1
It’s more than adding and subtracting.
2
Before bidding, the site should be examined for the following: Distance from the office Site conditions Site access Soil data and groundwater Security and traffic needs Adjacent structures Possible contamination Water, telephone, and electricity service Obstructions Parking and storage Debris disposal Local weather patterns Local labor and sub-trades Local regulations
3
Materials are purchased in bulk and often long before they are needed, in order to keep down costs. Estimators use basic math (counting), algebra (perimeter), plane geometry (area), and solid geometry (volume). There exist basic formulae for many typical applications.
4
You have to estimate the number of bricks for a wall that measures 15 feet tall and 84 feet long. Standard bricks are estimated at 6.67 bricks per square foot of wall area (add 5% waste). Mortar is estimated at 7.2 cubic feet per 100 square feet of wall area (add 40% waste). How much of each do you need? 1260 ft 2 x 6.67 = 8404 x 1.05 = 8824 bricks 1260 ft 2 ÷ 100 x 7.2 ft 3 = 90 ft 3 x 1.4 = 127 ft 3
5
Cinder blocks are estimated at 11 blocks per 10 ft 2 (add 10% waste). Mortar for block walls is estimated at 2.4 ft 3 per 100 ft 2 of wall (add 30% waste). Calculate the amount of block and mortar needed for 14 foot tall walls of a rectangular building (assume no windows and doors) that measures 37 feet by 52 feet. Calculate the materials of adding a brick veneer to the entire façade.
6
Footings and foundations require 3 dimensional calculations. Their quantities are expressed in cubic yards. 1 cubic yard = 27 cubic feet. To estimate the volume of this footing and foundation, first determine the square foot of the profile or cross-section of both. Then, determine the perimeter. Next, calculate the volume by multiplying the section area by the perimeter. Finally, convert to cubic yards.
7
Footing = 2.0 feet x 0.66 feet = 1.32 ft 2 Foundation = 2.0 feet x 0.66 feet = 1.32 ft 2 Section area = 1.32 ft 2 + 1.32 ft 2 = 2.64 ft 2 Perimeter of building = 24 feet x 4 = 96 feet 2.64 ft 2 x 96 feet = 253.44 ft3 253.44 ft 3 ÷ 27 ft 3 = 9.39 yards 3
8
I Beams to span the short wall dimensions. 20 foot I Beams cost $389.50 and must be placed 24” on center. Corrugated steel panels are laid on the beams. They are 27” wide and 20’ long and cost $262.50 each. Concrete is then poured on top of the corrugated steel panels to tie the roof together as one item. Concrete will be poured to a depth of 3” and span the entire roof. Cost is $175.00 per cubic yard.
9
Insulated panels are then applied to the concrete. These panels measure 48” x 72” and cost $318.80 each. Asphalt is then spread over the insulated panels to make the roof watertight. The asphalt cost is $18.75 per square foot. White stone is then spread over the asphalt to reflect sunlight. This stone costs $322.50 per cubic yard. Spread 3” thick. How would you set up the sheet for “Roofing”?