Presentation is loading. Please wait.

Presentation is loading. Please wait.

Grand Calumet River/Indiana Harbor Canal Feasibility Study

Similar presentations


Presentation on theme: "Grand Calumet River/Indiana Harbor Canal Feasibility Study"— Presentation transcript:

1 Grand Calumet River/Indiana Harbor Canal Feasibility Study
Discuss approach and considerations when planning habitat restoration for dredging projects East Chicago Waterway Management District Jim Wescott April 23, 2015

2 Grand Calumet River & Indiana Harbor Canal
East Chicago Waterway Management District and EPA are funding an investigation and study of the GCR/IHC to develop a remedial design ECWMD, EPA, and their consultant, Tetra Tech, want stakeholder feedback on remedial options, funding priorities, future end use, and other stakeholder groups not represented here today.

3 GCR/IHC Progress East Branch Actual Start spring 2013
Discuss WBGCR and how lessons learned applied to EBGCR.

4 Completed/In Progress
EBGCR USS Steel Section: Hydraulic Dredging WBGCR Reaches 3-5: Mechanical Excavation and Capping WBGCR Reaches 1&2:Hydraulic Dredging, Mechanical Excavation, Capping, and Habitat Restoration EBGCR Reaches 4A&4B: Hydraulic Dredging, Mechanical Excavation, Capping, and Habitat Restoration WBGCR Reaches 6&7:Mechanical Excavation and Capping EBGCR Gary Section: Feasibility Study/Remedial Design WB/EB GCR, Indiana Harbor Canal, and Lake George Canal Remedial Investigation and Feasibility Study

5 Current Project Area – GCR/IHC

6 Grand Calumet River Junction

7 Indiana Harbor Canal

8 Lake George Canal

9 RI/FS Tasks Remedial Investigation Feasibility Study Sediment Sampling
Pore Water Sampling Source Control Evaluation Bathymetric and Topographic Surveys Geotechnical Sampling Clean Up Goals Development Remedial Alternative Screening and Evaluation

10 GCR Surface Sediment Total 16 PAH

11 GCR Subsurface Sediment Total 16 PAH

12 GCR Surface Sediment PCBs

13 GCR Subsurface Sediment PCBs

14 GCR Surface Sediment Metals

15 IHC Surface Sediment Total 16 PAH

16 IHC Subsurface Sediment Total 16 PAH

17 IHC Surface Sediment PCBs

18 IHC Subsurface Sediment PCBs

19 IHC Surface Sediment Metals

20 LGC Surface Sediment Total 16 PAH

21 LGC Subsurface Sediment Total 16 PAH

22 LGC Surface Sediment PCBs

23 LGC Subsurface Sediment PCBs

24 LGC Surface Sediment Metals

25 Remedial Options No Action Monitored Natural Recovery In Situ Capping
Environmental Dredging or Excavation

26 Grand Calumet River Options
Sediment Dredge 10 feet of River (Majority of Impacted Sediment) and place 2 feet of sand over remaining sediment. Estimated $43,000,000 Dredge 3 feet of West Branch. Place active cap material over West and East Branches. Estimated $16,000,000. Option 2 with targeted dredging in East Branch. Estimated $17,500,000 Habitat Dredge and rebuild/restore Junction Marsh and the USS Lead Marsh. Estimated $13,000,000 Invasive Species control and replant both marshes. Estimated $1,000,000 Option 2 with partial dredging along river boundary. Estimated $7,500,000

27 Indiana Harbor Canal Options
Sediment Dredge 8 feet of Canal (Majority of Impacted Sediment) and place 2 feet of sand over remaining sediment. Estimated $48,000,000 Option 1 with 1 foot sand. Estimated $44,000,000 Partial dredging for PCB areas and place 2 feet of sand over remaining sediment. Estimated $15,000,000 Option 3 with 1 foot sand. Estimated $11,000,000

28 Lake George Canal Options
Lake George Canal East of Railroad Bridge Dredge area to navigation channel depth (10 feet) Estimated $8,000,000 Partial dredge to reduce resuspension (5 feet) Estimated $4,000,000 Lake George Canal between Railroad Bridge and Land Bridge Partial dredge (5 feet) and 2 feet sand cap. Estimated $8,500,000 Six (6) foot sand cap. Estimated $4,500,000 Lake George Canal west of Land Bridge Dredge 6 feet and 1 foot sand cap. Estimated $ 18,000,000 2.No Action

29 Selection Considerations
Cost Permits Site Access Utilities and other Debris Sediment Characteristics Long Term Effectiveness Potential for Recontamination Future End Use Stakeholder and Community Acceptance

30 Typical Remedial Tasks

31 Time Frame and Costs Seeking Project Partners
Begin Dredging spring 2016 Complete remedial action Cost Ranges from $40 Mil to $145 Mil Schedule heavily dependent on non-federal and federal funding Construction could be broken into smaller pieces to facilitate funding and stakeholder priorities Seeking Project Partners

32 Jim Wescott Tetra Tech jim.wescott@tetratech.com 312.201.7781
Questions? Jim Wescott Tetra Tech


Download ppt "Grand Calumet River/Indiana Harbor Canal Feasibility Study"

Similar presentations


Ads by Google