OPERATIONS MANAGEMENT for MBAs Fourth Edition
Meredith and Shafer Prepared by: Al Ansari Seattle University John Wiley and Sons, Inc. Chapter 6: Managing Process Improvement Projects
2
Chapter 6: Managing Process Improvement Projects
3
Introduction Chapter 6: Managing Process Improvement Projects
4
Background Project management concerned with managing organizational activities. Often used to integrate and coordinate diverse activities. Projects are special types of processes. Chapter 6: Managing Process Improvement Projects
5
Defining a Project Projects are processes that are performed infrequently and ad hoc, with a clear specification of the desired objective. Chapter 6: Managing Process Improvement Projects
6
Examples of Projects Constructing highways, bridges, tunnels and dams
Erecting skyscrapers, steel mills, and homes Organizing conferences and conventions Managing R&D projects Running political campaigns, war operations, and advertising campaigns Chapter 6: Managing Process Improvement Projects
7
Reasons for Growth in Project Operations
More Sophisticated Technology Better-Educated Citizens More Leisure Time Increased Accountability Higher Productivity Faster Response to Customers Greater customization for customers Chapter 6: Managing Process Improvement Projects
8
Planning the Project Chapter 6: Managing Process Improvement Projects
9
The Project Portfolio The project portfolio also known as the aggregate project plan is to achieve the organization’s goals Chapter 6: Managing Process Improvement Projects
10
Four Categories of Project
Derivative projects. Seek to make incremental improvements in the output and/or process. Breakthrough projects. Are at the opposite end of the continuum from derivative projects and seek the development of a new generation of outputs. Platform projects. Fall between derivative and breakthrough projects. R&D projects. Entail working with basic technology to develop new knowledge. Chapter 6: Managing Process Improvement Projects
11
Aggregate Project Plan
Chapter 6: Managing Process Improvement Projects
12
An Example of Aggregate Project Plan
Chapter 6: Managing Process Improvement Projects
13
Life Cycle of a Project (Stretched-S) & (Exponential)
Chapter 6: Managing Process Improvement Projects
14
Organizing the Project Team
Ad Hoc Project Form Weak Functional Matrix Strong Project Matrix Chapter 6: Managing Process Improvement Projects
15
Types of Project Team Members
Those having a long-term relationship with the project. Those that the PM will need to communicate with closely. Those with rare skills necessary to project success. Chapter 6: Managing Process Improvement Projects
16
Project Plans Chapter 6: Managing Process Improvement Projects
17
Elements of Project Charter
Overview A short summary of what the client expects from the project. Goals, or Scope Contains a more detailed statement of the general goals Business Case Describes the justification for the project General Approach Describes both the managerial and the technical approaches Chapter 6: Managing Process Improvement Projects
18
Elements of Project Charter Cont.
Contractual Aspects This includes a complete list and description of all reporting requirements, customer-supplied resources, liaison arrangements, etc., Schedule and Milestones This outlines the schedule and lists milestone events. Chapter 6: Managing Process Improvement Projects
19
Elements of Project Charter Cont.
Resources -- The project budget and cost Personnel Risk Management Plan This covers potential problems that could affect the project. Evaluation Method Every project should be evaluated against standards Chapter 6: Managing Process Improvement Projects
20
Three Project Objectives
Chapter 6: Managing Process Improvement Projects
21
Work Breakdown Structure
Chapter 6: Managing Process Improvement Projects
22
Project Master Schedule
Chapter 6: Managing Process Improvement Projects
23
Complexity of Scheduling Project Activities
Large number of activities Precedence relationships Limited time of the project Chapter 6: Managing Process Improvement Projects
24
Planning and Scheduling Projects
Planning. Determining what must be done and which tasks must precede others. Scheduling. Determining when the tasks must be completed; when they can and when they must be started; which tasks are critical to the timely completion of the project; and which tasks have slack and how much. Chapter 6: Managing Process Improvement Projects
25
Scheduling the Project
Chapter 6: Managing Process Improvement Projects
26
Terminology Activity Event Network Path Critical Path
Critical Activities Chapter 6: Managing Process Improvement Projects
27
Project Scheduling with Certain Activity Times: A Process Improvement
Inputs list of the activities that must be completed activity completion times activity precedence relationships Chapter 6: Managing Process Improvement Projects
28
Project Scheduling with Certain Activity Times: A Process improvement
Outputs graphical representation of project time to complete project identification of critical path(s) and activities activity and path slack earliest and latest time each activity can be started earliest and latest time each activity can be completed Chapter 6: Managing Process Improvement Projects
29
Example Chapter 6: Managing Process Improvement Projects
30
Network Diagram Chapter 6: Managing Process Improvement Projects
31
Activity Slack Time TES = earliest start time for activity TLS = latest start time for activity TEF = earliest finish time for activity TLF = latest finish time for activity Activity Slack = TLS - TES = TLF - TEF Chapter 6: Managing Process Improvement Projects
32
Path Slack Path Slack = Duration of Critical Path - Path Duration
Chapter 6: Managing Process Improvement Projects
33
Project Scheduling with Uncertain Activity Times
Inputs Optimistic (to), most likely (tm), and pessimistic (tp) time estimate for each activity activity precedence relationships Outputs graphical representation of project expected activity and path completion times variance of activity and path completion times probability that project completed by specified time Chapter 6: Managing Process Improvement Projects
34
Expected Activity Time and Variance of Activity Time
Chapter 6: Managing Process Improvement Projects
35
Example Chapter 6: Managing Process Improvement Projects
36
Probabilities of Completion
Chapter 6: Managing Process Improvement Projects
37
Probability of Project Being Completed on or Before Time 23
Only path A-D-J has reasonable chance of taking 21 or more: Z = / = 0.818 From standard normal table in Appendix A, there is a 79 % chance of completing project on or before time 23. Chapter 6: Managing Process Improvement Projects
38
Probability of Path A-D-J being Completed on or Before Time 23
Chapter 6: Managing Process Improvement Projects
39
Simulating Project Completion Times
Chapter 6: Managing Process Improvement Projects
40
Simulating Project Completion Times
Chapter 6: Managing Process Improvement Projects
41
Chapter 6: Managing Process Improvement Projects
42
Project Management Software Capabilities
Chapter 6: Managing Process Improvement Projects
43
Microsoft Project’s Gantt Chart
Chapter 6: Managing Process Improvement Projects
44
PERT Chart Generated by Microsoft Project
Chapter 6: Managing Process Improvement Projects
45
Calendar of Activities Created by Microsoft Project
Chapter 6: Managing Process Improvement Projects
46
Project and Feeder Buffers
Chapter 6: Managing Process Improvement Projects
47
Controlling the Project: Earned Value
Chapter 6: Managing Process Improvement Projects
48
Variance Report Cost standard determined using engineering estimates or analysis of past performance Actual cost monitored and compared with cost standard Project manager can exert control if difference between standard and actual (called a variance) is considered significant. Chapter 6: Managing Process Improvement Projects
49
Cost-Schedule Reconciliation Charts
Chapter 6: Managing Process Improvement Projects
50
Earned Value Chart Chapter 6: Managing Process Improvement Projects
51
Copyright Copyright 2010John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein. Chapter 6: Managing Process Improvement Projects