Diffusion Furnace Controller Design Team 14 Joe Grady James Crow Hongyu Chen Prakalp Sudhakar Victor Villagomez Client/Faculty Advisor: Dr. Gary Tuttle
2
Project Goals The objective of the senior design project is to design a new set of temperature controllers to use on a set of diffusion furnaces located at the Microelectronics Research Center. The project goals include: Updating analog controlled furnace to a digitally controlled furnace. Implementation of a new digital temperature controller integrated into the current microelectronics oven Providing a software interface so that temperature of the furnaces can be controlled and monitored remotely. PlanningDesignImplementConclusion
3
System Overview PlanningDesignImplementConclusion
4
Functional Requirements Controller must have a temperature tolerance within +/- 5 degree Celsius be digital and programmable have communication capability be able to control temperatures independently of each section Software must be able to monitor and control the parameters of the temperature controller to support multiple students to be accessed online via web browser PlanningDesignImplementConclusion
5
Non-functional Requirements The new controllers need to be placed where the old ones were so they need to able to fit within a certain space Connectors must be compatible with the new controller All the schematics and layout designs need to be of industry standards for future reference. Graphical interface of the software must be user-friendly PlanningDesignImplementConclusion
6
Schedule – Fall Semester PlanningDesignImplementConclusion
7
Project Costs ItemCost Two CN616 series controllers$1,250 Four Eagle PCB$200 Steel panel for furnace$65 Opto-isolators$26 Other miscellaneous parts for interfacing circuits $10 (approx.) USB – RS232 (Serial) Adaptor$40 Mac mini$0 PlanningDesignImplementConclusion
8
Risks and Mitigations The amount of inputs on the CN616 controller will not allow us to use all of thermocouples used in the old set-up; in the new setup, there is no differential thermocouple pairs between zones. Each zone is now controlled by a single SCR pair and a thermocouple If the controller has been setup remotely, there is no way to stop someone from adjusting the controller manually There is no way to prevent a user from opening the oven door before process is complete PlanningDesignImplementConclusion
9
Opto-isolator Circuit PlanningDesignImplementConclusion
10
AC Power Configuration PlanningDesignImplementConclusion
11
Thermocouple Layout PlanningDesignImplementConclusion
12
Software System Design Overview PlanningDesignImplementConclusion 1)Sends parameters to webserver 2)Sends commands to controller 3)Sets up furnace 4)Responds to controller 5)Sends feedback to webserver 6)Updates data on browser BrowserWebserver ControllerFurnace
13
Software System Architecture PlanningDesignImplementConclusion
14
Software Use Cases Diagram PlanningDesignImplementConclusion
15
Website UI Flow PlanningDesignImplementConclusion
16
Implementation - Opto- isolator Circuit to CN616 controller PlanningDesignImplementConclusion
17
RS-232 and Power Connections PlanningDesignImplementConclusion
18
Hardware Testing Compatibility testing SCR with our Opto-isolator Circuit PlanningDesignImplementConclusion
19
Software Implementation Technologies Web Browser Module PHP CGI (Common Gateway Interface Web Server Module Apache Controller Comm Module CGI in C UNIX POSIX serial port API PlanningDesignImplementConclusion
20
Software Implementation RS-232 Interface USB to serial adapter for Mac Mini Read Input data CGI Serial Port Open Read Write PlanningDesignImplementConclusion
21
Software Testing Blackbox Testing CubicTest Tools A graphical Eclipse plug-in For writing Selenium and Watir tests. PlanningDesignImplementConclusion
22
Single Oven System Test Connected our opto-isolator circuit to the gates of the SCR Used a power supply to turn on each zone individually Used a multi-meter to verify correct voltages on each zone Replaced the power supply with the controller Made the appropriate thermocouple and control connections Manually set the controller to verify the voltages for each zone PlanningDesignImplementConclusion
23
Project Future PlanningDesignImplementConclusion Set the controllers to PID control to improve overshoot, rise time and settling time Website compatible with more commands Website can be more user friendly by o Temperature data plot o Data saving
24
Conclusions PlanningDesignImplementConclusion Able to meet customer requirements Hardware met specifications Software met specifications
25
Questions ?