SPV SPV Working Group Taimore Afzal (Sellafield) – Chair Alan Wattling (EDF) Luis Yague (Confrentes – Iberdrola) Lubos Herak (Slovenské elektrárne) Ulf.

Similar presentations


Presentation on theme: "SPV SPV Working Group Taimore Afzal (Sellafield) – Chair Alan Wattling (EDF) Luis Yague (Confrentes – Iberdrola) Lubos Herak (Slovenské elektrárne) Ulf."— Presentation transcript:

1 SPV SPV Working Group Taimore Afzal (Sellafield) – Chair Alan Wattling (EDF) Luis Yague (Confrentes – Iberdrola) Lubos Herak (Slovenské elektrárne) Ulf Johansson (Vattenfall) Sam Harvey (EPRI) Alessandro Sarish (Electrabel) Mario Gluhak (Krsko)

2 SPV Aim of the working group Identify single point vulnerabilities and manage the associated risk

3 SPV Objectives Assess the maturity of the community Share learning and process best practice Share specific practical (equipment) examples Produce implementation guidance

4 SPV How would we develop in practice Benchmarking/Maturity questionnaire Produce a form to help capture equipment examples Produce implementation guidance

5 SPV Survey

6 SPV Survey Results 9 Responses –Sellafield, CNNO,FENOC, Daya Bay, KHNP, Krsko NNP, EDF x 2, Borssele NNP Best/Good Practice recommendations from –EDF Energy –Daya Bay –KHNP

7 SPV Template

8 SPV Methodology SPV Definition (What?) Analysis (How?) Mitigation/Elimination Strategy (What?) Implementation (How?)

9 SPV SPV Definition Power reduction threshold at which an SPV is designated –20%, 10%, 5%, > 2% ? –Short duration limited conditions of operation (LCO) –12 hour delay in returning to full power after refuelling Graduated calibration Action – collate all definitions and formulate a positioning paper (T. Afzal)

10 SPV Analysis (How deep do you go?) Definition of LRU (Lowest Replaceable Unit); referring to the lowest maintainable item, which in some cases may be a large module Designation at ‘Large’ component level and mitigation targeted at sub component level Action – Develop guidance on Analysis (A. Sarich)

11 SPV Actions Communicate Definition and develop guidance (All – 1 month) Guidance on Analysis (A. Sarich – 1 month) Guidance on mitigation (U. Johansson – 1 month) Guidance on Optioneering (T. Afzal – 1 month) Guidance on day-to-day management (A. Wattling - 1 month) Develop story board (A. Watling – 1 month) Development of Loss data template (L. Yague – 1 month) Disseminate Example template for ALL to contribute


Download ppt "SPV SPV Working Group Taimore Afzal (Sellafield) – Chair Alan Wattling (EDF) Luis Yague (Confrentes – Iberdrola) Lubos Herak (Slovenské elektrárne) Ulf."