Download presentation
Presentation is loading. Please wait.
Published byReynard Underwood Modified over 9 years ago
1
A127 Ardleigh Green Bridge replacement - update EPAGRA Meeting 2 July 2015 Ardleigh Green Bridge replacement – update
2
A127 Ardleigh Green Bridge replacement - update Alison Scammell – TfL Communications Manager Michael Burgess – TfL Assistant Project Manager Kevin Holland – TfL Traffic Management Specialist Nick Atkinson – Hochtief (UK) Public Liaison Officer
3
A127 Ardleigh Green Bridge replacement - update
4
Why are we replacing the bridge? Structure has come to the end of its serviceable life Train clearance distances not currently adequate Concrete corrosion – at risk of falling onto railway Corrosion of metalwork in the bridge Cracking of brickwork Highway strength not sufficient Carriageway width restrictions poses risk to road users
5
A127 Ardleigh Green Bridge replacement - update Concrete corrosion Steelwork corrosionFailing brickwork
6
A127 Ardleigh Green Bridge replacement - update Works split into two phases: Advance works Advance works in progress New service bridge to carry utilities Due to complete mid 2016 Main works Demolition and replacement of the main bridge Between mid 2016 and end 2017 Completed by 2017
7
A127 Ardleigh Green Bridge replacement - update Lane closures – A127 Some short term lane closures eg autumn 2015 one lane in each direction closed 24/7 for six weeks Overnight closure around Christmas 2015/2016 During bridge replacement works (mid 2016 – end 2017) only two lanes operational (one in each direction)
8
A127 Ardleigh Green Bridge replacement - update Expected traffic congestion Along A12 Colchester Rd and M25 (between Junctions 28 and 29) Increase of vehicles approaching Gallows Corner Small increase in traffic around Romford (A1251 Mercury Gardens increase of around 20 vehicles per hour) Slewins Lane & Squirrels Heath – increase of around 10-20 vehicles per hour
9
A127 Ardleigh Green Bridge replacement - update TfL action Adjusting signals at pinch points Advance notices of alternative routes Monitor the situation & take real time action Plan ahead for different scenarios
10
A127 Ardleigh Green Bridge replacement - update Bryant Avenue exit onto A127 Two periods of closure: Early 2016 for about four weeks Summer 2016 for about nine months
11
A127 Ardleigh Green Bridge replacement - update Reasons for closing Bryant Ave exit: To provide sufficient space for the working area near the bridge. A protective barrier needs to be in place on the bridge to stop vehicles driving onto the railway and into the works site. The new bridge will be higher than the current bridge. Raising the road surface requires steps to be in place at times during the works, which are unsuitable for traffic. Utilities (water, gas etc.) need to be diverted below and near the Bryant Avenue traffic island (requiring a shorter closure of Bryant Avenue in early 2016).
12
A127 Ardleigh Green Bridge replacement - update
13
Communications Working with LB Havering Letter drops Drop in information session Social media Press briefings Website - www.tfl.gov.uk/ardleigh-green
14
A127 Ardleigh Green Bridge replacement - update Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.