From… Maintenance Technical Advisory Guide (MTAG) Chapter 7 Isolated Partial Depth Concrete Repair
2
Partial-Depth Repairs 3-4.2
3
Learning Objectives 1.List benefits of partial-depth repairs 2.Describe the advantages and disadvantages of different available repair materials 3.Describe recommended construction procedures 4.List important quality control activities 5. Describe potential unexpected adjustments or construction quality problems 6. Identify troubleshooting solutions
4
Presentation Outline II ntroduction DD esign considerations CC onstruction QQ uality control TT roubleshooting
5
Removal and replacement of small, shallow areas of deteriorated PCC at spalled or distressed joints. Definition Introduction Distress limited to upper 1/3 of slab Existing load transfer devices are functional
6
Benefits Restores structural integrity Improves ride quality Extends the service life Restores a well-defined uniform joint sealant reservoir
7
Good Candidate Projects Spalling associated with joint inserts Spalling caused by intrusion of incompressibles Spalling associated with localized areas of scaling, weak concrete, clay balls, or high steel
8
Poor Candidate Projects Joint spalling associated with dowel bar misalignment or lockup Spalled cracks Spalling associated with durability problems or reactive aggregate
9
Good candidate?
14
Presentation Outline II ntroduction DD esign considerations CC onstruction QQ uality control TT roubleshooting
15
Design, Materials & Specifications From… Maintenance Technical Advisory Guide (MTAG) Module 7-1
16
Design Considerations Selecting repair boundaries Material selection Curing Opening to traffic
17
DULLSHARP Unsound-DelaminatedSolid Sounding the pavement: Hammer Steel rod Steel chain Selecting Repair Boundaries Detecting Deteriorated Concrete
18
Selecting Repair Boundaries Sounding
19
Selecting Repair Boundaries Repair Dimension Recommendations Minimum dimensions Length: 300 mm (12 in) Width: 100 mm (4 in) Depth: 50 mm (2 in) Extend repair 75 to 100 mm (3 to 4 in) beyond visible deterioration Combine close patches (<0.6 m [2 ft]) Repair entire joint if > 2 patches
20
Cementitious PCC-based Gypsum-based Magnesium phosphate High alumina Polymeric Epoxy Methyl methacrylate Polyester-styrene Polyurethane Bituminous Material Selection Repair Material Types
21
Enhances repair to pavement bond Sand-cement grouts used with PCC repair materials Epoxy bonding agents used with both PCC and proprietary materials Material Selection Bonding Agents
22
Material Selection Factors Allowable lane closure time Ambient temperature Cost Size of repair Estimated performance
23
Curing Cure to avoid shrinkage cracks Hot-weather curing—curing compound, moist burlap, or polyethylene Cold-weather curing—insulating blanket or tarp Follow recommendations for proprietary materials
24
Opening to Traffic Opening criteria Minimum strength (20.7 MPa [3,000 psi]) Minimum time Opening based on actual PCC strength is preferred
25
Typical Item Codes Item CodeDescription 120090Construction area signs 120100Traffic control system 128650Portable changeable message sign 150846Remove concrete pavement 150306Repair spalled concrete 156515Repair spalled and unsound surface area 401108Replace concrete pavement (rapid strength concrete 413101Repair corner breaks 413111Repair spalled joint 413114Replace joint seal (existing concrete pavement) 413115Seal joint (existing concrete pavement) 420201Grind existing concrete pavement 511040Concrete surface finish 511055Concrete surface texture 515028Repair spalled surface area http://i80.dot.ca.gov/hq/esc/oe/awards/#item_code
26
Construction and Inspection From… Maintenance Technical Advisory Guide (MTAG) Module 7-2
27
Presentation Outline II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting
28
Construction Steps 1.Marking repair boundaries 2.Concrete removal 3.Repair area cleaning 4.Joint preparation 5.Bonding agent application 6.Patch material placement 7.Curing 8.Joint sealing
29
Marking Repair Boundaries
30
Concrete Removal Saw-and-patch (recommended) Chip-and-patch Mill-and-patch Hydrodemolition
31
Concrete Removal Saw-and-Patch Method
32
Concrete Removal Chip-and-Patch Method
33
Concrete Removal Mill-and-Patch Method
35
Concrete Removal Hydrodemolition
36
Repair Area Cleaning Sandblasting
37
Repair Area Cleaning Air Blowing
38
Joint Preparation
39
Plan View Profile View Bond breaker Patch Pavement 75 mm (3 in) Scoring 25 mm (1 in) Joint Joint Preparation
40
Bonding Agent Application Patch area must be clean Application techniques Coat horizontal and vertical surfaces Apply uniformly
41
Bonding Agent Application
42
Patch Material Placement General Guidelines Batch small quantities Temperature recommendations Some epoxy materials placed in lifts Overfill patch area by ~3 mm (1/8 in) Consolidate material Screed and hand trowel
43
Patch Material Placement Grout Mixer
44
Patch Material Placement Adding Admixture
45
Patch Material Placement Mixing an Epoxy Patching Material
46
Patch Material Placement Consolidation
47
Patch Material Placement Finishing
48
Curing
49
Joint Sealing
50
Finished Patch
51
Construction Process
52
Presentation Outline II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting
53
Quality Control Verify repair boundaries Monitor to assure no damage to surrounding concrete Inspection of repair preparation material placement, and finishing Proper curing techniques
54
Quality Control Class Exercise Break into three groups Preliminary responsibilities Equipment inspection, weather requirements, and traffic control Construction inspection considerations Identify importance of each item Use Reference Manual and your experience
55
Project Checklist Preliminary Responsibilities Document Review Project Review Materials Checks Concrete patch material Other materials Joint Sealing General
56
Project Checklist Equipment Inspections Concrete Removal Equipment Patch Area Cleaning Equipment Mixing and Testing Equipment Placing and Finishing Equipment Other Equipment Others Weather Requirements Traffic Control
57
Project Checklist Project Inspection Responsibilities Patch Removal and Cleaning Patch Preparation Placing, Finishing, and Curing Patch Material Resealing Joints and Cracks Cleanup Responsibilities
58
Presentation Outline II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting
59
Troubleshooting Identify Problem Determine Cause Identify Solution Unexpected adjustments and construction quality problems Approach:
60
Deterioration beyond original boundaries Troubleshooting Unexpected Adjustments Solution? Problem
61
Deterioration deeper than upper 1/3 of the slab thickness Troubleshooting Unexpected Adjustments Solution? Problem
62
Troubleshooting What is wrong here?
63
Patch material flows into joint Troubleshooting Construction Quality Problems Potential causes? Problem
64
Cracking or debonding of patch material Troubleshooting Construction Quality Problems Potential causes? Problem
65
Troubleshooting Guide – Causes and Solutions More deterioration than expected Exposed steel Patch material in crack or joint Patch cracking
66
Presentation Outline Introduction Material selection Construction Quality control Troubleshooting
67
Learning Objectives 1.List benefits of partial-depth repairs 2.Describe the advantages and disadvantages of different available repair materials 3.Describe recommended construction procedures 4.List important quality control activities 5. Describe potential unexpected adjustments or construction quality problems 6. Identify troubleshooting solutions