From planning to foundations Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library A New Library for Trinity
2
A little background... A New Library for Trinity
3
1996 ‘Idea’ of New Library developed and visits planned A New Library for Trinity
4
1997 January Visit to US Libraries 1997 February Visit to European Libraries A New Library for Trinity
5
Issues identified during visits: Separation of books and readers Flexibility v. Environment Finishes for surfaces important IT wiring throughout Staff areas A New Library for Trinity
6
Separation of books and readers - reader space at Kroch Library, Cornell University
7
Separation of books and readers - book space at Kroch Library, Cornell University
8
Flexibility v. environment 1 - George Washington University
9
Flexibility v. environment 2 - Boston College
10
Flexibility v. environment 3 - Emory University, Atlanta
11
Finishes for surfaces important - Case Western Reserve University
12
Finishes for surfaces important - Kroch Library, Cornell University
13
IT wiring throughout - Case Western Reserve University
15
Staff areas - Case Western Reserve University
16
Staff areas - Kroch Library, Cornell University
17
A New Library for Trinity The Site The Brief The Competition
18
The Site
19
A New Library for Trinity The Brief: 650 - 700 additional reader places 360,000 additional volumes on open access Integration of IT and traditional use Single point of focus for services Linking of three library buildings
20
A New Library for Trinity The architectural competition: ~ 50 interested 9 invited to compete 6 entries Competition run by RIAI
21
A New Library for Trinity Architects appointed: McCullough Mulvin and Keane Murphy Duff
23
A New Library for Trinity Reader block - 4 floors Book block - 5 floors Ground level - orientation, materials processing 2 Lower levels - books, readers, plant Conservation Building
24
A New Library for Trinity IT and Multimedia Anticipation of use Size of equipment Multi-media = ‘old’ media?
25
Size of Computers- Limerick University
26
Developments in Computer sizes - Gateway August 1999
30
A New Library for Trinity Completion March 2001 Refurbishment of Berkeley July - December 2001 New Library Complex in full use September 2002-
31
A New Library for Trinity Pleasing everyone?
32
From planning to foundations Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library A New Library for Trinity