FUNDAMENTAL TEST PROCESS
Dr. Wolfgang J. Schneider 2003 – 2006 Dr. Wolfgang J. Schneider
2
FUNDAMENTAL TEST PROCESS
Part 1 Test Planning and Control Dr. Wolfgang J. Schneider
3
Dr. Wolfgang J. Schneider 2003 - 2006
Acknowledgement Most of the content has been developed by ISTQB and it’s affiliates for fair use. The copy right of those parts is with them. The layout has been developed by us. Dr. Wolfgang J. Schneider
4
Fundamental Test Process
INTRODUCTION Many people think that “Testing” means just executing tests. To be effective and efficient, much more time has to be spent on other important tasks. Dr. Wolfgang J. Schneider
5
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
6
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
7
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
8
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
9
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
10
Fundamental Test Process
INTRODUCTION We are talking about: Planning the Tests Designing Test Cases Preparing for Execution Evaluating the Status Dr. Wolfgang J. Schneider
11
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
12
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
13
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
14
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
15
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
16
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
17
Fundamental Test Process
MAIN ACTIVITIES Planning and Control Analysis and Design Implementation and Execution Evaluating Exit Criteria and Reporting Test Closure Activities Dr. Wolfgang J. Schneider
18
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
19
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
20
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
21
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
22
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
23
Test Planning and Control
Verifying the Mission Defining the Objectives Specification of Test Activities (In Order to meet the Objectives and mission) Dr. Wolfgang J. Schneider
24
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
25
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
26
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
27
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
28
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
29
Test Planning and Control
TEST CONTROL Comparing actual Progress against the Plan Reporting the Status (including Deviations from the Plan) Taking Actions necessary to meet the Mission and Objectives of the Project In Order to control Testing, it should be monitored throughout the Project Dr. Wolfgang J. Schneider
30
Test Planning and Control
FEEDBACK Test Planning takes into Account the Feedback from Monitoring and Control Activities Dr. Wolfgang J. Schneider
31
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
32
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
33
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
34
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and interfacing the teams involved in testing “Testware” Dr. Wolfgang J. Schneider
35
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and interfacing the teams involved in testing “Testware” Dr. Wolfgang J. Schneider
36
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and interfacing the teams involved in testing “Testware” Dr. Wolfgang J. Schneider
37
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and interfacing the teams involved in testing “Testware” Dr. Wolfgang J. Schneider
38
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and Interfacing the Teams involved in Testing “Testware” Dr. Wolfgang J. Schneider
39
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and Interfacing the Teams involved in Testing “Testware” Dr. Wolfgang J. Schneider
40
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Techniques Test Items Coverage Identifying and Interfacing the Teams involved in Testing “Testware” Dr. Wolfgang J. Schneider
41
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Human Resources – People Test Environment Hardware like Servers and PCs Dr. Wolfgang J. Schneider
42
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Human Resources – People Test Environment Hardware like Servers and PCs Dr. Wolfgang J. Schneider
43
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Human Resources – People Test Environment Hardware like Servers and PCs Dr. Wolfgang J. Schneider
44
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Human Resources – People Test Environment Hardware like Servers and PCs Dr. Wolfgang J. Schneider
45
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Human Resources – People Test Environment Hardware like Servers and PCs Dr. Wolfgang J. Schneider
46
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
47
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
48
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
49
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
50
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
51
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
52
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
53
Test Planning – Major Tasks
Determining the Scope and Risks Identifying the Objectives of Testing Determining the Test Approach Determining the Required Test Resources Implementing the Test Policy Implementing the Test Strategy Scheduling Test Analysis and Design Tasks Scheduling Test Implementation Scheduling Test Execution Scheduling Test Evaluation Determining the Exit Criteria Dr. Wolfgang J. Schneider
54
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
55
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
56
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
57
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
58
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
59
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
60
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
61
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
62
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
63
Test Control – Major Tasks
Measuring and Analyzing Results Monitoring and Documenting Progress Test Coverage Exit Criteria Initiation of Corrective Actions Making Decisions Dr. Wolfgang J. Schneider
64
DR. WOLFGANG J. SCHNEIDER GMBH
International Information Technology Consultants Professional Testing Solutions Telecommunications and Utility Billing Systems Euro Preparation for Companies in New EU Member Countries EDIFACT – DATANORM – ELDANORM – ETIM Interfaces Data Exchange with Banks and Credit Card Companies Total Quality Management – Good Manufacturing Practices IT Service Management - IT Infrastructure Library (ITIL) Knowledge Management Solutions IT Fitness for GAAP – IAS – FASB Balanced Scorecard Dr. Wolfgang J. Schneider Take Advantage of 30+ Years of IT Experience !