Herriman City Municipal Water PowerPoint Presentation March 10, 2011.

Similar presentations


Presentation on theme: "Herriman City Municipal Water PowerPoint Presentation March 10, 2011."— Presentation transcript:

1 Herriman City Municipal Water PowerPoint Presentation March 10, 2011

2 System Maintenance  Service of Booster Pumps & Wells  Fire Hydrant Flushing  Valve Exercising  Tank Cleaning

3 Service Of Booster Pumps & Wells Shut Down Power/Lockout-Tagout Disassemble Pump Clean All Parts Replace All Bearings, Packings & Seals Repair Or Replace Other Parts As Needed Reassemble Pump Realign Pump Lubricate With Ultra Sound Equipment Test & Bring Back On Line

4 Pump Shaft Alignment Ultra Sound Equipment

5 Fire Hydrant Flushing & Valve Exercising Annually We Flush & Inspect All Fire Hydrants & Dead Ends With The Assistance Of Unified Fire Fully Close & Reopen Each Valve In Our Water System

6 Tank Cleaning Clean, Inspect & Video Every 3-5 Years Why? This Provides Us With Visual Conditions Of The Inside Of Our Tanks This Allows Us To Clean The Tanks Without Taking Them Off-Line. All Our Water Tanks Were Cleaned In November 2010

7 Projects Well 1 Booster Station Chlorine & Fluoride Analyzer 5600 W Culinary & Secondary Water Lines Early Stages of Implementation Of Secondary Water System Mountain View Corridor Betterments

8 Well 1 Booster Pump Station Completed

9 Chlorine & Fluoride Analyzer Installed At Well 1, HP Tanks & The RoseCrest Booster Pump Station Provides Trending Of Fluoride & Chlorine Levels Connected To The SCADA System Which Allows Off Site Tracking & Control Of Chemical Levels. Analyzers Provide Additional Safety To The Water System & Our Residents

10 Silver Spur Construction Won Bid Project Will Begin March 16, 2011 This Project Has A Completion Time Of 90 Days

11 Secondary Water System Secondary Water Rate Study-Bowen Collins Project Will Go Out To Bid Early Summer Purple Shaded Area Will Be First Area To Receive Secondary Water

12 Mountain View Corridor March 2011 There Is A 32” Culinary & 10” Secondary HDPE Pipe The Betterments Are Approximately 50% Completed Trench is 32’