The project structure (WBS) 24-March-2015 1
2
Recap Software Development Planning 2
3
Recap – What IS or ISN’T a Project Plan A project plan IS a collection of different views of the project A project plan IS a model of the project’s future A project plan IS a living artifact A project plan is NOT a GANTT chart A project plan is NOT a schedule 3
4
Recap - PMBOK Definition The process necessary for defining, preparing, integrating and coordinating all subsidiary plans into a project management plan. The project management plan becomes the primary source of information for how the project will be planned, executed, monitored and controlled, and closed. 4
5
Recap - Planning timeline 5
6
Project Planning Process Areas Developing the Project Plan Interacting with Stakeholders Getting Commitment to Plan Maintaining the Plan 6
7
Specific Goals Establish Estimates Develop a Project Plan Obtain Commitment to the Plan 7
8
Role: Project Manager (RUP) 8
9
Project Planning Roles and Responsibilities ResponsibleAccountableConsultedInformed Project Management XX Project Stakeholders XX Project TeamXX Project Review Authority X 9
10
Activities for developing the SDP Develop the SDP project management content Develop enclosed project management plans Coordinate the development of supporting plans 10
11
Topic – Scope Management and WBS Planning the Development The project structure (WBS) References Software Project Management: A Unified Framework, Walker Royce, Addison Wesley Fundamentals of Project Management, James P. Lewis, AMACOM Books Software Project Management, Bob Huges, Mike Cotterrel PMBOK 11
12
Going further into Planning Planning is about answering some questions like: “What must be done?” “When will it be done?” “Who will build it?” “How much will it cost?” 12
13
Planning the “WHAT” Planning the “what” is crucial One frequent reason projects fail is that a significant part of the work is forgotten! 13
14
Project Scope Management Scope Planning Scope Definition Create WBS Scope Verification Scope Control 14
15
Scope Planning Defining and managing the scope is key to project success Detailed project scope statement process Process for creating the WBS from the detailed statement Formal verification specification Change control process 15
16
Scope Definition Detailed project scope statement Change Requests Project Scope Management Plan update 16
17
Scope Definition [1] Detailed project scope statement Project Objectives (Specific, Measurable, Attainable, Relevant, Time-limited) Requirements Boundaries Deliverables Acceptance Criteria Constraints Assumptions 17
18
Scope Definition [2] Detailed project scope statement Initial Organization Initial Risk Milestones Fund limitations Cost estimate Configuration Management Requirements Specifications Approval Requirements 18
19
Create WBS Project Scope Statement Updates Work Breakdown Structure WBS Dictionary Scope Baseline Project Scope Management Plan Updates Change Requests 19
20
Scope Verification Assures that the detailed scope definition, WBS and WBS dictionary are formally reviewed and approved by the project stakeholders 20
21
Scope Verification Accepted deliverables Change Requests Recommend corrective actions 21
22
Scope Control Assures that all Requested Changes and Corrective Actions are processed by the Integrated Change Control Management process 22
23
Scope Control Project Scope Statement (Updates) Work Breakdown Structure (Updates) WBS Dictionary (Updates) Scope Baseline (Updates) Requested Changes Recommended Corrective Action Organizational Process Assets (Updates) Project Management Plan (Updates) 23
24
What is the WBS? WBS is a hierarchical decomposition of work Can be action driven or deliverable driven (verbs or nouns) Organizes and defines the total scope of the project Each level of the WBS represents an increased level of detail 24
25
WBS Introduction 25
26
WBS Dictionary 26
27
WBS Goals Improve estimates Keep the team focused Assign work to resources Keep the project on track 27
28
WBS 28
29
WBS Example Build a House Plans development ArchitectureResilienceConstructionConcreteWallsRoof 29
30
WBS Example Level 1Level 2Level 3 1 Widget Managem ent System 1.1 Initiation1.1.1 Evaluation & Recommendations 1.1.2 Develop Project Charter 1.1.3 Deliverable: Submit Project Charter 1.1.4 Project Sponsor Reviews Project Charter 1.1.5 Project Charter Signed/Approved 1.2 Planning1.2.1 Create Preliminary Scope Statement 1.2.2 Determine Project Team 1.2.3 Project Team Kickoff Meeting 1.2.4 Develop Project Plan 1.2.5 Submit Project Plan 1.2.6 Milestone: Project Plan Approval 30
31
31 Level 1Level 2Level 3 1Widget Manageme nt System 1.3 Execution1.3.1 Project Kickoff Meeting 1.3.2 Verify & Validate User Requirements 1.3.3 Design System 1.3.4 Procure Hardware/Software 1.3.5 Install Development System 1.3.6 Testing Phase 1.3.7 Install Live System 1.3.8 User Training 1.3.9 Go Live 1.4 Control1.4.1 Project Management 1.4.2 Project Status Meetings 1.4.3 Risk Management 1.4.4 Update Project Management Plan 1.5 Closeout1.5.1 Audit Procurement 1.5.2 Document Lessons Learned 1.5.3 Update Files/Records 1.5.4 Gain Formal Acceptance 1.5.5 Archive Files/Documents
32
32
33
Conventional WBS Issues Prematurely structured around the product design Prematurely decomposed, planned and budgeted into either too much detail or too little detail They are project specific, and cross project comparison is impossible 33
34
Evolutionary WBS An evolutionary WBS should organize around the PROCESS framework than around the product framework Example (what the book says) First-level WBS elements are Disciplines Second-level elements are lifecycle phases Third-level should focus on the activities that produce the artefacts of every phase/iteration 34
35
WBS tailoring criteria Project scale Organizational structure Custom development Business context Precedent experience 35
36
WBS Creation Activities Identifying the deliverables and related work Structuring and organizing the WBS Top-down approach Chronological approach Bottom-up approach Developing and assigning identification codes to the WBS components Verifying that the degree of decomposition of the work is necessary and sufficient. 36
37
WBS development guidelines When to stop? What is the best level of detail? Whom should be involved? 37
38
WBS RACI ResponsibleAccountableConsultedInformed Project ManagerXX Project TeamX Project Review Authority X Project Stakeholders XX 38
39
Project Plan Architecture WBS is the project’s plan “architecture” It must encapsulate change It must evolve with the appropriate level of detail through the project lifecycle It must cover ALL project tasks, and NO MORE 39
40
WBS Structure by Phase 40
41
WBS By Discipline 41
42
Level of detail Projects can under-plan as they can over- plan Balance is crucial in finding the right level of detail Must be detailed enough to buy in stakeholders and still remain manageable Normally 3-7 levels 42
43
Is it a work package? If you can estimate the work If it takes between 8 and 80 hours If you can complete it without interruption If you can outsource it 43
44
WBS in MS Project 44
45
Project organization Closely linked to WBS Two organizations Matrix Project Plan for evolution and accommodate change 45
46
Project organization key points Organizational structures form the architecture of the teams Organizations involved in software line of business need to have an organization that supports a common process Project organizations need to allocate artefacts and responsibilities clearly and balanced across project team(s) The project organization must evolve with the WBS and the project lifecycle 46
47
GANTT (Visio) 47
48
GANTT (MS Project) 48
49
Network Diagrams 49
50
Network Diagram Details 50
51
Budgeting defaults example (no actual numbers) WBS DisciplineBudget(%) Management10 Environment10 Requirements10 Design15 Implementation25 Assessment25 Deployment5 Total100 51
52
Generic WBS Project WBS TemplateTemplate Software Development.mpp MSF Application Development.mpp 52
53
WBS for Agile Agile based WBS is built around user functionality (“Epics”, “User stories”) 53
54
F(eature) BS should provide business value should be estimable should be small enough to fit within an iteration should be testable 54
55
EVM 55
56
EVM in Agile 56
57
Define WBS 57
58
Identify OBS 58
59
Wrap-up Use a top-down approach. Begin at the project goal level and break the work successively to lower levels of definition. Create it with the input from domain experts and team members. Do not include any work which is not part of the project. Cover the entire scope of the project at least at the upper level of the WBS 59
60
Wrap-up continued Each component of the WBS, excepting the highest one, is a part of the parent WBS component. The lowest level of the WBS shall have the following properties: It is possible to estimate its need for resources, duration and costs. The start and the end of the execution can be clearly defined. 60
61
Wrap-up continued It's realization can be outsourced. It has a deliverable or a clear part of it. It can be completed within reasonable time limits. There is no universally accepted rule regarding the length of an work package. However, it shall not exceed 1-2 weeks to complete. Specific to the software development projects, it can be executed by a single developer. 61
62
Next time Scheduling 62