Download presentation
Presentation is loading. Please wait.
1
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO Meeting—RAL September 7, 2009
2
MICO:Zisman2 Spectrometer Solenoid Status (1) Vendor working on both magnets in parallel —magnet 2 being modified to accommodate additional 1-stage cooler —magnet 1 being modified to accommodate 4 th 2-stage cooler o with room for a single-stage cooler as well, if needed Single-stage cooler ordered and expected at vendor about mid-October Cooler tests have been performed on three new 2-stage coolers —all provide ~1.2 W in recondensing mode o same results as found in tests of previous devices
3
September 7, 2009MICO:Zisman3 Magnet 2 Turret Mods Magnet 2 turret partially disassembled —being extended to accommodate new 1-stage cooler beyond HTS leads New cooler goes here Mount for HTS leads
4
September 7, 2009MICO:Zisman4 Cryocooler Stage 1 Connections Cryocooler connection pieces made from OFHC copper —straps connect plates to permit flexible mounting of drop-in coolers o additional copper plate will be used to attach new cooler to leads
5
September 7, 2009MICO:Zisman5 Vacuum Feedthrough RT-70 K feedthrough will be tested to confirm thermal properties
6
September 7, 2009MICO:Zisman6 Magnet 1 Modifications Changes to permit 4 th 2-stage cryocooler are proceeding in parallel with magnet 2 fixes —hope is to have magnet 1 ready soon after magnet 2 is retested o should minimize schedule delay even if magnet 2 changes do not solve all problems –high likelihood of being able to train magnet 2 to full current –no guarantee that magnet 2 will operate without needing “top-up” of cryogens carrying out thermal calculations now to examine this, but real proof awaits testing
7
September 7, 2009MICO:Zisman7 Magnet 1 Cold Mass Additional connection for 4 th 2-stage cryocooler has been created New connection for cooler added
8
September 7, 2009MICO:Zisman8 Magnet 1 Shield Corresponding hole added to shield —shield will also be “beefed up” locally to improve heat transfer to edges o this is where cold-mass support intermediate temperature point is connected –extra heat load from higher temperature at this point is burden for stage 2 of coolers probably more of an issue than bulk radiation load New connection for cooler added Area where cold- mass support intercept attached
9
September 7, 2009MICO:Zisman9 Spectrometer Solenoid Plans Continue with magnet 2 training to reach 265 A or beyond Continue work on magnet 1 —about 2 months behind magnet 2 at present Evaluate power supplies to test proposed circuit modifications —this is “external” and thus less pressing —expect to do this with magnet 2
10
September 7, 2009MICO:Zisman10 RFCC Module (1) Cavity fabrication mostly completed (5 ea.) —waiting for special order of tubing for cooling lines o need mill run for this, as original supplier could not provide from stock —expect 5 cavities in hand by the end of this year Coupling coil delays continue —mainly due to administrative difficulty in getting production contract placed with vendor o HIT summer vacation prevented getting this done sooner —another issue is lack of complete set of fabrication drawings o ICST task, but it is not happening –anticipate need to augment ICST design effort with LBNL staff (DeMello) “natural” solution for interface matters, but was not anticipated for routine production drawings o critical because vendor (Qi Huan) contract is “build to print” –MUST have drawings to proceed with vendor fab!
11
September 7, 2009MICO:Zisman11 RFCC Module (2) Hard to see MuCool CC delivered before next summer We are continuing to do what we can to expedite matters —“action at a distance” is a challenge o for Li Wang o for LBNL staff
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.