Presentation is loading. Please wait.

Presentation is loading. Please wait.

Status of CLAS12 PCAL project

Similar presentations


Presentation on theme: "Status of CLAS12 PCAL project"— Presentation transcript:

1 Status of CLAS12 PCAL project
S. Stepanyan JLAB

2 Agenda of the meeting Project status - Stepan Stepanyan
PCAL cosmic tests, experience with fADCs - Cole Smith PCAL installation, mounting fixture, schedule - Bob Miller Plans for EC PMT repairs - Cole Smith FADC as time measuring device and as a real-time scalers - Sergey Boiarinov/Chris Cuevas Electronic cables, tests and fixes - Gegham Asryan AOB 2/20/13 CLAS12 workshop, Feb. 20, 2013

3 CLAS12 PCAL To contain full shower from high energy (> 6 GeV) electrons and photons, and to resolve close clusters from high energy p0 decay Alternating layers of lead sheets (2.2 mm) and scintillator strips (10 mm) with three stereo readout views, UVW (5 layers per readout view), total of 5.5 r.l. Extruded scintillator strips, 4.5x1 cm2, with two holes along the strip for light readout (FNAL), 84 strips in U-layer, 78 strips in V- and W-layers Light transport from scintillator to PMT via 1 mm diameter green wave-shifting fibers from Kuraray inserted inside the holes in the strips, 2 fibers per hole Total number of readout channels 1152 (6x192) 2/20/13 CLAS12 workshop, Feb. 20, 2013

4 CLAS12 PCAL: Status update 02/20/2013
Four out of fully assembled five modules are tested By the end of the month, cosmic test of the Module-V will be in progress, and stacking of the last module will start It is expected to complete assembly of Module VI in June, 2013 Four PCAL modules are now ready for installation Design of the installation is started and should be ready in June-July, 2013 Estimated time for installation, including cabling, is 2-3 weeks/module ESB EEL 5 2 1 3 4 2/20/13 CLAS12 workshop, Feb. 20, 2013

5 QA&C: scintillators, fibers, lead sheets
As part of QA&C, the following measurements have been performed for all modules: Light yield for several points along the scintillator strips for strips L>200 cm (since from the original production piece two scintillators have been cut one with L>200 cm and another L<200 cm, light yield measurements of the longest will determine the quality of the shorter one) Light transmission of 20% of fibers from each batch Thickness of lead sheets at several uniformly distributed points Outcome of QC measurements: Only one scintillator has been rejected so far, Sector 6, W63, Layer 3 (only 4 layers left to measure, out of 90 layers) Few lead sheets were rejected due to corrosion, waviness or incorrect dimensions 2/20/13 CLAS12 workshop, Feb. 20, 2013

6 Bad strip: Sector 6, W63, Layer 3
Several measurements have been made with different fibers Measurements with similar length strip were alternated to make sure system is stable 2/20/13 CLAS12 workshop, Feb. 20, 2013

7 Scintillators and fibers for five modules
Light yield (pedestal subtracted) at the end of the fiber (480 cm from the PMT). Light is generated with small piece of scintillator. Light yield (pedestal subtracted) at 10 cm from the near edge. Fiber length from the edge of the strip to PMT ~25 cm 2/20/13 CLAS12 workshop, Feb. 20, 2013

8 Lead sheets 28 right angle triangular sheets per module
Thickness at 36 points per sheet is measured using ultrasonic thickness gauge Design range for thickness mm to 2.31 mm Note: Graphs include all 36 points of 28 sheets for each module 2/20/13 CLAS12 workshop, Feb. 20, 2013

9 What next Finish test of Module 5 Finish assembly and test of Module 6
Repair PMTs on EC modules in the Hall, cable and check Install PCAL modules, cable and check Collect spears and useful leftovers (scintillators, PMTs, dividers, mu-metals shields, connectors, fibers, cables) Write a geometry document for the reconstruction and simulation software Write a NIM article 2/20/13 CLAS12 workshop, Feb. 20, 2013


Download ppt "Status of CLAS12 PCAL project"

Similar presentations


Ads by Google