Cost Drivers Affecting Deployment of COTS-Based Systems Jeffrey Poulin and Walt Johnson Jeffrey.Poulin,W.A.Johnson @ lmco.com (607)751-6899 Lockheed Martin Systems Integration Owego, NY
2
Agenda Overview of COTS programs Cost drivers used in sizing model Requirements history Impact of cost drivers and requirements Lessons learned
3
Program A Purpose: Migrate data from 100+ applications into a data warehouse for common data mining. Size from Cost Model: –4375 Function Points –3.5m SLOC COBOL –50k SLOC Java/other Technologies used: –IBM System 390/MVS –DB2 Database –Datalogic GUI Builder –PRISM code generator for COBOL –Various APIs
4
Cost Drivers for Program A
5
Requirements Volatility for Program A Change Requests –Release 1: 61 –Release 2: 34 –“Not a large cost driver” (Managed by stable Configuration Management Process) Business Rules: –15 planned –100+ actual –Caused multiple design iterations of DB Schema
6
Cost Impact to Program A Cost impact as a function of planned vs. actuals: –Release 1: 5.1x –Release 2: 2.2x –Overall: 2.6x Lessons Learned: –Insist on complete documentation of business rules and legacy data. –Diverse nature of interfaces demanded custom handling and limited reuse.
7
Program B Purpose: Develop and integrate products for processing addresses on mail pieces using optical character recognition Size from Cost Model: –158k SLOC of development –180k SLOC of reuse –10 major suppliers of COTS components Technologies used: –IBM Risc System/6000 with AIX –Oracle Database –Visual Studio –Java/J-Builder GUI –Various APIs
8
Cost Drivers for Program B Total System Solution- 55% –System Design –Software development –COTS licenses –Integration of COTS and existing components (black-box) –Hardware Network- 13% Project management- 10% Interface development- 7% –To all legacy systems Training – 1% Support- 13% –Maintenance –Enhancements
9
Requirements Volatility for Program B Requirements –June 1998: 543July 1999: 934 –Aug 1999: 1208Oct 1999: 1299 –Feb 2000: 1186Dec 2000: 963 41.8% Fluctuation
10
Change Requests for Program B 5.1% CR rate Not a major impact
11
SLOC History of Program B High correlation between cost model prediction and EAC Inability to maintain COTS-based vision
12
Cost Impact to Program B Cost impact based on Estimate at Complete: –Release 1: 1.05x –Release 2: 1.11x Lessons Learned: –Necessity of managing customer expectation in COTS-based environment –Requirement to adapt customer business processes to obtain vision of using COTS-based solutions (very difficult!)