GloboGym Fighting Cobras Conceptual Design Review Riley Pack, Sebastian Seeds, Greg Stahl, Paul Loeb, Nic Zinner, Pierce Edwards September 21, 2006 Project Frankenfine: A Near Space Mission
2
Mission Overview Objectives: –Scientific: Take still pictures of the earth and horizon Record digital video of the satellite and its surroundings Measure forces acting upon the satellite –Standards: Ethical Professional Environmentally Friendly
3
Mission Overview (Continued) Expectations: –View of Earth’s horizon from upper atmosphere. –Visual and analytical data about the forces and stresses acting on a satellite. –Analyze above data to help future flights.
4
Design Parts: –Aluminum Tape Lightweight, durable adhesive agent for construction. –HOBO data logger (plus accessories) Small computer data logger and additional equipment to sense, record and later upload to a PC temperature information gathered during flight. –Electric Switches (and wires) Electronic components to link the various systems to each other and power. –Digital Camera (modified) Portable digital image recording device for obtaining visual data during the flight. –Glue gun (and sticks) Adhesive agent and tool for construction.
5
Parts (Continued) –Heating Unit Electronic circuitry to allow data devices to operate and low temperatures. –Foam Core Foam based construction material for satellite frame. –POCKETek Digital Video Recorder Micro digital video recording unit to record video data during flight. –Sandisk 2GB Memory Card 2GB SD flash memory unit for storing video data. –HOBO Pendant G-logger package Data logger and equipment for measuring angular displacement. –Aluminum Superstructure construction material. –Batteries Common power cells for electronics use during flight.
6
Interior Design Drawing
7
Exterior Design Drawing
8
Functional Block Diagram Switch Power Source Heater (Sat 1) Switch Power Source Heater (Sat 2) Switch Power Source Timing Circuit Camera 1 4 Channel HOBO Internal Temperature External TemperatureRelative Humidity Video Camera HOBO Accelerometer (HOBO Pendent G-Data Logger)
9
Management Organizational Chart –Structures: Sebastian Seeds: Structural construction and supervision –Structural construction, logistics, and schedule. –Foam core construction (cutting, gluing, and measurement). –Integration, structural construction, and testing supervision. –Buy supplies. Nicolas Zinner: Structural support and integration –Aluminum (cutting, sizing, and integration with the foam core) and hardware integration (direct attachment of hardware to structure). Paul Loeb: Testing and Assembly –Testing design, testing procedure, and executing structural testing before and after hardware integration. –Backup structural design and structural contingencies. –Assembly supervision.
10
Management(Continued) –Hardware Riley Pack: Organization, supervision, and component testing. –Hardware construction, logistics, and schedule. –Independent hardware testing before integration. –Hardware construction and hardware integration supervision. Pierce Edwards: Hardware integration, testing, and recording. –Direct integration and placement of hardware within the satellite. –Functionality test design, procedure, and execution before and after integration with the structure. –Video. Greg Stahl: Circuitry and Heating –Soldering (direct hardware connection and integrity). –Circuitry support, repair, design, and contingencies. –Heater placement and integration.
11
Schedule Complete Design – 9/21/2006 Submit Proposal – 9/21/2006 Conceptual Design Review Presentation – 9/21/2006 Design Document Revision A – 10/5/2006 Prototype Design – 10/12/2006 Critical Design Presentation – 10/17/2006 Design Document Revision B – 10/17/2006 Acquire All Hardware – 10/20/2006 Testing Final Structural Design (Whip/Drop Tests) – 10/20/2006 Integrate Hardware – 11/5/2006 Cold Test – 11/5/2006 Design Document Revision C – 11/9/2006 Launch Day – 11/11/2006 Design Document Revision D – 11/30/2006 Final Presentation – 12/05/2006
12
Mass Budget ItemMass (g) Still Camera, Film, and Battery150 HOBO Data Logger29 Heating units (2)30 POCKETek Digital Video Recorder and SD Card40 G-Force Data Logger~35 Timing Circuit and 12V Battery Pack~40 9V Batteries (6)~240 Structure~200 Total764
13
Monetary Budget ItemAmount Space Grant Funds$275.00+ Pledged Team Funds (if needed)$120.00+ POCKETek Digital Video Recorder$99.50- ScanDisk 2GB SD Memory Card$52.99- HOBO Pendant G Logger Package$99.00- Aluminum$15.00- (Projected) Spare Parts$15.00- Total Shipping$24.00- Total Funds$395.00+ Total Expenses$305.49- Total$89.51+