Download presentation
Published byHerbert Reynolds Modified over 9 years ago
1
Grand Calumet River/Indiana Harbor Canal Feasibility Study
Discuss approach and considerations when planning habitat restoration for dredging projects East Chicago Waterway Management District Jim Wescott April 23, 2015
2
Grand Calumet River & Indiana Harbor Canal
East Chicago Waterway Management District and EPA are funding an investigation and study of the GCR/IHC to develop a remedial design ECWMD, EPA, and their consultant, Tetra Tech, want stakeholder feedback on remedial options, funding priorities, future end use, and other stakeholder groups not represented here today.
3
GCR/IHC Progress East Branch Actual Start spring 2013
Discuss WBGCR and how lessons learned applied to EBGCR.
4
Completed/In Progress
EBGCR USS Steel Section: Hydraulic Dredging WBGCR Reaches 3-5: Mechanical Excavation and Capping WBGCR Reaches 1&2:Hydraulic Dredging, Mechanical Excavation, Capping, and Habitat Restoration EBGCR Reaches 4A&4B: Hydraulic Dredging, Mechanical Excavation, Capping, and Habitat Restoration WBGCR Reaches 6&7:Mechanical Excavation and Capping EBGCR Gary Section: Feasibility Study/Remedial Design WB/EB GCR, Indiana Harbor Canal, and Lake George Canal Remedial Investigation and Feasibility Study
5
Current Project Area – GCR/IHC
6
Grand Calumet River Junction
7
Indiana Harbor Canal
8
Lake George Canal
9
RI/FS Tasks Remedial Investigation Feasibility Study Sediment Sampling
Pore Water Sampling Source Control Evaluation Bathymetric and Topographic Surveys Geotechnical Sampling Clean Up Goals Development Remedial Alternative Screening and Evaluation
10
GCR Surface Sediment Total 16 PAH
11
GCR Subsurface Sediment Total 16 PAH
12
GCR Surface Sediment PCBs
13
GCR Subsurface Sediment PCBs
14
GCR Surface Sediment Metals
15
IHC Surface Sediment Total 16 PAH
16
IHC Subsurface Sediment Total 16 PAH
17
IHC Surface Sediment PCBs
18
IHC Subsurface Sediment PCBs
19
IHC Surface Sediment Metals
20
LGC Surface Sediment Total 16 PAH
21
LGC Subsurface Sediment Total 16 PAH
22
LGC Surface Sediment PCBs
23
LGC Subsurface Sediment PCBs
24
LGC Surface Sediment Metals
25
Remedial Options No Action Monitored Natural Recovery In Situ Capping
Environmental Dredging or Excavation
26
Grand Calumet River Options
Sediment Dredge 10 feet of River (Majority of Impacted Sediment) and place 2 feet of sand over remaining sediment. Estimated $43,000,000 Dredge 3 feet of West Branch. Place active cap material over West and East Branches. Estimated $16,000,000. Option 2 with targeted dredging in East Branch. Estimated $17,500,000 Habitat Dredge and rebuild/restore Junction Marsh and the USS Lead Marsh. Estimated $13,000,000 Invasive Species control and replant both marshes. Estimated $1,000,000 Option 2 with partial dredging along river boundary. Estimated $7,500,000
27
Indiana Harbor Canal Options
Sediment Dredge 8 feet of Canal (Majority of Impacted Sediment) and place 2 feet of sand over remaining sediment. Estimated $48,000,000 Option 1 with 1 foot sand. Estimated $44,000,000 Partial dredging for PCB areas and place 2 feet of sand over remaining sediment. Estimated $15,000,000 Option 3 with 1 foot sand. Estimated $11,000,000
28
Lake George Canal Options
Lake George Canal East of Railroad Bridge Dredge area to navigation channel depth (10 feet) Estimated $8,000,000 Partial dredge to reduce resuspension (5 feet) Estimated $4,000,000 Lake George Canal between Railroad Bridge and Land Bridge Partial dredge (5 feet) and 2 feet sand cap. Estimated $8,500,000 Six (6) foot sand cap. Estimated $4,500,000 Lake George Canal west of Land Bridge Dredge 6 feet and 1 foot sand cap. Estimated $ 18,000,000 2.No Action
29
Selection Considerations
Cost Permits Site Access Utilities and other Debris Sediment Characteristics Long Term Effectiveness Potential for Recontamination Future End Use Stakeholder and Community Acceptance
30
Typical Remedial Tasks
31
Time Frame and Costs Seeking Project Partners
Begin Dredging spring 2016 Complete remedial action Cost Ranges from $40 Mil to $145 Mil Schedule heavily dependent on non-federal and federal funding Construction could be broken into smaller pieces to facilitate funding and stakeholder priorities Seeking Project Partners
32
Jim Wescott Tetra Tech jim.wescott@tetratech.com 312.201.7781
Questions? Jim Wescott Tetra Tech
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.