1 Construction Management Contract
Assembly and Installation Industry Information Day Construction Management Contract by Ken Blackler 21 May 2015 Disclaimer: The views and opinions expressed herein do not necessarily reflect those of the ITER Organization

2 Table of Contents: General Scope of Services Description of tasks
Interfaces with other contractors Contract Schedule

3 Construction Manager-as-Agent
Contract Map ITER Organization Construction Manager-as-Agent Domestic Agency Works Contractors Machine Assembly Works Mechanical & Piping Works Specialized Works Super Conducting Joints Special Techniques Lifting & Handling Tokamak Works Contracts Support Contracts Access, Plant Hire Civils & Finishing Balance of Plant Electrical, I&C Works Scaffolding CMA ASY MCP EIC SPx LFT SCF APH CIV

4 Construction Management Contract
ITER Organization Construction Manager-as-Agent Domestic Agency Works Contractors Machine Assembly Works Mechanical & Piping Works Specialized Works Super Conducting Joints Special Techniques Lifting & Handling Tokamak Works Contracts Support Contracts Access, Plant Hire Civils & Finishing Balance of Plant Electrical, I&C Works Scaffolding CMA ASY MCP EIC SPx LFT SCF APH CIV

5 1. General Purpose: Background:
Define scope, mission and work activities of the Construction Management-as-Agent (CMA) Contractor. Background: Large and complex worksite Many technical challenges that will arise during the construction Many different actors that must be coordinated in a safe and efficient manner Strong and effective management, combining Tokamak specific knowledge and industrial know-how is required in order to maintain schedule and minimize cost IO Construction Department is responsible to plan, manage and execute the construction works on site of the ITER Tokamak, plant equipment and facilities, and their start-up, testing and commissioning (excluding building construction).

6 1. General – ITER Specifics
In-kind Procurement Many components are provided ‘free-issue’ by the ITER Member countries through their Domestic Agencies IO-CT and IO-DA manage the supply chain through an integrated team Machine Assembly Assembly of the Tokamak is a unique activity where IO has the greater knowledge and must bear the majority of the risks. IO must maintain a strong control of the Machine Assembly activities The CMA shall support IO by supplying the necessary industrial know how, processes and resources. Plant Installation These are conventional works which follow significantly more standard processes CMA shall be involved to a greater extent IO maintains overall responsibility for the priorities and technical performance, management of outstanding issues and interfaces with DAs.

7 2. Scope of Services Services included:
Management Planning and Program Management Works Contract Management Worksite Coordination Site Coordination Occupational Health and Safety Environmental Health and Safety Material Management Works Supervision Supervision of the Works Quality Control Record Keeping Completion Activities Start-up and Testing Maintenance Management The Construction Management Contractor shall not self-perform any works. The extent of involvement shall be different for the Tokamak and the Plant Systems. This is a summary only. The complete scope shall be defined in the tender specifications

8 3. Description of Services - Management
Planning and Program Management Baseline management: Work breakdown structure, scope database, construction schedule and cost Detailed planning, cost estimates, risk analysis of works Report progress, using Earned Value, KPI etc. Administer Requests for Information, Field Changes, Non-Conformances Works Contract Management Engineer and/or Assistant to the Engineer for FIDIC contracts; Construction work packages e.g. materials list, drawings, specifications, procedures, equipment and tools, hold points, and quality control documents Additionally For Tokamak Assembly Works Field Installation Work Packages - based upon IO supplied Construction Processes, specifications and documentation; Assembly drawings, based upon sequences, specifications, 3D models and engineering drawings provided by IO. Additionally For Conventional Works: Field Installation Work Packages and assignment to contractors This is a summary only. The complete scope shall be defined in the tender specifications

9 3. Description of Services – Worksite Coordination
Site Rules and Regulations Manage and coordinate activities on the site, space utilisation, traffic, control of pollution and the environment; Access control requests for the worksite; Coordination, steering and planning meetings with IO, DA and works Contractors; Development and implementation of a “pro-rata” account; Occupational Health and Safety Support the IO in implementing a continuous improvement safety programme; Manage the Permit to Work system; Environmental Health and Safety Ensure that materials used on site do not pose an undue risk to site personnel, nor endanger the environment; Identify and approve any hazardous materials coming onto the ITER site; Material Management Expedite materials by interfacing with IO, DA, suppliers, warehouse and global logistics service provider; Control materials, including receiving, preservation, quarantine and in-field traceability; Administration and operation of the SmartPlant Materials system; This is a summary only. The complete scope shall be defined in the tender specifications

10 Construction Worksite Teams
Overall Daily Site Coordination. Management of Interfaces Site Construction Manager CMA Worksite Construction Team Worksite Construction Team Worksite Construction Team Worksite Construction Team Worksite Construction Team Worksite Construction Team CMA CMA CMA CMA CMA CMA Machine Assembly Tokamak Complex Control Buildings Cooling Water and Cryogenic Electrical Buildings Site Works and Coordination MA Contractor Works Contractors

11 3. Description of Services – Works Supervision
Supervision of the Works Issue instructions to Contractors (within delegated limits and which do not alter the cost of the project); Check applications for payment and assess them prior to IO payment; Manage field engineering processes and information exchange; Assess field change requests, deviation requests and non-conformities. Additionally For Tokamak Assembly Works Support IO to supervise day works, report technical issues. Provide independent assessment of field change requests, deviation requests and non-conformities. Additionally For Plant Installation: Planning, supervision, testing and completion of works within a building, area or room. manage interfaces, resolve disputes, solve on-site technical issues; Provide field engineering support to contractors, with expert support from IO. This is a summary only. The complete scope shall be defined in the tender specifications

12 3. Description of Services – Works Supervision (2)
Quality Control Check compliance between execution drawings prepared by contractors and drawings and specifications prepared by IO; Assess Contractor’s quality plans and control plans (MIP); Verify conformance of completed works to requirements, specifications and contract deliverables, undertake inspections to confirm; Coordinate and supervise Inspections, Notification and Hold Points; Manage Measuring and Test Equipment including certification, calibration; Record Keeping Manage information, records and documents related to construction within the IO IT environment, including document scanning, classification, filing, searching and printing; Check documentation and ‘as built’ drawings; Support the IO in maintaining complete and accurate records of all site activities. This is a summary only. The complete scope shall be defined in the tender specifications

13 3. Description of Services – Completion Activities
Start-up and Testing Working with IO experts, confirm construction activities have been correctly performed. Manage testing performed by the Contractors, IO and DA, record the outcomes, prepare plans for rectification. Maintenance Management Plan and regular, preventative and corrective maintenance for installed equipment; Keep all maintenance associated records; Manage any remedial, corrective and preventive actions. This is a summary only. The complete scope shall be defined in the tender specifications

14 4. Interfaces with other contractors
Construction Manager-as-Agent contractor shall interface strongly with all works contracts Act as Engineer/Assistant to Engineer for FIDIC works contracts placed by IO Coordinate works performed by IO and DA contractors Three stages of site coordination Preparation stage - ENGAGE coordination civil construction Early works managed by CMA with overall site coordination by EUDA contractor (ENGAGE) Main works with CMA site coordination Stage 1 ENGAGE Coordination No IO Works Stage 2 IO and DA Works Stage 3 CMA Coordination

15 5. Information Systems SmartPlant software suite implemented:
Construction planning and management Materials management Testing Configuration control for construction System integrated to ensure flow of data, documents from design tools and logistics systems Customisation by IO to adapt to agreed ways of working (e.g. workflows) IO will train-the-trainers in the awarded Construction Management contractor

16 Tokamak Completion and Hook-ups
6. Work Profile Current schedule is ‘as early as possible’’ Uneven profile in resources Logic driven by machine assembly sequences Machine assembly is back-end loaded (mandatory) Plant works early loaded and may be smoothed Specialised works to be reallocated to plant or machine assembly works contracts Complete before tenders launched Optimisations will be key to workforce management Work Packages - Not-levelled Tokamak Completion and Hook-ups Machine Assembly

17 Time Distribution of Works by Domestic Agency
Some works shall be transferred to IO for execution

18 Time Distribution of IO Works by Contract

19 Please send all questions to:
Replies to all questions received within 2 weeks shall be published on the ITER web site and notified to all attendees