TECH 50800 Project Design and Manufacturing Control Process for Formula SAE Analyze Phase Date: 11/19/2014 Team members: Chris Lawrence.

Similar presentations


Presentation on theme: "TECH 50800 Project Design and Manufacturing Control Process for Formula SAE Analyze Phase Date: 11/19/2014 Team members: Chris Lawrence."— Presentation transcript:

1

2 TECH 50800 Project Design and Manufacturing Control Process for Formula SAE Analyze Phase Date: 11/19/2014 Team members: Chris Lawrence

3 Brief Review of Project Charter Purpose of project is to create and implement a process that students must follow in order to produce defect free parts for the vehicle. Desired result is significant reduction in combined design and build time, while improving overall vehicle design and build quality. – Uniform quality standards – Reduced packaging issues: identification of problems before assembly – Only good parts are manufactured (in theory) – More time spent in design (CAD) and less time in build

4 CTQ Tree(s) Part fits/functions in theory (CAD) Approved Design Approved Drawing Part is made to Drawing Design & Mfg Completed to Schedule Critical to Quality Part fits/functions in real life Part has design consistent with car concept KPOV Parts are done on time Approved Concept KPIV Brainstorm process Conceptual Design process Engineering calcs verified CAD Fitment verified GD&T verified Engineering drawing verified Quality control verifies dims Schedule and deadlines VOC/SWOT Summary “Good” Design No Bad Parts Car is done on Time

5 Data is being collected using the process observation worksheet, checksheet, and a weekly progress tracker. All data collected on a weekly basis at minimum Notes on these sheets are very important due to the small quantity of quantitative data Data Collection

6 Graphs

7 Comparison of 2013 vs 2014 System implemented in Fall 2014, comparison of effectiveness of new system Design Cycle StartEndNo. Days 20135/15/20124/26/2013346 20146/6/201411/19/2014166 Manufacturing Cycle StartEndNo. Days 20137/10/20126/2/2013327 2014 (planned)12/1/20143/1/201590 Milestones in Schedule 2013 1: First Drive 2. Competition 2014 1. Brainstorm 2: Conceptual Design 3. Detailed Design 4. Drawings 5 Manufacture of all Parts 6. First Drive 7. First Test (with aerodynamics) 8. Competition

8 Cause and Effect Matrix Inputs are KPIV variables, outputs are KPOV variables Cause and Effect Matrix Formula SAE 0 = no correlation, 1 = low correlation, 4 = moderate correlation, 9 = high correlation Input Approved Concept Approved Design Approved Drawing Passes QA Kept on Schedule Score Notes Days Spent Brainstorm94004 17.00 Days Spent Conceptual Design94004 17.00 Days Spent Detailed Design09449 26.00 Detailed Design is Critial to Process Days Spent Engineering Drawings 00994 22.00 # of Rejections11119 13.00 # of Ignored "Design Tollgates"00009 9.00 # of Missed Meetings44404 16.00 # of Missed Weekly Progress49409 26.00 Consistent Weekly Progrees is Critical

9 Analysis Phase Conclusions Of the KPOV’s, the most important to this project is TIME (Design and Mfg. on Schedule). It affects all of the other KPOV’s. Any KPIV that can adequately track the likelihood of completing the project on time, and/or track the effort being displayed by each system/team member is critical. The most important KPIV variables are – Deadline Pass/Fail and #of days past due – Pass/Fail of progress each week by each system – Detailed Design phase time length, quality (subjective) – Number of milestones: more milestones means earlier detection of problems