9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan.

Similar presentations


Presentation on theme: "9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan."— Presentation transcript:

1

2 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan

3 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Schedule Overview 20022003200420052006FY2008FY2009 Construction Operation FY2003FY2004FY2005FY2006FY2007 CD-2aCD-2b CD-3aCD-3b Start of Operations (X-Rays to Far Hall) CD-4 Project Engineering Design Long-Lead Procurement FY2010 Time Now UV Beam To cathode 1st beam on Linac axis Start LTU commissioning Start Undulator commissioning Start XTOD commissioning BTH, FH UH DUMP Beneficial Occupancies NH { CLOC

4 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC

5 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC SLAC linac tunnel LTU Linac-0 Linac-1Linac-2Linac-3 BC-1BC-2 DL-2 DL-1 Undulator 6 MeV 150 MeV 250 MeV 4.54 GeV 14.35 GeV Linac-X X Ray Diag. Far Hall Dump Tune up Dump BSY Single beam Dumper 12/06new rfgun 7/07 25-1a30-8c21-1b21-1d21-3b24-6d 4/08 7/08 12/06UV Beam to Cathode 7/07First Beam on Linac Axis 4/08Start LTU Commissioning 7/08Start Undulator Commissioning Start XTOD Commissioning X

6 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Startup Test Plan PRD 1.1-002 Spells out our plan for turning on the LCLS systems. Currently working on rev-1. Evolved from "Commissioning Document" discussed at previous workshop. The editors continue to welcome your contributions!

7 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC

8 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC

9 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Startup Phases Phase I - low beam quality –BBA, radiation reduction, x-ray diagnostics, SR measurements Phase II - high beam quality – low emittance tuning, gain curve measurement, precision x-ray measurements Phase III - transition to operation –Full rep rate, stable operating conditions, full energy range, finalize operational procedures

10 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC End of Startup Startup Plan goes well beyond "Start of Operations" which is met when X Rays are detected at the Far Hall At the end of Phase III we leave the machine with operators who are then able to provide users with required beams on a daily basis.

11 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Phase I Performance Goals

12 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Phase I Demonstrates Bunch compression and bunch length control Orbit control and stability Xray diagnostics functionality SR measurement capability Beam collimation and radiation protection

13 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Phase II Performance Goals

14 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Phase II Demonstrates SASE FEL process is working Requires –FEL quality orbit straightness and stability –Good linewidth –Good emittance –High bunch current –Gain length measurements Areas of physics concern: CSR, instabilities, wakefield effects, new physics effects,…

15 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Phase III Performance Goals

16 9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC Completion of Phase III Demonstrates We are ready to turn the machine over to the operators and the users We need another project!


Download ppt "9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan."