March 22, 20051 Prototype Fabrication Economic & Test Plan QDR Michael Caldwell Jeff Haddin Asif Hossain James Kobyra John McKinnis Kathleen Mondino Andrew Rodenbeck Jason Tang Joe Taylor Tyler Wilhelm AAE 451: Team 2
2
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 2 Overview Aircraft 3-View Overall Schedule Economic Plan Flight Test Plan
3
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 3 Aircraft 3-View Mission Requirements 15 min. endurance Take-off distance ≤ 60 ft. V stall ≤ 15 ft/s V loiter ≤ 25 ft/s 35 ft. turn radius
4
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 4 Overall Schedule Thursday, March 10 Thursday, March 24 Monday, March 28 Thursday, April 14 Tuesday, April 19 Tuesday, April 26 Thursday, April 28 Parts Ordering Thiokol Draft Report Due Critical Design Review Prototype Fabrication Component Testing Flight Testing Flight Readiness Review First Official Flight at Mollenkopf Athletic Center Thiokol Final Report Due Summary Project Presentation
5
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 5 Overall Schedule Thursday, March 24 to Saturday, April 2 Monday, March 28 to Saturday, April 2 Saturday, April 2 to Saturday, April 9 Saturday, April 2 to Saturday, April 9 Saturday, April 9 to Sunday, April 10 Sunday, April 10 to Tuesday, April 19 Prototype Wing Fabrication and Testing Component Testing Wing Fabrication Fuselage Fabrication Install Components Flight Testing / Modifications
6
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 6 Economic Plan Total Person-Hours (as of Week 9 - 3/21/05):1700 hours Estimated Total Person-Hours at Project Completion:3500 hours
7
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 7 Economic Plan Component Testing Motor and Controller$134.00 Rate Gyro $124.99 Receiver $ 69.00 Servos $ 65.96 Battery$ 29.90 Propellers$ 22.00 ----------------------------------------- Total$445.85 Prototype Fabrication and Testing EPP Foam$ 60.00 Balsa$ 20.00 Ultrakote$ 18.00 Landing Gear$ 15.00 Epoxy$ 10.00 ----------------------------------------- Total$123.00 Cost Estimation
8
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 8 Economic Plan
9
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 9 Flight Test Plan Schedule / Location of Flight Testing April 14 – 19 Possible Locations (depending on availability) Outside Airport Intramural Fields West Lafayette High School McAllister Park Inside Mollenkopf Athletic Center Lambert Fieldhouse Armory
10
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 10 Flight Test Plan Objectives Unpowered Glide Stability Lifting Capabilities Straight Line / Turning Flight Include Take Off and Landing Endurance Flying Qualities
11
[ 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 ]1234567891011 March 22, 2005 11 Summary Aircraft 3-View Overall Schedule Economic Plan Flight Test Plan Questions?