Download presentation
Presentation is loading. Please wait.
Published byBasil Floyd Modified over 9 years ago
1
TDC2/TCC2 consolidation EATM 15/07/2014
2
EN/EL – DC and control cable identification and cut completed – Old light removal in TDC2 – New AUG installed
3
Demin. circuit valve replacement Remplacement des vannes terminé
4
Unités de ventilation Travaux terminés.
5
XTAX upgrade 12/12 XTAX tables XTAX repaired Still alignment issue for XTAX T4 This week: survey & test on XTAX T6 + roof closure
6
Magnet Manifolds re-installed
7
OTND (Onet nucleaire) Nettoyage 3 eme chateau XTAX OK Démontage passerelle et chemins de câbles en cours
8
OTND (Onet nucleaire)
9
Oculus porte
10
Dose Most critical activitiesCollective dose in uSv 471594186 XTAX table upgrade4186 374052554 Removal, temporary storage and reinstall...2554 197361705 TDC2/TCC2 replace valves1705 438701630 Mesures topographiques TCC21630 447161526 Remplacement flexibles aimants TDC21526 483481104 démantèlement et nettoyage TDC21104 486641063 TDC2 Consolidation works EN/EL/CF - Phas...1063 TOTAL 25000
11
Planning
Similar presentations