CERN Ivan Romera MPE-Technical meeting Status on CERN-ITER collaboration for Machine Protection Acknowledgments: J.Burdalo, R.Schmidt, S.Wagner, M.Zaera Sanz, M.Zerlauth and Critical Systems Lab EDMS 1283934
2
CERN Ivan Romera MPE-Technical meeting Overview of current agreement 2 Collaboration agreement with duration from 2010 to end 2012 ● Task-1: Consultancy for the setup of a Machine Protection Working Group Proposal and recommendations sent to ITER ● Task-2: Definition of the overall architecture of the Machine Protection and Central Interlock System The overall architecture of these systems is defined ● Task-3: Specifications for the fault scenarios simulations Done for the magnet interlock system, new methods were developed to assess architectures of interlock systems + external consultant from system safety domain ● Task-4 Definition of tools for diagnostics of the machine protection systems Partially done, combined with the development of a prototype
3
CERN Ivan Romera MPE-Technical meeting Recap - Powering Layout 3
4
CERN Ivan Romera MPE-Technical meeting Recent activities 1/5 4 ● Prototype for magnet powering interlocks has been completed and delivered to Cadarache (fully documented) ● Following individual commissioning, system is awaiting first connection and tests with quench detectors before being shipped to India & China Redundant S7400 PLCs I/Os in 2oo3 Local supervision Standard User Interface Based on redundant safety PLCs + 2oo3 I/O module configuration (down to and including client connections) Fault tolerant to any single component failure Redundancy of programming through safety matrix + standard logic Local SCADA system + touch screen Standard user interface (DLUI) for client connections and diagnostics
5
CERN Ivan Romera MPE-Technical meeting Recent activities 1/5 5 ● Prototype for magnet powering interlocks has been completed and delivered to Cadarache (fully documented) ● Following individual commissioning, system is awaiting first connection and tests with quench detectors before being shipped to India & China Based on redundant safety PLCs + 2oo3 I/O module configuration (down to and including client connections) Fault tolerant to any single component failure Redundancy of programming through safety matrix + standard logic Local SCADA system + touch screen Standard user interface (DLUI) for client connections and diagnostics
6
CERN Ivan Romera MPE-Technical meeting Recent activities 2/5 6 ● Different HW architectures tested in order to find the fastest and more dependable solution N Discharge loop based on Standard + Failsafe components Implementation based on Safety Matrix + AWL
7
CERN Ivan Romera MPE-Technical meeting Recent activities 3/5 7 ● Different HW architectures tested in order to find the fastest and more dependable solution Discharge loop using only standard components but diversity of components Implementations based on AWL for Boolean Processors and CPU
8
CERN Ivan Romera MPE-Technical meeting Recent activities 4/5 8 ● Working on 2 nd version of User Interface Box (only non COTS component), including Profinet connectivity for diagnostic purposes ● PCB already produced and currently being tested Rad tolerant FPGA User connectivity Mechanics + redundant power supplied Profbus in V1.0 Profinet in V2.0
9
CERN Ivan Romera MPE-Technical meeting Recent activities 5/5 9 ● Completed dependability analysis of magnet powering interlock system with external company from system safety domain (CSL – Critical Systems Lab), including Dependability analysis and review of functional specification, definition of Investment Protection functions Definition of state machines for system functionality (concurrency between circuits) Study of interfaces and dependencies with main client systems (QD, PC, FDU,…) Catalogue of (unresolved) design issues Failure Mode and Effect Analysis (FMEA) for backbone architecture
10
CERN Ivan Romera MPE-Technical meeting Budget and resources 10 ● CERN resources invested to date: 2200 hours of CERN staff (system design, meetings,…) 400 hours of student/Fellow for analysis of interlock architectures 1200 hours of Fellow (50% since Aug 2011) for development of interface box 960 hours of PJAS + 880 hours of external consultant for PLC SW and SCADA ● Additional external resources invested to date: 300 hours of system safety consultancy (through direct contract of CSL with ITER) ● Budget and expenses evolved as planned
11
CERN Ivan Romera MPE-Technical meeting Conclusions 11 ● The collaboration agreement ended in 2012, all deliverables completed ● Collaboration has been fruitful learning experience for CERN in many fields (COTS vs voting in interlock systems, radiation tolerant FPGAs, Profinet, studies of architecture and system dependability,..) ● Due to delay of China test and ITER wish for a V2.0 of user interface, agreed on extension of collaboration by 1 year ● Possible continuation as of 2014 on following topics (tbd): Analysing + feed back the performance from the China tests into final design Provision of full-scale system including full monitoring part Definition of the entire powering interlock system (includes clarification of open questions) Other topics related to Machine Protection (towards interlocking of Plasma)