Status Report, ENTM 02/11/2010 BEAM INTERCEPTING DEVICES FOR LINAC 4
2
Overview Beam stoppers for source/LEBT and for Linac4 transfer line Chopper line collimator Beam dumps for the movable bench (C. Maglioni) 50-100 MeV measurements bench dump Beam dumps for LBE/LBS lines and LBS slit Head, tail, H 0 /H - internal dumps for the PSB injection region (R. Chamizo) Linac4 main dump (R. Chamizo) 2 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20
3
3 LINAC 4 layout
4
Beam stoppers for source/LEBT 4 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 Beam dumps for the movable bench (C. Maglioni) Linac4 main dump (R. Chamizo) 50-100 MeV measurements bench dump Chopper line collimator
5
Beam stoppers for source/LEBT 5 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 LINAC4 Project Document No. L4-T-ES-0001 EDMS Document No. 1057463 Racetrack flanges are housing the beamstopper. Two flanges facing each other (180°) 3MeVL4-Nom Maximum H- Current40 mA80 mA Pulse Length150µs400µs Max Rep-Rate2Hz Beam Energy45 keV Beam parameters
6
Beam stoppers for source/LEBT Design finished Production started Ready by the end of the year One unit with Iris to produce a pencil beam 6 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20
7
Produced and installed 7 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 Chopper line collimator (3MeV)
8
Beam stopper for Linac4 transfer line Slit LBS Slits LBE Fast beam stopper Sieve (removed) Beam stopper 8 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20
9
Beam stopper for Linac4 transfer line Intension to reuse the existing stopper tank (layout dimensions and functionality) Simulations for the material to be done Cooling to be foreseen (additional piping) 9 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20
10
Beam dumps for LBE/LBS lines and LBS slit SPECIFICATIONS FOR BEAM DUMPS IN LINAC4 DUMP LINE, LBE AND LBS LINES F. Regis will work on that LBE dump LBS dump, feasibility study for integration done LBS slit Start with the 3-12 MeV slit design Go towards a stripping foil with a dedicated dump (below the spectro- meter magnet? Have a thick slit, absorb most, but less clean beam? 10 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 LINAC4 Project Document No. L4-B-ES-0001 v.1.0 EDMS Document No. 1056611 v.1.0
11
50-100 MeV measurements bench dump USER SPECIFICATIONS FOR LINAC4 COMMISSIONING DUMP AT 50 AND 100 MEV To be treated together with the main dump (160MeV) Two solutions: A “movable“ version for 50 and 100 MeV Use a stationary dump for 160 MeV 11 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 LINAC4 Project Document No. L4-T-EP-0004 v.0.2 EDMS Document No. 1094599 v.0.2
12
50-100 MeV measurements bench dump 12 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 50 MeV 100 MeV
13
Chopper collimator done Source stopper ready in January 2011 Dumps for the measurement bench April 2011 50/100 MeV dump – 160 MeV main dump for the end of 2012 LBE/LBS and slit from 2013 onwards TL beam stopper for 2014 Head and tail /H 0 /H - for 2014 13 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 Planning
14
EVM / Planning 14 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 wuv1.0Generated:28-oct-2010 13:48 cmdwuWU IDBaselineStatusDescriptionWBSHolders EMail Start DateFinish DateComments cmdPxx# Skill[Missing] Email or ProfileOrg Code [Recharging]DurationUnit (M.WK, %)Start DateFinish DateComments cmdde# WeightDeliverable descriptionActual QtyTotal QtyUnitStart DateFinish DateComments wu48032 Baseline 2PLTL StopperLINAC4 2.13oliver.aberle@cern.ch1-Nov-201031-Mar-2012new date MSP10Materials & machining5515135000CHF MIS.S20FSU support5515110000CHF MSP30Design office5515125000CHF de1026Materials and oders0100%1-Jun-201131-Jul-2011delayed de206Electric parts0100%1-Jun-201131-Jul-2011delayed de3013Machining0100%1-Aug-201130-Sep-2011delayed de400Parts manufactured0100%1-Aug-201130-Sep-2011delayed de450 Technical specification & validation01U1-Nov-201028-Feb-2011new date de500Beam stoppers assembled01U30-Sep-20111-Dec-2011delayed de600Stopper fully tested01U1-Dec-20111-Feb-2012delayed de7025Stopper execution drawings0100%1-Mar-201130-Jun-2011delayed de800dump installed01U1-Mar-201231-Mar-2012 wu48028 Baseline 2ACStopper Ion sourceLINAC4 2.13oliver.aberle@cern.ch1-Nov-200930-Jan-2011Date modified MSP10Materials & machining5515050000CHF MIS.S20FSU support5515020000CHF MSP30Design office5515025000CHF de1035Materials and oders60100%1-Nov-200930-Sep-2010modified de2014Electric parts40100%1-Nov-200929-Oct-2010modified de3021Machining25100%1-Nov-200930-Sep-2010production de400Parts manufactured25100%1-Nov-200930-Sep-2010production de4525Stopper execution drawings100 %30-Nov-200926-May-2010Design finished de500Beam stoppers assembled02U1-Feb-201011-Oct-2010Date modified de600Stopper fully tested02U31-Oct-201030-Nov-2010Date modified de700Stopper installed02U1-Dec-201030-Jan-2011Renaming wu48038 Baseline 2ACDump conceptual designLINAC4 2.13rocio.chamizo@cern.ch1-Apr-20091-Oct-2010 de101 Technical specification & validation0.61U1-Apr-20091-Oct-2010 Checking new operation scenarios wu48034 Baseline 2AC Ho/H-,head & tail dumps - conceptual designLINAC4 2.13rocio.chamizo@cern.ch1-Jan-20091-Oct-2010Studies on going de101Technical specification ready0.81U1-Jan-20091-Oct-2010
15
EVM / Planning 15 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 EVM to be created for: 3-12 MeV measurement bench LBE/LBS dumps and LBS slit And the 50/100 MeV dump
16
16 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 Reserve slides
17
17 O. Aberle, EN-STI, Linac4 Beam Coordination Committee - Meeting 20 Reserve