Download presentation
Presentation is loading. Please wait.
Published bySamson White Modified over 9 years ago
1
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012
2
o SPS consolidation overview o Transformers o Thyristor bridges o Electronics and CIS o Powering tests o Conclusions 2 Outlines
3
3 Consolidation overview Overview
4
SPS Dipole Circuit Power system ratings: 25 kV/6kA/150 MW 12 converters connected in series 2 active spares. 4 Overview Spares
5
2 converters 1 active spare 5 Overview SPS Quadrupole Circuit Power system ratings: 4.8 kV/2.2 kA/ 10.6 MW 2 converters + 1 active spare
6
6 History of SPS powering 1975: SPS Main Power System was put into service, 1981: Transformer upgrade for collider mode (voltage increase), 1993: Change of the regulation control electronics 1998: Replacement of the command and interlocking system (CIS) 1998-2000: Filter capacitors replacement (PCB elimination), 2002: New Earth Protection and Discharge System (Crowbar), The consolidation program shall continue to maintain the excellent availability of the machine Overview
7
SPS powering consolidation: A large project! 7 Overview 18kV cables Qty 20 km LS1 EN/EL Transformers Qty = 68 LS1 TE/EPC Thyristors Qty = 68 LS1 TE/EPC Electronics and CIS LS1-2 TE/EPC
8
8 Overview Strategy: For the case of major problem, we shall be able to return to the previous situation. Transformers: Full compatibility between old and new transformers (dimensions of the pits and power connections), Thyristor bridges: Full compatibility between old and new thyristor bridges (no modification of existing converter racks), 18 kV cables: Keep the ability to reconnect the old cables. Feasibility study underway (EN/EL).
9
9 Transformers For SMD and SMQ Transformers
10
10 Oil Transformers … reasons to change Ageing (≈30 years of operation): High maintenance costs and urgent need of consolidation: o Corrosion, o Oil leakages. PCB traces Oil treatment in 2008-2009 to conform to French/Swiss regulation, However, traces of PCB remain (within the legal limit <50ppm), The oil transformers will be replaced by cast-resin transformers during LS1: 60 transformers in 30 enclosures (6 MCHF). Transformers
11
11 Transformers Existing oil transformers
12
12 Transformers… Transformers 4 pre-series transformers already in operation in 2011, 4 additional transformers installed for the operation in 2012,
13
Transformers 13 Preparations in 2012… The SAX area will be required for the storage of the new cast-resin transformers in 2012-2013, The old oil transformers need to be stored on platform with oil retention (b.951) until 2016. Clear out of all equipment is required Presently, the SAX area is managed by GS. We would like to take the responsibility for this area as it was designed to store oil transformers.
14
Transformers 14 Preparations in 2012… Access road around BA2 to be rebuild (budget 55 kCHF covered by GS),
15
Transformers 15 Installation in 2013… Installation of 60 transformers by TE-EPC (January - December 2013), The installation per converter (4 transformers) takes 10 days, The pre-tests without power take 4 days, The support of the following groups is required: EN/HE for transport and crane, EN/EL for the control cabling and earthing system, Planning proposal The coordination and the planning of all co-activities is required with the support of the SPS coordination team. BA1January 2013 BA2February – March BA3April – May BA4June BA5September BA6October
16
16 Thyristor bridges For SMD and SMQ Thyristors
17
17 Thyristors … reasons to change Expected lifetime of all components is reached: Increasing problems with reliability of operation (water leaks, issues with electrical contacts, thyristor firing circuits etc…) The old bridges will be replaced during LS1: 68 thyristor bridges in 17 power converters (1 MCHF). Thyristors
18
18 Thyristors Thyristors: existing water-cooled power bridges
19
19 Thyristors… Thyristors Integration into the existing racks
20
20 Thyristors… Thyristors Two parallel bridges Replaced by one single bridge
21
Thyristors 21 Preparations in 2012… Delivery of prototypes (Dipoles & Quadrupoles) in July 2012, Mechanical validation in a spare converter (outside SPS), Installation of 2 thyristor bridges in BA2 spare converter in September for validation with the SPS, Operation with this spare converter until end of 2012, Delivery of all bridges in 2013.
22
Thyristors 22 Installation in 2013… Installation of 68 bridges by TE-EPC from January to December 2013, The installation per power converter takes 6 days, The pre-tests without power take 2 days, No co-activities with other groups Planning proposal BA1January 2013 BA2February – March BA3April – May BA4June BA5September BA6October
23
23 Electronics and CIS
24
24 Electronics… reasons to change Increasing problems with reliability of operation (connectors, contacts, etc…), Modern diagnostics tools are needed to optimize performances and post mortem analysis, The consolidation of Electronics is a long term project and will be completed in LS2. Electronics
25
25 Electronics… Electronics Electronics designed by S. Van Der Meer
26
26 Electronics Analogue Voltage Regulation Analogue Voltage Regulation Power part Power part Analogue Current Regulation Analogue Current Regulation Function Generation Function Generation DAC MUGEF in 2012 I ref V ref I meas V meas Analogue Voltage Regulation Analogue Voltage Regulation Power part Power part Analogue Current Regulation Analogue Current Regulation Func. Gen. Func. Gen. DAC MUGEF after LS1 I ref V ref I meas V meas ADC Digital Current Regulation Digital Current Regulation Analogue regulation can be reactivated in minutes First step: integration of Current Regulation in the Mugef in LS1.
27
27 The new MUGEF software will provide many benefits including post- mortem logging, asynchronous starting and stopping of the SPS mains (no need for a special supercycle) and digital regulation of current. Digital regulation in the new MUGEF software uses the same regulation library (Libreg) as the FGCs in the LHC, POPS and Booster. Digital regulation will improve the tracking of the reference, management of current and voltage reference limits and monitoring of the regulation error. Electronics
28
28 Command and Interlock System (CIS) CIS HMI (BA3) Master PLC (BA3) Local PLC’s (all BA’s) Local PLC’s (all BA’s) Local PLC’s (all BA’s) … Modernization of the CIS system Reprogramming of new PVSS for CIS was not yet successful. We had to return to the old HP workstation First phase Second phase
29
29 Powering tests
30
30 System tests at the end of LS1 By the end of LS1, all 18 kV cables, all transformers, all thyristors, part of the regulation system will have been replaced: comprehensive tests of the entire system are required before physics can re-start. Power tests of the entire system: SPS ring closed at the end of February 2014, First beam in the SPS beginning of June 2014, Requirement EPC: 2 months of powering tests in March-April 2014,
31
31 Conclusions
32
32 Manufacturing of transformers and thyristor bridges underway, Pre-series transformers have been validated in operation, Pre-series thyristor bridges will be validated in operation in September, Some preparations still need to be done in 2012 (SAX area, civil eng. BA2), In case of major problems, we can always return to the previous situation, Power test period is required, All old transformers and thyristor bridges will be kept for at least 1-2 years as a backup, Proposal to transfer the management of the SAX area to EPC, Conclusions
33
33 Thank you…
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.