Presentation is loading. Please wait.

Presentation is loading. Please wait.

EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Air Force Research Laboratory Air Base Technology Branch AFRL/MLQC Tyndall AFB FL Randall W. Brown, PhD,

Similar presentations


Presentation on theme: "EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Air Force Research Laboratory Air Base Technology Branch AFRL/MLQC Tyndall AFB FL Randall W. Brown, PhD,"— Presentation transcript:

1 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Air Force Research Laboratory Air Base Technology Branch AFRL/MLQC Tyndall AFB FL Randall W. Brown, PhD, PE Principal Engineer Airfields &Pavements Group

2 OVERVIEW Background Findings/Solutions Repair Process Summary Conclusions

3 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Background

4 BACKGROUND KEY EVENTS: 2 FEB 99 AFRL/MLQC contacted by HQ AMC on behalf of 89 CES, Andrews AFB MD 10-13 MAR 99 Ground Penetrating Radar (GPR) Investigation 13-15 APR 99 Follow-on GPR Investigation Cone Penetrometer Testing (CPT) Video inspection of airfield culvert 9-20 AUG 99 Repair of “Dip” in Runway 01L/19R at Andrews AFB MD

5 PROBLEM: A 2” dip in Andrews’ runway 1L/19R (The Air Force One Runway) was causing operational problems, particularly for small aircraft. BACKGROUND

6 APPROACH: Identify the Source of the Problem Using: A) Ground Penetrating Radar B) Cone Penetration Testing C) Optical Scan of Drainage Culvert (1) Develop a Suite of Alternative Solutions Considering Cost, Runway Downtime, and Effectiveness (2)

7 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Findings/Solutions

8 FINDINGS/SOLUTIONS FINDINGS: Water Infiltration Poor Backfill Material Leaking Underlying Culvert Loss of Fines Through Culvert Weakened Pavement Support Settlement

9 FINDINGS/SOLUTIONS ALTERNATIVES: SOLUTION SELECTED - FOAM JACKING: Reconstruction (1) Foam Jacking (By-product of FY 98 AFRL research) (2) “Do Nothing” (3) Reduced Downtime (Conservatively 50%) (1) Reduced Cost (Conservatively 50%) (2) Effective Based on Private Sector and AFRL/MLQC Data (3)

10 FINDINGS/SOLUTIONS KEY ELEMENTS Initial Slab Lifting Using Polyurethane Foam Deep Injection Stabilization (Compaction Grouting with Polyurethane Foam) Repair Leaking Culvert Final Slab Alignment Using Polyurethane Foam Route and Seal Joints

11 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Repair Process

12 REPAIR PROCESS PRE-TREATMENT CONE TESTING

13 REPAIR PROCESS PRE-TREATMENT CONE TESTING

14 REPAIR PROCESS DRILLING INJECTION HOLES

15 REPAIR PROCESS SEVERITY OF THE RUNWAY “DIP”

16 REPAIR PROCESS PREPARATION FOR INITIAL LIFTING OF RUNWAY SURFACE

17 REPAIR PROCESS INITIAL INJECTION

18 REPAIR PROCESS PREPARATION FOR DEEP INJECTION

19 REPAIR PROCESS SOIL STABILIZATION THROUGH DEEP INJECTION

20 REPAIR PROCESS EXTRACTION OF COPPER TUBES

21 REPAIR PROCESS FINAL ALIGNMENT

22 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Summary

23 SUMMARY 106 19,172 lbs 2,500 lbs 282.00 hrs - 22.25 hrs 259.75 hrs 126.50 hrs Fri 20 Aug 99, 2400 required completion Fri 20 Aug 99, 1030 actual completion holes injected deep injection foam slab lifting foam gross time available time lost due to ramp freezes net time available actual time working on airfield

24 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Conclusions

25 CONCLUSIONS Estimated Savings (50%) Estimated Downtime Savings (60%) 12 days -- actual repair time using foam 30 days -- optimistic estimate for reconstruction

26 CONCLUSION KEEP HER FLYING!

27 EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Air Force Research Laboratory Air Base Technology Branch AFRL/MLQC Tyndall AFB FL Randall W. Brown, PhD, PE Principal Engineer Airfields &Pavements Group


Download ppt "EXPEDIENT REPAIR OF ANDREWS AFB RUNWAY 01L/19R Air Force Research Laboratory Air Base Technology Branch AFRL/MLQC Tyndall AFB FL Randall W. Brown, PhD,"

Similar presentations


Ads by Google