, schedule, cost, quality, procurement plans Work breakdown structure (WBS) Revise plans, Ensure the plans address organization need Execution Take the actions necessary to complete the work described in planning (e.g. purchase HW and SW, develop and install SW), deliver the actual work of the project, perform quality assurance Monitoring & controlling Monitor deviations from the plan, take corrective actions to mach progress with the plan, measure progress toward project objectives, ensure that deliverable are being completed and objectives are being met in terms of scope, cost, time, and quality, complete a performance report Closing Gain acceptance for project results, products, and services Report lessons learned Information Technology Project Management, Sixth Edition

14 Mapping the Process Groups to the Knowledge Areas
You can map the main activities of each PM process group into the nine knowledge areas using the PMBOK® Guide 2008 Note that there are activities from each knowledge area under the planning and monitoring and controlling process groups Two new processes were added in 2008: identify stakeholders and collect requirements Information Technology Project Management, Sixth Edition

15 Table 3-1: Project Management Process Groups and Knowledge Area Mapping*
*Source: PMBOK® Guide, Fourth Edition, 2008. Information Technology Project Management, Sixth Edition

16 Table 3-1. (continued) Information Technology Project Management, Sixth Edition

17 Table 3-1 (continued) Information Technology Project Management, Sixth Edition

18 Developing an IT Project Management Methodology
Just as projects are unique, so are approaches to project management A methodology describes how things should be done. Many organizations develop their own project management methodologies, especially for IT projects Different organizations have different PM methodologies The PMBOK is a standard methodology that describes best practice for should be done PRINCE2, Agile, RUP, and Six Sigma provide different project management methodologies Information Technology Project Management, Sixth Edition

19 What Went Wrong? In 2006, the IRS lost more than $320 million due to a poor fraud-detection system project A 2008 U.S. Government Accountability Office (GAO) report stated that IRS had fixed just 29 of 98 information security weaknesses identified the previous year Information Technology Project Management, Sixth Edition

20 What Went Right? AgênciaClick, an interactive advertising and online communications company based in São Paulo, Brazil, made PMI’s list of outstanding organizations in project management in 2007 Since 2002, the company saw revenues jump 132 percent, primarily due to their five-year emphasis on practicing good project management across the entire company Information Technology Project Management, Sixth Edition

21 Case Study: JWD Consulting’s Project Management Intranet Site
This case study provides an example of what’s involved in initiating, planning, executing, controlling, and closing an IT project This example uses Microsoft project to assist in PM You can download templates for creating your own project management documents from the companion Web site for this text or the author’s site Note: This case study provides a big picture view of managing a project; later chapters provide detailed information on each knowledge area Information Technology Project Management, Sixth Edition

22 JWD project Job Well Done (JWD) is a consulting organization
JWD provides consulting services on PM to other organizations JWD aims to initiate a new Intranet site project The site allows JWD to share its PM knowledge by providing an exemplary process for managing its projects Projects goals allows JWD to work effectively Allows customers to access information Bringing in more business Information Technology Project Management, Sixth Edition

23 Project Pre-initiation
Determine the scope, time, and cost constraints for the project Identify the project sponsor Select the project manager Develop a business case for a project Meet with the project manager to review the process and expectations for managing the project Determine if the project should be divided into two or more smaller projects Information Technology Project Management, Sixth Edition

24 JWD pre-initiation tasks
Project scope: Intranet system to provide consultants and customers with valuable information on PM Project time estimate: 6 months Project cost estimate: $140,000 Project sponsor: Joe Fleming, also CEO Project manger: Erica Bill, PMO director Business case (see Table 3-2) If there is a strong business case Joe & Erica will meet to review the process and expectations for managing the project, else the project would not continue The project will not be divided in the case Information Technology Project Management, Sixth Edition

25 Business case Justify investing in the project and includes:
Introduction/background Business objective Current situation and problem statement Critical assumptions and constraints Analysis of options and recommendation Preliminary project requirements Budget estimate Schedule estimate Potential risk exhibits Information Technology Project Management, Sixth Edition

26 Project Initiation Initiating a project includes recognizing and starting a new project or project phase The main goal is to formally select and start off projects Information Technology Project Management, Sixth Edition

27 Stakeholder Register Information Technology Project Management, Sixth Edition

28 Stakeholder Management Strategy
Contents are often sensitive, so do not publish this document. Information Technology Project Management, Sixth Edition

29 Project Charters and Kick-off Meetings
See Table 3-6 for an example of a charter Charters are normally short and include key project information and stakeholder signatures It’s good practice to hold a kick-off meeting at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans Information Technology Project Management, Sixth Edition

30 Project charter Project title Start date and end date
Budget information Project manger Project objectives Main project success criteria Approach Roles and responsibilities Sign off (signature of all of stakeholders) comments Information Technology Project Management, Sixth Edition

31 Kick-off Meeting Agenda
Information Technology Project Management, Sixth Edition

32 Project Planning The main purpose of project planning is to guide execution Every knowledge area includes planning information (see Table 3-7 on pages 97-98) Key outputs included in the JWD project include: A team contract (table 3-8) A project scope statement (table 3-9) A work breakdown structure (WBS) (figure 3-3) A project schedule, in the form of a Gantt chart with all dependencies and resources entered A list of prioritized risks (part of a risk register) See sample documents on pages Information Technology Project Management, Sixth Edition

33 Scope statement Project title, date of statement, prepared by who
Project summary and justification Product characteristics and requirements Summary of project deliverable Project success criteria Information Technology Project Management, Sixth Edition

34 JWD Consulting Intranet Site Project Baseline Gantt Chart
Information Technology Project Management, Sixth Edition

35 List of Prioritized Risks
Information Technology Project Management, Sixth Edition

36 Project Executing Usually takes the most time and resources to perform project execution Project managers must use their leadership skills to handle the many challenges that occur during project execution Many project sponsors and customers focus on deliverables related to providing the products, services, or results desired from the project A milestone report can help focus on completing major milestones Information Technology Project Management, Sixth Edition

37 Part of Milestone Report
Information Technology Project Management, Sixth Edition

38 Project Monitoring and Controlling
Involves measuring progress toward project objectives, monitoring deviation from the plan, and taking correction actions Affects all other process groups and occurs during all phases of the project life cycle Outputs include performance reports, change requests, and updates to various plans See Table 3-14 for progress report Information Technology Project Management, Sixth Edition

39 Project Closing Involves gaining stakeholder and customer acceptance of the final products and services Even if projects are not completed, they should be closed out to learn from the past Outputs include project archives and lessons learned (table 3-16), part of organizational process assets Most projects also include a final report (table 3-17) and presentation to the sponsor/senior management Information Technology Project Management, Sixth Edition

40 Templates Table 3-18 on pp lists the templates available on the companion Web site ( and the author’s site ( Information Technology Project Management, Sixth Edition

41 Chapter Summary The five project management process groups are initiating, planning, executing, monitoring and controlling, and closing You can map the main activities of each process group to the nine knowledge areas Some organizations develop their own information technology project management methodologies The JWD Consulting case study provides an example of using the process groups and shows several important project documents Information Technology Project Management, Sixth Edition