Presentation is loading. Please wait.

Presentation is loading. Please wait.

Manufacturing Operations Scheduling

Similar presentations


Presentation on theme: "Manufacturing Operations Scheduling"— Presentation transcript:

1

2 Manufacturing Operations Scheduling
Chapter 16 Manufacturing Operations Scheduling B2 [ ] E [ P [---] D1 [ X ] C [- 3 4 5 6 7 8

3 Overview Scheduling Process-Focused Manufacturing
Scheduling Product-Focused Manufacturing Computerized Scheduling Systems Wrap-Up: What World-Class Companies Do

4 Scheduling Process-Focused Manufacturing

5 Process-Focused Manufacturing
Process-focused factories are often called job shops. A job shop’s work centers are organized around similar types of equipment or operations. Workers and machines are flexible and can be assigned to and reassigned to many different orders. Job shops are complex to schedule.

6 Scheduling and Shop-Floor Decisions
Master Production Schedule (MPS) Product Design and Process Plans Material Requirements Plan (MRP) Capacity Requirements Plan (CRP) Order- Processing or Routing Plans Planned Order Releases Report Work Center Loading and Overtime Plan Assignment of Orders to Work Centers Day-to-Day Scheduling and Shop-Floor Decisions

7 Pre-production Planning
Design the product in customer order Plan the operations the product must pass through this is the routing plan Work moves between operations on a move ticket

8 Common Shop Floor Control Activities
The production control department controls and monitors order progress through the shop. Assigns priority to orders Issues dispatching lists Tracks WIP and keeps systems updated Controls input-output between work centers Measures efficiency, utilization, and productivity of shop

9 Shop Floor Planning and Control
Input-Output Control Gantt Chart Finite and Infinite Loading Forward and Backward Scheduling

10 Input-Output Control Input-output control identifies problems such as insufficient or excessive capacity or any issues that prevents the order from being completed on time. Input-output control report compares planned and actual input, planned and actual output, and planned and actual WIP in each time period

11 Input-Output Control Report
Week: Planned input: labor-hrs Actual input: labor-hrs Cumulative deviation Planned output: labor-hrs Actual output: labor-hrs Cumulative deviation Planned ending WIP: l-h Actual ending WIP: l-h

12 Gantt Charts Gantt charts are useful tools to coordinate jobs through shop; graphical summary of job status and loading of operations

13 Gantt Charts Work Centers Mon. Tue. Wed. Thu. Fri. Sat. Machining
Fabrication Assembly Test E F G C D E F H C D E H C D Scheduled Progress Setup, Maint.

14 Assigning Jobs to Work Centers: How Many Jobs/Day/Work Center
Infinite loading Assigns jobs to work centers without regard to capacity Unless excessive capacity exists, long queues occur Finite loading Uses work center capacity to schedule orders Popular scheduling approach Integral part of CRP

15 Assigning Jobs to Work Centers: Which Job Gets Built First?
Forward scheduling Jobs are given earliest available time slot in operation excessive WIP usually results Backward scheduling Start with promise date and work backward through operations reviewing lead times to determine when a job has to pass through each operation Less WIP but must have accurate lead times

16 Order-Sequencing Problems
Sequencing Rules Criteria for Evaluating Sequencing Rules Comparison of Sequencing Rules Controlling Changeover Costs Minimizing Total Production Time

17 Order-Sequencing Problems
We want to determine the sequence in which we will process a group of waiting orders at a work center. Many different sequencing rules can be followed in setting the priorities among orders. There are numerous criteria for evaluating the effectiveness of the sequencing rules.

18 Order-Sequencing Rules
First-Come First-Served (FCFS) Next job to process is the one that arrived first among the waiting jobs Shortest Processing Time (SPT) Next job to process is the one with the shortest processing time among the waiting jobs Earliest Due Date (EDD) Next job to process is the one with the earliest due (promised finished) date among the waiting jobs

19 Order-Sequencing Rules
Least Slack (LS) Next job to process is the one with the least [time to due date minus total remaining processing time] among the waiting jobs Critical Ratio (CR) Next job to process is the one with the least [time to due date divided by total remaining processing time] among the waiting jobs Least Changeover Cost (LCC) Sequence the waiting jobs such that total machine changeover cost is minimized

20 Evaluating the Effectiveness of Sequencing Rules
Average flow time - average amount of time jobs spend in shop Average number of jobs in system - Average job lateness - average amount of time job’s completion date exceeds its promised delivery date Changeover cost - total cost of making machine changeovers for group of jobs

21 Experience Says: First-come-first-served
Performs poorly on most evaluation criteria Does give customers a sense of fair play Shortest processing time Performs well on most evaluation criteria But have to watch out for long-processing-time orders getting continuously pushed back Critical ratio Works well on average job lateness criterion May focus too much on jobs that cannot be completed on time, causing others to be late too.

22 Example: Sequencing Rules
Use the FCFS, SPT, and Critical Ratio rules to sequence the five jobs below. Evaluate the rules on the bases of average flow time, average number of jobs in the system, and average job lateness. Job Processing Time Time to Promised Completion A hours 10 hours B C D E

23 Example: Sequencing Rules
FCFS Rule A > B > C > D > E Processing Promised Flow Job Time Completion Time Lateness A B C D E

24 Example: Sequencing Rules
FCFS Rule Performance Average flow time: 141/5 = 28.2 hours Average number of jobs in the system: 141/49 = 2.88 jobs Average job lateness: 90/5 = 18.0 hours

25 Example: Sequencing Rules
SPT Rule A > E > C > B > D Processing Promised Flow Job Time Completion Time Lateness A B C D E

26 Example: Sequencing Rules
SPT Rule Performance Average flow time: 127/5 = 25.4 hours Average number of jobs in the system: 127/49 = 2.59 jobs Average job lateness: 76/5 = 15.2 hours

27 Example: Sequencing Rules
Critical Ratio Rule E > C > D > B > A Processing Promised Flow Job Time Completion Time Lateness E (.875) C (.889) D (1.00) B (1.33) A (1.67)

28 Example: Sequencing Rules
Critical Ratio Rule Performance Average flow time: 148/5 = 29.6 hours Average number of jobs in the system: 148/49 = 3.02 jobs Average job lateness: 93/5 = 18.6 hours

29 Example: Sequencing Rules
Comparison of Rule Performance Average Average Average Flow Number of Jobs Job Rule Time in System Lateness FCFS SPT CR SPT rule was superior for all 3 performance criteria.

30 Controlling Changeover Costs
Changeover costs - costs of changing a processing step in a production system over from one job to another Changing machine settings Getting job instructions Changing material Changing tools Usually, jobs should be processed in a sequence that minimizes changeover costs

31 Controlling Changeover Costs
Job Sequencing Heuristic First, select the lowest changeover cost among all changeovers (this establishes the first two jobs in the sequence) The next job to be selected will have the lowest changeover cost among the remaining jobs that follow the previously selected job

32 Example: Minimizing Changeover Costs
Hardtimes Heat Treating Service has 5 jobs waiting to be processed at work center #11. The job-to-job changeover costs are listed below. What should the job sequence be? Jobs That Precede A B C D E A B C D E Jobs That Follow

33 Example: Minimizing Changeover Costs
Develop a job sequence: A follows D ($50 is the least c.o. cost) C follows A ($92 is the least following c.o. cost) B follows C ($69 is the least following c.o. cost) E follows B (E is the only remaining job) Job sequence is D – A – C – B – E Total changeover cost = $ = $286

34 Minimizing Total Production Time
Sequencing n Jobs through Two Work Centers When several jobs must be sequenced through two work centers, we may want to select a sequence that must hold for both work centers Johnson’s rule can be used to find the sequence that minimizes the total production time through both work centers

35 Johnson’s Rule 1. Select the shortest processing time in either work center 2. If the shortest time is at the first work center, put the job in the first unassigned slot in the schedule. If the shortest time is at the second work center, put the job in the last unassigned slot in the schedule. 3. Eliminate the job assigned in step 2. 4. Repeat steps 1-3, filling the schedule from the front and back, until all jobs have been assigned a slot.

36 Example: Minimizing Total Production Time
It is early Saturday morning and The Finest Detail has five automobiles waiting for detailing service. Each vehicle goes through a thorough exterior wash/wax process and then an interior vacuum/shampoo/polish process. The entire detailing crew must stay until the last vehicle is completed. If the five vehicles are sequenced so that the total processing time is minimized, when can the crew go home. They will start the first vehicle at 7:30 a.m. Time estimates are shown on the next slide.

37 Example: Minimizing Total Production Time
Exterior Interior Job Time (hrs.) Time (hrs.) Cadillac Bentley Lexus Porsche Infiniti

38 Example: Minimizing Total Production Time
Johnson’s Rule Least Work Schedule Time Job Center Slot Infiniti Interior 5th 1.6 Porsche Interior 4th 1.9 Lexus Exterior 1st 2.0 Cadillac Exterior 2nd 2.1 Bentley Exterior 3rd

39 Example: Minimizing Total Production Time
Exterior Interior L C B P I Idle Idle L C B P I It will take from 7:30 a.m. until 7:30 p.m. (not allowing for breaks) to complete the five vehicles.

40 Scheduling Product-Focused Manufacturing

41 Product-Focused Scheduling
Two general types of product-focused production: Batch - large batches of several standardized products produced Continuous - few products produced continuously.... minimal changeovers

42 Scheduling Decisions If products are produced in batches on the same production lines: How large should production lot size be for each product? When should machine changeovers be scheduled? If products are produced to a delivery schedule: At any point in time, how many products should have passed each operation if time deliveries are to be on schedule?

43 Batch Scheduling EOQ for Production Lot Size
How many units of a single product should be included in each production lot to minimize annual inventory carrying cost and annual machine changeover cost?

44 Example: EOQ for Production Lots
CPC, Inc. produces four standard electronic assemblies on a produce-to-stock basis. The annual demand, setup cost, carrying cost, demand rate, and production rate for each assembly are shown on the next slide. a) What is the economic production lot size for each assembly? b) What percentage of the production lot of power units is being used during its production run? c) For the power unit, how much time will pass between production setups?

45 Example: EOQ for Production Lots
Annual Setup Carry Demand Prod. Demand Cost Cost Rate Rate Power Unit 5,000 $1,200 $ Converter 10, Equalizer 12, , Transformer 6,

46 Example: EOQ for Production Lots
Economic Production Lot Sizes

47 Example: EOQ for Production Lots
% of Power Units Used During Production d/p = 20/200 = or 10% Time Between Setups for Power Units EOQ/d = 1,490.7/20 = days

48 Batch Scheduling Limitations of EOQ Production Lot Size
Uses annual “ballpark” estimates of demand and production rates, not the most current estimates Not a comprehensive scheduling technique – only considers a single product at a time Multiple products usually share the same scarce production capacity

49 Batch Scheduling Run-Out Method
Attempts to use the total production capacity available to produce just enough of each product so that if all production stops, inventory of each product runs out at the same time

50 Example: Run-Out Method
QuadCycle, Inc. assembles, in batches, four bicycle models on the same assembly line. The production manager must develop an assembly schedule for March. There are 1,000 hours available per month for bicycle assembly work. Using the run-out method and the pertinent data shown on the next slide, develop an assembly schedule for March.

51 Example: Run-Out Method
Assembly March April Inventory Time Forec. Forec. On-Hand Required Demand Demand Bicycle (Units) (Hr/Unit) (Units) (Units) Razer Splicer Tracker ,500 1,500 HiLander

52 Example: Run-Out Method
Convert inventory and forecast into assembly hours Assemb. March March Invent. Time Forec. Invent. Forec. On-Hand Req’d. Dem. On-Hand Dem. Bicycle (Units) (Hr/Unit) (Units) (Hours) (Hours) Razer Splicer Tracker , HiLander Total 470 1,250 (1) (2) (3) (4) (5) (1) x (2) (2) x (4)

53 Example: Run-Out Method
Compute aggregate run-out time in months Aggregate Run-out Time = = [(Total Inventory On-Hand in Hours) + (Total Assembly Hours Available per Month) - (March’s Forecasted Demand in Hours)] / (April’s Forecasted Demand in Hours) = ( , ,250)/1,250 = months

54 Example: Run-Out Method
Develop March’s Production Schedule March’s March’s Desired Desired Assembly Ending End.Inv. Required Time Inventory & Forec. Production Allocated Bicycle (Units) (Units) (Units) (Hours) Razer Splicer 158 1, Tracker 264 1,764 1, HiLander 999.8 (6) (7) (8) (9) (3) x .176 (3) + (6) (7) - (1) (8) x (2)

55 Computerized Scheduling
Develops detailed schedules for each work center indicating starting and ending times Develops departmental schedules Generates modified schedules as orders move Many packages available.... select one most appropriate for your business

56 Wrap-Up: World-Class Practice
In process-focused factories: MRP II refined.... promises are met, shop loading is near optimal, costs are low, quality is high In product-focused factories: EOQ for standard parts containers, this sets S, lot sizes are lower, inventories slashed, customer service improved Scheduling is integral part of a computer information system

57 End of Chapter 16


Download ppt "Manufacturing Operations Scheduling"

Similar presentations


Ads by Google