Download presentation
Presentation is loading. Please wait.
Published byMadeleine Kelley Modified over 9 years ago
1
Schematic Design of an Accelerated Bridge Construction Project Michael P. Culmo, P.E. Vice President of Transportation and Structures CME Associates, Inc., East Hartford, CT
2
Reference Manual Use the Connections Details Manual –Type study concept –Select details from various states
3
Case Scenario 4 lane bridge over an expressway Existing bridge has deteriorated beyond repair Heavy traffic on both roadways There is a short but undesirable detour
4
Public Involvement Public hearing heldPublic hearing held Businesses do not want a long construction process with stage constructionBusinesses do not want a long construction process with stage construction Businesses are not keen about a detourBusinesses are not keen about a detour They will accept a short term closure with the detourThey will accept a short term closure with the detour –As opposed to a long term staged project
5
Design Approach Options Build a temporary bridge to speed up construction of the new bridge –$$$$ –Not that fast Use multi-stage construction –Very long construction –Will require long term lane closures Establish the detour and accelerate the bridge construction to less than 30 days
6
Existing Bridge
7
Deck Joints Low Clearance Existing bridge issues
8
Proposed Bridge Type After a formal type study, the owner opted with the following structure criteria –Use NEXT Beams to accelerate construction Design as simple span for Dead Load and continuous spans for Live Load –Increase clearance by raising approach grades (3’) –Use integral abutments (no deck joints) –Composite concrete deck –Membrane waterproofing and Bituminous wearing surface –Use Precast Rail System (Vermont/NH system)
9
Substructures Push abutments back to top of slopePush abutments back to top of slope –Minimize wingwall requirements –Use integral abutments with flying wings –Eliminate spray attack on abutments Place abutments in a different footprint than the existingPlace abutments in a different footprint than the existing –facilitates construction Use open frame pier bent on spread footingsUse open frame pier bent on spread footings
10
Proposed Bridge Move abutment away from roadway No Deck jointsIncrease vertical clearance
11
Bridge Section
12
Beam Design Preliminary Beam Sizing –Use PCI NEXT Beam Standards
13
Beam Design LLDF
14
Beam Design AASHTO LL Distribution Factor – Type K Moment Shear
15
Beam Design AASHTO LLDF Type H Moment Shear
16
Beam Design Structure TypeHK LLDF Moment 0.960.752 LLDF Shear 1.170.938
17
How to select details FHWA manual “Connection details for prefabricated bridge elements and systems” 1.Review Chapter 1 Investigate connection types, materials, tolerances 2. Search applicable sections of other chapters for details
18
Section 1.4 Typical Connection Types After reviewing chapter 1, the owner chose the following connection types –Grouted reinforcing splice couplers Quick, proven system Can develop full bar strength Simplifies the design process (similar to CIP) –Grouted Voids Easy for simple connections –Concrete Closure pours between precast elements Use for a limited number of connections (slower)
19
Grouted Reinforcing Splice Connectors Emulates a reinforcing steel lap splice Multiple companies – non-proprietary Used in precast parking garages and stadiums and bridges
20
Grouted Reinforcing Splice Connectors Emulates a reinforcing steel lap splice Multiple companies – non- proprietary Used in precast parking garages and stadiums and bridges Time Lapse Video on Youtube TM –Search “Georgia Pier Construction” Installation Video on Youtube TM Search “Georgia Pier Construction” Installation video
21
Footing to Sub-grade Connection
22
Footing Details
23
Footing to Column Connection
25
Column to Cap Connection
27
Completed Pier Footing to subgrade connection Column to footing connection Column to cap connection
28
Abutment Details Integral Abutment to precast piles –Section 3.2.3.1 Precast Integral Abutment to Piles Detail developed by Maine DOT –Used on three different bridges
29
Abutment to Pile Connection
31
Abutment To Wingwall Connection
33
Approach Slab Connection
34
Completed Abutment Pile to cap connection Approach slab connection Flying Wingwall connection Abutment cap connection
35
Deck Design with Next Beam Design as a conventional cast in place deck – Use max stem spacing for design (5.0 feet) – Design overhang from outside stem (2.53 feet)
36
Parapet Connection
38
Superstructure to Integral Abutment Connection Use a similar detail at the pier
39
Completed Bridge Precast Integral Abutment Composite Deck Membrane waterproofing with bit. Wearing surface Precast Pier Precast Parapet
40
Final Bridge
41
Estimated Construction Schedule
42
Costs Typical New Bridge (Cost=$200/sf) = $1,920,000 Premium for ABC (assume 20%) = $384,000 Temporary Bridge (Cost=$60/sf) = ($576,000) Net Savings = $192,000 Note: These prices will vary by region
43
Ways to reduce bid prices with ABC Standardization Programmatic (not one of a kind) Reduced project site costs (trailers, etc.) Reduced Maintenance of Traffic Costs Inflation Other Non- Bid Savings with ABC Fewer Police Details Reduced Resident Engineering time User Costs Plus: $$ Can be significant Minus: $$ Not in the budget Other Cost Savings
44
Quality Florida has had very good success with precast piers in very harsh environments Precast concrete beams require no maintenance Integral abutments eliminate deck joints
45
Old Adage By elimination of temporary bridges or costly stage construction schemes, you CAN have all three Rapid Construction High Quality Low Cost You can only have any two
46
Conclusions It is possible to build a complete bridge in 30 days (or less) The FHWA manual provides a starting point for a complete bridge prefabrication project You do not need to sacrifice quality to get rapid construction You can save money on an accelerated bridge project by: –Reducing construction time –Eliminate temporary bridges or staging
47
Questions culmo@cmeengineering.com
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.