Yaoundé, November 18 2014 Presented by: Mamata Teindrebeogo, Amadou Doudou Seck World Bank
2
Procurement Manuals Include steps for the 2 procurement DLIs Updated Procurement plan Procurement Risks and Mitigation Measures / Status of implementation / Any difficulties Procurement Schedule Procurement Challenges Support from AAU, NUC, Consultant / Any other need? How to improve support? 2
3
ACE Use their current institutional procurement procedures World Bank Procurement and Consultant Guidelines for AAU, NUC, a few ACES and Gambia No works for Component 2 All Procurement Manuals have been approved Pending Lomé University 3
4
DLI#4: Timely and Audited Procurement: ◦ DLR#4.1: Timely procurement audit ($50,000 disbursement per year); TOR and Selection of the Auditor: Start now Present the first report by the end of the first year ◦ DLR#4.2: Timely and Satisfactory Procurement Progress ($50,000 per year). 25% of all procurement contracted by year1 55% by year 2 100% by year 3 Verification of installation by year 4 4
5
Ask your questions– please! 5
6
Aiming for 70% of ACE allocation Has it been updated in line with the latest version of the Implementation plan? Identify your priority procurement packages Examples: technically complex (such as renovations, civil works, specialized laboratory equipment, etc.) Status of procurement plan implementation/ Any difficulties to conduct procurement activities? 6
7
Bank has carried out a procurement risk and capacity evaluation See PAD for details Mitigation measures often involve training and new staff What is your progress? Any difficulty? 7
8
Procurement takes time – please be aware Internal procedures are often time consuming Plan accordingly and not at last minute Need to monitor time line and take quick actions 8
9
Often issues with limited private sector capacity in terms of quality and quantity of bidders Do you have sufficient technical specialists to prepare specifications and TORs? Some training activities involve a procurement process – plan for this also 9
10
Technical Assistance (TA) with procurement manual? TA on standard bidding documents or requests for proposals (RFPs)? TA on procurement plan TA on procurement training? TA on technical specifications or TORs? TA technical assistance on other specific issues? 10
11
Thanks 11