The PPSO SIG Spring 2006 Conference…
2
Agenda 9:45 - 10:30Registration 10:30 - 11:15“How to Identify Benefits” – John Zachar 11:15 - 11:35Coffee / networking 11:35 - 12:45“Changing Project Management Processes to Include Benefits Realisation” – David Marsh 12:45 - 14:00Lunch / networking 14:00 - 14:45“Extending Progress Reporting to Include Benefits” – David Marsh 14:45 - 15:00Tea / networking 15:00 - 15:45“Embedding changes” – Terri Kinton 16:00Close
3
BENEFITS CENTRED PROJECT MANAGEMENT David Marsh MMP
4
AIM To provide you with some ideas for introducing Benefits Centred Project Management into your organisation
5
OBJECTIVES To explain what is Benefits Centred Project Management and why you need it To explain the techniques To hear what Effect a Benefits Centred Project Management approach had
6
Why Do We Need Benefits Centred Project Management The need for real success Need to include the management of the benefits in the project A business benefit driven approach to delivering the project The holistic approach Effective/efficient use of scarce resources (M’s)
7
Benefits From Benefits Centred Project Management Defined bridge between the project and the benefits Improved : Project structure Project governance Realism Understanding Chance of success Reduced risk of adverse impact on business Senior management focus
8
What is Benefits Centred Project Management The efficient management of the execution of a project/ work packages within a controlled environment to: achieve the required benefits for the operation of the business. achieve a set of defined business outcomes. co-ordinate the planning, monitoring and control of the project/work packages with benefit efficiency as the key.
9
Differences in Benefits Centred Project Management Revised contents of the Project Control Documents Revised Project Management organisation structure New planning techniques
10
Revised Contents of the Project Control Documents The use of a wider (benefits centred) definition (Blueprint) of what the project is to deliver. Re-structured User Requirements – lateral and vertical MOSCO.
11
Re-Structured User Requirements Subdivide the requirements – Laterally What functions must, should and could you have. Subdivide the requirements – Vertically What performance/capacity/look and feel in each of these groups of functions must, should and could you have
12
Blueprint Operational Vision What the organisation or function will be like once we have completed the Project Business Vision The business benefits or changes (Quantitative or Qualitative - to be obtained) Change Vision The attitude and or culture changes needed
13
Revised Project Management Organisation Structure Who in your existing organisation structure is responsible for: Agreeing that the planned benefits are realistic Ensuring that the project will deliver the benefits Ensuring the project is structured to deliver the benefits Responsible for delivering the benefits Is the the Senior User the right person?
14
Project Board Project Support Office Organisation Structure Board Of Directors Project Assurance NEW ROLE Benefits Realisation Manager and Team Project Manager Sponsoring Group
15
Role of Project Board Ultimate responsibility - stewardship/keeper of the Vision Establish the project Responsible for resources and funding Manage the interfaces with other projects etc Ensure project links to strategy and evolving business needs Ensure efficient organisation of the staff Commissioning reviews Control of project implementation
16
Role of Benefits Realisation Manager Establishing how the benefits will be delivered Leading Prioritisation and Change Control Responsible for planning the delivery of the benefits Preparing business areas for transition Leading benefits realisation activities Optimising the release of deliverables for the business Ensure the Project Boards requirements are met Working with Project Manager to ensure Work Packages will enable project to deliver Reviewing potential new requirements for inclusion in the project
17
PREPARING THE PROJECT PLAN
18
The Project Planning Process (1) Graph Required Benefits Profile Identify potential new and existing work packages Prepare /obtain estimates - duration, resource requirement, costs & benefits Prepare Work Package-Project Contribution Matrix
19
Prepare Project Plan - match Required Benefits Profile Identify & confirm dependencies and ’Handshakes' Identify & agree Project Milestones Identify & agree Project review points Update risk analysis, Benefits Management Plan Prepare Quality and Configuration Management Plan The Project Planning Process (2)
21
The Work Package-Project Contribution Matrix All Work Packages to be included Contribution can be measured in terms of : Benefits obtained (outputs and outcomes) Earned Value Analysis Must, should, or could etc.. Weighting and ranking tables Difficulty and/or risk etc.
22
Work Package -Project Contribution Matrix Work Package %age Contribution Benefit (and Value) 1 2 3 4 5 6
25
Defining Project Milestones Milestones important to the project: Obtaining benefits Commitments for expenditure or resources Strategic decision points outside the project Asset transformation points