The Systems Analysis Toolkit Project Management Tools
3
Systems Analysis and Design Fourth Edition Systems Analyst’s Toolkit Part 3 Project Management Tools
4
Systems Analysis and Design Fourth Edition Objectives Describe project management tools and how they are used Describe the steps used in project planning Explain the project estimating process Describe the different scheduling tools, including Gantt charts and PERT/CPM charts
5
Systems Analysis and Design Fourth Edition Objectives Calculate completion times, start dates, and end dates for a project Explain the tasks of project monitoring, control, and reporting Explain the steps involved in software change control Understand the reasons why projects sometimes fail
6
Systems Analysis and Design Fourth Edition Introduction The Systems Analyst’s Toolkit explains Project management tools and techniques including planning, estimating, scheduling, monitoring, control, reporting, and the use of project management software Gantt charts and PERT/CPM that can be used to schedule and monitor projects and changes
7
Systems Analysis and Design Fourth Edition Project Management Project management is the process of defining, planning, organizing, leading, and controlling the development of an information system Project management is important throughout the SDLC, and especially during the systems implementation phase
8
Systems Analysis and Design Fourth Edition Project Management Project management overview Goal is to deliver a system that is acceptable to users, on time, and within budget Every project must have a project manager, or project leader Most large projects also have a project coordinator who handles administrative matters and relationships with users
9
Systems Analysis and Design Fourth Edition Project Management Management functions Planning: identifying and planning project tasks and estimating completion times and costs Organizing: staffing, including selecting the project team and assigning responsibilities to team members Leading or directing: guiding, supervising, and coordinating the team’s workload Controlling: monitoring progress, evaluating results, and taking necessary corrective action
10
Systems Analysis and Design Fourth Edition Project Management Project planning A project plan is an overall framework for managing costs and schedules The planning process involves Activities (tasks) Events (milestones) Click to see Figure 3-1
11
Systems Analysis and Design Fourth Edition Project Estimating Factors that project managers must consider Size of the project A project that is twice as large as another will require considerably more than twice the resources As the size of the project grows, the number of interfaces grows even faster Capabilities of team members Click to see Figure 3-3 Click to see Figure 3-2
12
Systems Analysis and Design Fourth Edition Project Estimating Developing time and cost estimates Project size and scope IT resources Prior experience Constraints
13
Systems Analysis and Design Fourth Edition Project Scheduling The project manager must know The duration of each task The order in which the tasks will be performed The start and end times for each activity Who will be assigned to each task Assignments should not overload or under-utilize team members A level workload is desirable
14
Systems Analysis and Design Fourth Edition Scheduling Tools A project manager can use several graphical planning tools Gantt charts PERT/CPM charts
15
Systems Analysis and Design Fourth Edition Scheduling Tools Gantt charts A Gantt chart is a horizontal bar chart that illustrates a schedule Time is shown on the horizontal axis and activities are arranged vertically The position of a bar shows the start and end of a task, and the length of the bar shows the task’s duration Click to see Figure 3-5
16
Systems Analysis and Design Fourth Edition Scheduling Tools Gantt charts Tasks can be combined into activity groups to simplify the chart Various methods exist for tracking progress Shade the completed portion of a bar Use a triangle or arrowhead as an indicator Use a second bar to show the completed work Click to see Figure 3-6
17
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM The Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) were developed separately but now are referred to as PERT/CPM A PERT/CPM chart displays a project as a network diagram, with activities shown as vectors, and events represented by nodes
18
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM The vectors representing tasks connect the nodes, which indicate milestones The activity’s estimated duration is shown below the vector Click to see Figure 3-7b Click to see Figure 3-7a
19
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM The vectors representing tasks connect the nodes, which indicate milestones The activity’s estimated duration is shown below the vector Tasks that must be completed in a specific sequence are called dependent, or serial, tasks Click to see Figure 3-8
20
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM The vectors representing tasks connect the nodes, which indicate milestones The activity’s estimated duration is shown below the vector Tasks that must be completed in a specific sequence are called dependent, or serial, tasks Dummy activities can be used to show task dependencies Click to see Figure 3-9
21
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM A project can be represented with a Gantt chart and a PERT/CPM chart Significant differences exist between the two methods, and each method has strengths and weaknesses Click to see Figure 3-10
22
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Activity duration A weighted formula can be used to estimate activity duration The formula calculates a weighted result based on three separate estimates (optimistic (O), pessimistic (P), and most likely (M))
23
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Earliest completion times The earliest completion time for an activity is called the ECT The ECT is the minimum amount of time needed to complete all the activities that precede the event Click to see Figure 3-10
24
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Earliest completion times Working from left to right on the chart, the ECT is calculated by taking the ECT of the preceding event and adding the duration of the immediately preceding task If the event has more than one preceding task, use the largest ECT of the preceding tasks, including any dummy tasks The ECT is shown as a number in the upper- right section of the event node symbol
25
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Latest completion times The latest completion time for an activity is called the LCT The LCT is the latest time at which the event can occur without delaying the overall project
26
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Latest completion times To determine an LCT, you reverse the procedure for an ECT Work from right to left, and subtract the LCT of the following task If the event has more than one following task, use the smallest LCT of the following tasks, including any dummy tasks The LCT is shown as a number in the lower- right section of the event node symbol
27
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Latest completion times The slack time for an event is the amount of time by which an event can be late without delaying the project The slack time is the difference between the LCT and the ECT, if any
28
Systems Analysis and Design Fourth Edition Scheduling Tools PERT/CPM Critical path A critical path is a series of events and activities with no slack time At least one complete path will exist where every node has equal ECTs and LCTs If any task on the critical path is delayed beyond its LCT, the entire project falls behind by that amount of time Project managers focus on the critical path in order to keep the project on track
29
Systems Analysis and Design Fourth Edition Project Monitoring, Controlling, and Reporting Project monitoring and control Project managers Set standards Ensure that they are followed Keep track of the progress of team members Compare actual progress to the plan Verify the completion of project milestones
30
Systems Analysis and Design Fourth Edition Project Monitoring, Controlling, and Reporting Project scheduling Spend adequate time planning up front Anticipate problems, identify potential solutions, and select best way to solve problem
31
Systems Analysis and Design Fourth Edition Project Reporting The project manager must Collect the information Verify the information Organize the information Evaluate the information Prepare a summary Submit a report to management
32
Systems Analysis and Design Fourth Edition Project Reporting Project status meetings Project managers schedule regular status meetings with the systems development team Share information Update the group Identify problems or delays Explain new techniques Offer comments to team members Conduct brainstorming sessions
33
Systems Analysis and Design Fourth Edition Project Reporting Project status reports A project manager must report regularly to a supervisor, upper managers, and users When to inform others of potential problems Too soon, and the manager might lose credibility by reporting on minor problems Too late, and there might not be time for a solution to a serious problem Best course of action is somewhere between the two extremes
34
Systems Analysis and Design Fourth Edition Project Management Software A software package, such as Microsoft Project, offers many features PERT/CPM and Gantt charts Resource scheduling Project calendars Cost tracking and cost-benefit analysis Printed reports and screen displays Computer-generated screens show activities as nodes, with vectors connecting the tasks and indicating task dependencies Click to see Figure 3-12
35
Systems Analysis and Design Fourth Edition Software Change Control Software change control is the process of managing and controlling changes requested after the system requirements document has been approved Changes are inevitable A typical control procedure has four steps 1. Complete a change request form 2. Take initial action on the request 3. Analyze the impact of the requested change 4. Determine the disposition of the requested change Click to see Figure 3-13
36
Systems Analysis and Design Fourth Edition Keys to Project Success Successful systems must satisfy business requirements, meet users’ needs, stay within budget, and be completed on time The essential objective is to provide a solution to a business problem
37
Systems Analysis and Design Fourth Edition Keys to Project Success Some reasons for failure Unclear requirements, targets, or scope Shortcuts or sloppy work Poor design choices Insufficient testing or test procedures Lack of software change control Changes in culture, funding, or objectives Unrealistic cost estimates Poor monitoring and control of progress Inadequate reaction to early signs of problems Failure to recognize activity dependencies Personality conflicts and employee turnover
38
Systems Analysis and Design Fourth Edition Keys to Project Success When the project manager recognizes a problem, what options are available? Trim the project requirements Add to the project resources Delay the project deadline Improve the quality of project management Whatever the reason, the project manager must try to get the project back under control and keep it under control
39
End Tookit Part 3