GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.

Similar presentations


Presentation on theme: "GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule."— Presentation transcript:

1 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 05/24/05 Elliott Bloom SU-SLAC Subsystem Manager Ken Fouts SU-SLAC Subsystem Engineering Manager elliott@slac.stanford.edu, kfouts@slac.stanford.edu 650-926-2469 650-926-2553 Gamma-ray Large Area Space Telescope

2 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 2 Last Month's Accomplishments (1 of 3) Management –Supported Observatory I&T Planning Meeting at GD. –Procedure Status –65 of 68 I&T documents in review/approval cycle. –Tracking hardware shortages for LAT integration. Current shortages: –GRID HTR PWR HARNESS ASSY, LAT-DS-05057 –GRID HTR TEMP SENSOR HARNESS ASSY, LAT-DS-03662 IFCT –Validated EGSE in the grid with EM TEM’s prior to connection to flight HW. –Completed Two-Tower Test –Completed I&T Receiving Tests on TKR 1, 2 and 3. –Completed Bay 5 Tower (TKR/TEM/CAL) installation –Completed Bay 1 TKR Installation –Installed and crimped Grid thermisters and thermocouples.

3 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 3 Online –E-logbook –Added ability to search shift logbook with Google Desktop –Implementing requested improvements –Beyond 2 towers –Housekeeping multi-pen strip chart GUI –Parallelizing INT scripts –Attempting to move some LATTE 5 features into production (e.g., HSK, LATc) –Continued supported of CAL, TKR, TRG, INT and test suites. –Supported data taking, trigger and E2E script development. –Problem assessment and fixes are a large part of online workload –NCRs, support for clean room operations, support of subsystems scripts. –CCB activity and JIRA maintenance Last Month's Accomplishments (2 of 3)

4 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 4 SVAC –Successful turn around for calibration of two tower data –ready before data taking started –Joint effort TKR/CAL/SAS/SVAC –Offline data processing system under CCB and working well –Single tower data analysis –No show stoppers yet –Generated several special test requests –Good start with two tower data –Data is being analyzed in details –No major problem identified so far Last Month's Accomplishments (3 of 3)

5 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 5 Power Outage Impact on I&T Emergency Generator allowed work to continue in B33 TKR 3 was installed on Thursday Room 103 circuit breaker/panel fault was resolved by turning off non-essential power. The current plan to resolve the B33 Room 103 power issue is as follows: –SEM will procure several 150A breakers to replace the current main breaker in the power box as time (and testing) permits. –Several temporary power drops will be added to the office area on a separate circuit so that computers can be powered up and desk lamps can be used in the desk and board area outside of the clean room. –SEM will verify the power panel arc flash calculations, write and execute the procedures to open the panel for inspection and load measurements in the current state (only 6 out of 42 breakers on). –At the completion of TVAC on Wednesday, SEM would begin work to replace the main breaker and determine the panel loads in more detail as the remaining breakers are turned back on. 4 hour shutdown is planned for Wednesday. Our goal is to safely bring the building back to 100% with minimal impact to building users.

6 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 6 I&T MGSE/Grid Activities Tower A & B in the Grid Mass simulators installed EM PDU and GASU EGSE shelf and cable service loop EGSE harness routing Harness service loop

7 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 7 I&T NCRs by Month Open/Closed Status Month NCR Opened Current Status As of May 23rd Previous Month

8 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 8 Procedure Status 68 documents total 65 latest versions submitted for sign-off 59 are released

9 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 9 Procedure Status (1 of 6) – Management

10 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 10 Procedure Status (4 of 6) – IFCT Electrical

11 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 11 Upcoming I&T Events –Two tower test (Complete) –Receiving tests for TKR 2 (Complete 5/13) –Receiving tests for TKR 1 (Complete 5/11) –Receiving tests for TKR 3 (Complete 5/16) –Receive TEM/TPS 1 and 2 ECD 5/9 (Complete 5/19) –TKR 2 in Bay 5 (Complete 5/17) –TKR 1 in Bay 1 (Complete 5/19) –CAL/TEM Installation in Bay 5 ECD 5/24 –CAL/TEM Installation in Bay 1 ECD 5/25 –4 Tower Tests ECD 6/7 –Receive TEM/TPS 3 and 4 ECD 5/16 5/26 –Receive TKR 4 ECD 6/9

12 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 12 I&T Detail Schedule (1 of 4)

13 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 13 I&T Detail Schedule (2 of 4)

14 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 14 I&T Detail Schedule (3 of 4)

15 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 15 I&T Detail Schedule (4 of 4)

16 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 16 I&T 6 Month Look Ahead (1 of 2)

17 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 17 I&T 6 Month Look Ahead (2 of 2)

18 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 18 Issues & Concerns ISSUES Availability of flight assembly hardware. –Shortages identified by I&T and being worked with Subsystems. Flight Cables CONCERNS Continued support for NCR closure. Resolution of Room 103 power issue. TPS rework and replacement, availability for future tower installations. Delivery dates for third layer ELX boxes and TKR. LATTE 5.0 ready Oct. 1 for use in LAT Functional testing due to start 10/14. E2E tests start 11/1.

19 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 19 “Issues” for single tower tests: offline analysis “Issues” for single tower tests: offline analysis CAL_HI and CAL_LO fired without any crystal hits –Most likely due to direct deposition in diodes CAL_HI trigger fired without high energy deposition – Most likely due to direct deposition in diodes Discrepancy between TKR occupancy on top GTRC’s between DATA and MC in electronics space (generated STRXX) –Most likely due to the differences in particle composition between DATA and MC –Maybe a small fraction could be from CC FIFO buffers filled up in data (this is a feature not a bug) Discrepancy between Data and MC for TKR dead channel list –Partially disconnected channels are not simulated Discrepancy calculated and measured event size (generated STR3) –Miscalculations based on wrong assumptions for event multiplicities Discrepancy between GEM and TriggerAlg for trigger types –Analysis software (TriggeAlg) is not a realistic representation of GEM since it does not address threshold/calibration differences Discrepancy in trigger rates for 1,5,10 and 20 KHz runs, underestimated for low rates and overestimated for high rates at a few % level –Rates from generator were not known to better than a few %, so it is consistent with measurements –overestimation had to do with deadtime since some events did not make into the stream Compared events that triggered BOTH the TKR and EXT pulse generator running at 20KHz with events that trigger TKR only, former had lower hit multiplicity (generated STR8) –Reason was that when a trigger window was opened (on raising edge) by EXT the TKR signal was already on for some time which means some of the hits already died away by the time we looked at. Expect this to be more frequent a higher rates Distribution for TKR trigger arrival times was not flat –Needed to select EXT trigger to open the window and then make the same plot and naturally the spike disappears There is consistently 10-15% more triggers seen during the 5 and 10kHz runs than expected as measured by the exponential fit to the delta event time register of the GEM. TKR only triggers is around 85% (TBR) of the time when the muon telescope triggers Under investigation Investigation has not started Closed

20 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 20 The Oscar goes to…

21 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 21 Two Tower Tests Baseline Run : Flight Configuration There are 234664 triggers There are 0 events with Trigger Parity errors There are 0 events with Packet errors There are 20 events with TEM errors Time of first trigger: Thu May 5 20:48:41 2005 (GMT) Time of last trigger: Thu May 5 21:48:42 2005 (GMT) Duration: 3601 seconds Rate: 82 hz Reconstructed positions 79% single track events 14% two-track events Calibrated Energy Spectrum Expected to peak at 100 MeV

22 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 22 Time Between Events: Baseline Run As expected 26.5 us !

23 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 23 Two Tower Tests Baseline Run : Reconstructed Z Direction Tracks passing through 1 tower only Tracks passing through both towers Tracks coming from top of the tower Cos  = -1 Maximum trigger acceptance is reduced and is consistent with expectations based on geometrical calculations Selection cuts: Single track events Ratio between predicted and measured MIP > 0.7 and < 1.3 From Anders…

24 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 24 Two Tower Tests Baseline Run : Sum of Crystal Energies in the CAL Tracks passing through 1 tower only Tracks passing through both towers Energy calibrations work within a tower and across towers Energy in MeV Selection cuts: Single track events Ratio between predicted and measured MIP > 0.7 and < 1.3

25 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 25 Two Tower Tests Baseline Run : MC vs DATA Tower 0 Tower 4 From Dave…

26 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 26 Science Data vs. Housekeeping Data Tower 0, bottom layer Tower 0, top layer Tower 4, bottom layer Tower 4, top layer Time Temperature Hit multiplicity From Xin…

27 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 27 Priorities for Data Analysis for 2 towers We proposed to the Collaboration to analyze these runs first –We are identifying names to be attached to the list below –1/1 – baseline –Check trigger types and rates, event sizes, raw and recon distributions for tracks within one tower and across towers –Monte Carlo comparison –2/1,2/2 – baseline and change PDU PS values –First time we have a Power Distribution Unit. Could it be a source of noise? If so, can the raw distributions tells us? –2/6, 2/7 – read TKR from Left or Right only –Cable lengths are different between odd and even numbered towers, but the DAQ takes that into account. Let’s check it by comparing raw and recon distributions from both towers. Select events that triggered at the center and at the edges –4/1 to 4/4 – baseline with pulse generator @ 1,5,10,20 kHz –Muon distributions should not be affected by high rates from pulse generator –Do we understand the deadtime? –B2 – nominal settings TEM diagnostics enabled –It is just like 1/1 but with TEM diagnostics ON –B10 – CAL HE muon gain, 4 range readout, TEM diagnostics enabled –Calibrate TOT –measure dead strips –Calibrate edges of crystals –B13 – CAL HE muon gain, 4 range readout, Zero Suppression disabled –Check pedestals in the CAL –Trend pedestals, muon peaks, log ratios, what else?

28 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 28 Wrapping up… Good start with two tower data –Runs finished this morning –Will distribute data to Collaboration today More to come… –Join us in the Instrument Analysis Weekly Meetings –Friday 8 am PDT (VRVS) –Still looking for more people… –Our web site http://www- glast.slac.stanford.edu/IntegrationTest/SVAC/Instrument_ Analysis/Instrument_Analysis.html

29 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 29 Cost/Schedule Reports for Presentation April 2005 Month End 4.1.9 Integration & Test Gamma-ray Large Area Space Telescope

30 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 30 Level 3 Milestone Count

31 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 31 Level 3 Milestone List

32 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 32 Milestone Variance Explanation Schedule Impact –None Cost Impact –None Corrective Action –Not required

33 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 33 Cost Report

34 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 34 Cost Variance Explanation Why overrun/underrun? –Currently on plan What will be done to correct? –Stay the course

35 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 35 FTE Report (DOE/NASA-funded only)

36 GLAST LAT Project Technical/Cost/Schedule Review 05/24/05 4.1.9 - Integration and Test 36 FTE Variance Explanation Why overrun/underrun? –Small overrun due to use of additional SLAC services for machining What is the impact? –None What will be done to correct? –N/A