Download presentation
Published byRalf McCormick Modified over 9 years ago
1
The SKB Spent Fuel Disposal Project – License Application
Olle Olsson ©SKB
2
Nuclear Sweden 10 (12) operating reactor units at 3 sites
~45 % electricity 12,000 tonnes of spent fuel SFR; Final Repository for Short- lived Radioactive Waste Clab; Central Interim Storage Facility for Spent Nuclear Fuel ©SKB
3
Authorities and legislation
The Government Swedish Radiation Safety Authority The Swedish National Council for Nuclear Waste Municipality Environment Court The Planning and Building Act The Swedish Environment Code The Nuclear Activities Act The Financing Act The Radiation Protection Act ©SKB
4
Funding of nuclear waste management in Sweden
Owners Financing SEK per kWh of nuclear electricity Approx 43 billion SEK in 2010 Responsibility of the reactor owners Reviewed by SSM ©SKB
5
40 years of development Encapsulation plant and deep repository Detailed characterization, repository construction 2011 Application to build a repository Site investigations 2006 Application to build an encapsulation plant 2000 Feasibility studies Canister Laboratory Äspö Hard Rock Laboratory 1993 Methodology development SFR in operation Clab in operation The government approves KBS-3 for the start-up of new reactors The Nuclear Fuel Safety (KBS) Project starts 1984 m/s Sigyn in operation 1976 ©SKB
6
The Swedish system Healthcare, industry and research
Final repository for short-lived radioactive waste Final repository for spent nuclear fuel High-level waste Low and intermediate-level waste Nuclear power plant Central interim storage facility for spent nuclear fuel and encapsulation facility ©SKB
7
License application submitted March 2011 for
Backfill Spent Fuel Repository at Forsmark Rock Buffer Canister Typområden 1977–1985 Översiktsstudier 1990-tal Förstudier 1993–2002 Encapsulation plant in Oskarshamn ©SKB
8
SKB is applying To continue interim storage of spent nuclear fuel and reactor core components. The amount of spent nuclear fuel may reach a maximum of 8000 metric tons (calculated as uranium). To construct and operate a facility (Clink) to store spent nuclear fuel and core components and for encapsulation of spent nuclear fuel. Capacity of approximately 200 canisters per year. To construct and operate a facility for final disposal of spent nuclear fuel and nuclear waste (construction material in the fuel assemblies) Final disposal of the spent fuel that is currently stored in Clab and future fuel that will arise from operating the ten reactors that currently have a permit to operate Final disposal according to the KBS-3 method with vertical placement of the canisters (KBS-3V) Water operations that are needed to build and operate the facilities Storage for rock aggregate ©SKB
9
The legal framework Two laws The Environmental Code
The Nuclear Activities Act Two nuclear facilities at two different sites Two different Environmental courts Submitted to the court in Stockholm Evaluation of if the proposed facilities and activities meet the stated aims and are in accordance with legal requirements ©SKB
10
Strategic crossroads A single coherent Environmental Code application for the entire final repository system that is processed at a single environmental court The applications, 'top documentation', will offer a comprehensive − and not merely well-informed − intelligible description and overview of the operations being applied for and comprehensive argumentation for satisfying the requirements A common EIA for the entire final repository system for all three applications The safety reports will also be included in the Environmental Code application to the Environmental Court Particularly central issues justify detailed background documentation and separate appendices for Choice of method Site selection ©SKB
11
The Nuclear Fuel Project and other work within SKB
Research Technology development Site investigations and modelling Facility project planning Final repository Encapsulation facility Environmental Impact Assessments Dialogue and consultation Safety analysis Application documentation ©SKB
12
Stakeholder involvement Going from protests to dialogue
©SKB
13
Siting studies 1977-2009 ”Geology and society”
3 4 Östhammar 5 6 7 8 Oskarshamn Possible feasible bedrock Study areas 1977–1985 Regional studies 1990s Feasibility studies 1993–2002 Site investigations 2002–2009 ©SKB
14
3rd of June 2009 - SKB selects Forsmark for the repository for spent nuclear fuel
Photo composition of a repository for spent nuclear fuel at Forsmark Main reason for selection of Forsmark: Considerably better conditions for long term safety of a repository ©SKB
15
SKB has selected the KBS-3 method
Primary safety function: Complete containment Secondary safety function: Retardation ©SKB
16
KBS-3-method development and verification SKB full-scale laboratories
Äspö Hard Rock Laboratory, in operation since 1996 Canister Laboratory, in operation since 1998 Bentonite Laboratory, in operation since 2007 ©SKB
17
Purposes of the SR-Site project
Role of SR-Site report in licence application: To demonstrate that a KBS-3 repository at the Forsmark site is safe in the long term. The main purposes of the SR-Site project were To assess the safety, as defined in applicable Swedish regulations, of the proposed KBS-3 repository at Forsmark; To provide feedback to design development, to SKB’s R&D programme, to detailed site investigations and to future safety assessment projects. ©SKB
18
General development of the reference evolution
Initial “transient” caused by excavation of host rock and construction and presence of repository. Transients can be anything from years to thousands of years Long-term evolution characterised by changes induced by the changing external conditions. ©SKB
19
General outcome of the analysis of the reference evolution
The outcome of the analysis of the reference evolution implies that The vast majority of the 6,000 deposition positions will experience favorable mechanical, hydrogeological and chemical conditions throughout the one million year assessment period. As a consequence, the vast majority of the 6,000 canisters are expected to maintain their containment capacity throughout the assessment period However, canister failures cannot be entirely ruled out due to Enhanced corrosion in deposition positions where advective conditions prevail after buffer loss due to erosion Earthquake induced secondary shear movements in fractures intersecting deposition holes Both are low probability phenomena ©SKB
20
Risk curves for the two contributing scenarios
Central conclusion A KBS-3 repository that fulfils long-term safety requirements can be built at the Forsmark site The calculated risk for a final repository at Forsmark is below the regulatory risk criterion with a margin, even in a million year time perspective. ©SKB
21
Confidence in the conclusions in SR-Site
The reliance of the KBS-3 repository on a stable and favourable geological environment at repository depth - mechanical stability, low groundwater flow rates and favourable groundwater composition, and the use of sufficiently durable materials (copper and bentonite clay) for the engineered barriers The understanding of the phenomena that affect long-term safety, resulting in a mature knowledge base The understanding of the characteristics of the site through several years of surface-based investigations of the conditions at depth The detailed specifications of the engineered parts of the repository and the demonstration of how components fulfilling the specifications are produced in a quality assured manner ©SKB
22
Licensing 2011-2015 (?) Five ”yes” are needed
The municipality of Oskarshamn The Government The municipality of Östhammar The Environmental Court The Swedish Radiation Safety Authority Scientific community, environmentalists and other opinion formers ©SKB
23
From License application to deposition of canisters
Government approval Permit Construction Permit Test operation Permit Operation ~15 years Application A-PSAR PSAR SAR 1 SAR 2 ©SKB
24
The Nuclear Fuel programme
Licensing process Start construction Start operation Safety Report PSAR SAR Technology development Industrialized design Production system Quality control system Construction projects Spent fuel repository Encapsulation plant 2 y after construction initiation 4 years … 6 years… ©SKB
25
Challenges To manage the licensing process
To move from RD&D to industrialization To further strengthen the scientific basis for the safety case To keep and develop the public confidence ©SKB 25
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.