Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005
2
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 2
3
3 Beam parameters obtained from the central frequency measurements, averaged over the data obtained from the horizontal and vertical planes.
4
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 4 Results of TI8 test
5
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 5 End of civil engineering works in Point 5 (1st February 2005)
6
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 6 Superconducting cable 1
7
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 7 Superconducting cable 2
8
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 8 Dipole cold masses
9
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 9 Number of quenches to reach 8,33 T at the first cooldown (560 dipoles)
10
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 10 LHC Dipoles: integrated field
11
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 11 Dipole field quality: average b3
12
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 12 Arc quadrupole cold masses
13
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 13 MSCB sextupole dipole correctors
14
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 14 Cryodipole overview
15
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 15 SSS overview
16
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 16 Magnet Installation Installation is progressing in sectors 8-1 and 4-5. More than 100 superconducting magnets have been installed. The installation rate must now ramp up to 20 magnets per week (16 dipoles and 4 SSSs) in the next few weeks. At the end of October, sector 7-8 will be liberated for magnetic installation. From then on there will be no shortage of slots.
17
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 17 First cryodipole lowered on 7 March 2005
18
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 18 First SSS lowered on 19 April 2005
19
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 19 Transport in the tunnel with an optical guided vehicle
20
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 20 Transfer on jacks
21
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 21 Preparation of interconnect
22
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 22 Interconnection of beam tubes
23
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 23 Interconnect in sector 8-1: in progress in sub- sectors C and F
24
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 24 Pre-assembly of first low-beta triplet (hall 181)
25
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 25
26
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 26 UA47: Quench protection & Power converters
27
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 27
28
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 28 Cryogenics overview
29
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 29 2400 W @ 1,8 K in the UX85 cavern
30
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 30 Repair of QRL modules
31
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 31 Repair of special QRL elements at CERN
32
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 32 Cryogenic distribution line
33
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 33 QRL
34
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 34 Reinstallation of QRL in 7-8 Sub-sectors A and B (600 m) have been cooled down on Wednesday 14 th September. After the cold tests, the inner triplet will be installed, cooled down and powered whilst the rest of the line is being installed.
35
First cooldown of 600 m cryogenic LHC line sector 13-14 September 2005 He in He out Th.screen line LHe line Pump. line 20 K line
36
CERN L.Evans & C.WyssINFN CSN1 Napoli September 2005 36 Conclusions Main objectives: –terminate installation in February 2007 –first collisions in summer 2007 The industrial production of standard components is compatible with this objective. The ramping up of QRL activities and magnet installation is critical to maintain this schedule. Additional actions have been implemented to ensure proper QRL production and installation rates. The installation and interconnection of cryomagnets have started in the tunnel. The commissioning of technical systems will take place in two adjacent sectors in parallel. Main next actions: –partial test of sector 7-8 in autumn 2005 –commissioning test of the two first sectors (7-8 and 8-1) in summer 2006 –find external collaborators to help with commissioning. => many thanks to INFN for its support !