Presentation is loading. Please wait.

Presentation is loading. Please wait.

NCHRP 8-60 Risk Analysis Tools and Management Practices to Control Transportation Project Costs Keith R. Molenaar, PhD Stuart D. Anderson, PhD, PE Transportation.

Similar presentations


Presentation on theme: "NCHRP 8-60 Risk Analysis Tools and Management Practices to Control Transportation Project Costs Keith R. Molenaar, PhD Stuart D. Anderson, PhD, PE Transportation."— Presentation transcript:

1 NCHRP 8-60 Risk Analysis Tools and Management Practices to Control Transportation Project Costs Keith R. Molenaar, PhD Stuart D. Anderson, PhD, PE Transportation Estimators Association Annual Conference Saratoga Springs, New York October 4, 2008

2 NCHRP 8-60 Research Team

3 Agenda Objective Motivation Process Methods and Tools Implementation Conclusions

4 Research Objective To develop a comprehensive guidebook on risk-related analysis tools and management practices for estimating and controlling transportation project costs

5 Background Risk Strategy Identify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed.

6

7

8 Cost Estimate at Any Phase Total Project Estimate = Base + Contingency Risk-related analysis tools and management practices

9 Basic Framework Assess/ Analyze Allocate Monitor and Control Identify Mitigate and Plan Risk Management Process Scalable for Project Complexity Adaptable to Project Development Phases

10 Risk Definitions and Tools Risk Identification Risk Assessment and Analysis Risk Mitigation and Planning Risk Communication

11 In a Nutshell: Risk Identification Identification, categorization and documentation of comprehensive, non- overlapping set of: –“ risks ” (potential problems) –“ opportunities ” (potential improvements) Events that might occur, which could change project cost or schedule

12 Risk Identification - Tools Brainstorming Scenario planning Expert interviews Delphi methods Influence or risk diagramming Risk checklists Red flag lists

13 Risk Identification - Checklists DOE ACEC/AGC Caltrans WSDOT

14 In a Nutshell: Risk Assessment and Analysis Process of adequately describing, assessing and analyzing the risks –Risk frequency –Risk severity Results in a set of ranked risks or quantified risks for inclusion in risk register

15 Qualitative Assessment Tools –Probability-Impact Matrices Quantitative Assessment Tools –Expected Value Methods –Three-Point Estimate Methods –First Order Second Moment Methods –Monte Carlo Simulation Methods Risk Assessment and Analysis - Tools

16 Probability-Impact Matrices

17 Three Point Estimate Tools The average cost of the item is (o+4m+p)/6

18 Monte Carlo Simulation Models cost schedule Activity A Activity C Activity B Start End

19 4.4 4.64.85.05.25.45.6 1234567891011121314151617181920212223242526272829303132333435363738394041424344454647484950 Iteration 80% of the values are equal or less than 5.2 Monte Carlo Simulation Models

20 Risk Analysis Process Risk Assessment to Identify Contingency Most Likely Estimate Contingency

21 Ranking of Risks

22 In a Nutshell: Risk Mitigation and Planning Risk Mitigation and Planning Assigning responsibility/ownership for risks Developing plans to address risks Risk Management Process

23 Risk Mitigation and Planning - Tools Red Flag Lists Risk Registers Risk Management Plans Risk Information Systems

24 Risk Registers

25

26 Risk Communication Tools

27

28 Implementation A Complexity-Based Solution –Type I – Risk Identification and Contingency Percentage –Type II – Qualitative Risk Analysis and Identified Contingency Items –Type III – Quantitative Risk Analysis and Contingency Management

29 Estimate Contingency Actions to Perform Type II Risk Analysis 1.Red Flag Items or Rank risks (PxI matrix) 2.Choose % contingency from allowable range Maryland Sliding-Scale Contingency 0-25%Final Design 25-35%Programming and Preliminary Design 35-40%Planning Contingency Project Phase

30 Type I - Example Ohio DOT Design Completion Contingency Guidelines for Cost Estimating of Major Projects

31 Estimate Contingency Actions to Perform Type II Risk Analysis 1. Rank risks (PxI matrix) 2. Estimate Expected Value for top 20% of risks 3. Choose % contingency from allowable range 4. Use additional contingency if warranted by the top risks

32 Estimate Contingency Actions to Perform Type III Risk Analysis 1. Rank risks (PxI matrix) 2. Develop a risk-based cost and schedule model 3. Choose appropriate contingency

33 Agenda  Objective  Motivation  Process  Methods and Tools  Implementation Conclusions

34 The simplest representations often work best While the analysis may be supported by a complex, rigorous, and probabilistically- sophisticated model, it is of little value if it is overly complicated in their representation http://www.fhwa.dot.gov/programadmin/contracts/cmetg.cfm

35 Conclusions Other Related Initiatives FHWA Expert Task Group –Guide to Risk Assessment and Allocation –“Train-the-Trainer” Workshops NHI Course on Risk Management NCHRP SHRPII R-09 Guide for the Process of Managing Risk on Rapid Renewal Projects

36 Question, Answers and Discussion! Thank You!

37 Study Help Examine Sliding Scale Contingency Use Delphi Technique Capture expert opinion Series of questions using an Excel Spreadsheet Assess contingency ranges for different project complexities and stages in project development Requesting your help!


Download ppt "NCHRP 8-60 Risk Analysis Tools and Management Practices to Control Transportation Project Costs Keith R. Molenaar, PhD Stuart D. Anderson, PhD, PE Transportation."

Similar presentations


Ads by Google