Download presentation
Presentation is loading. Please wait.
Published byNorman Griffin Modified over 9 years ago
1
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities Operating Guidelines Work Breakdown Structure (WBS) / Master Deliverables List (MDL) Task Planning & Scheduling Budget Risk Planning Communication Plan Change Management Plan Quality (QA/QC) Plan Transition & Closure Plan Project Team Commitment Management Endorsement Implement Transition Plan Review Lessons Learned Reward & Recognize Archive Continuous Communication Managing Scope, Schedule & Budget Manage Risks Manage Change Communicate Progress Issues Lessons Learned Initiate & Align Endorse the Plan Work the Plan Transition & Closure Plan the Work
2
WORK THE PLAN Manage the Scope, Schedule, & Budget Manage Risks Manage Change Communicate: Progress Issues Lessons Learned Initiate & Align Endorse the Plan Work the Plan Transition & Closure Plan the Work
3
Plan the Work 10% + 90 % + Work the Plan TIME LEVEL OF EFFORT Initiate & Align Plan the Work Endorse Close Work the Plan WORK THE PLAN
4
Working the Plan is… Actively managing those planned elements, including scope, schedule, & budget SCOPE BUDGET SCHEDULE Q PROJECT RISK
5
WORK THE PLAN Working the Plan is… Actively monitoring and managing identified risks and change…
6
WORK THE PLAN Working the Plan is… …and responding proactively instead of reactively to potential changes and risk
7
WORK THE PLAN Working the Plan is… Communicating project progress, project issues, and lessons learned
8
WORK THE PLAN Working the Plan is… Effectively communicating & building on relationships within the team, customers, & sponsors
9
WORK THE PLAN Managing Scope, Schedule, & Budget Endorsed Project Management Plan Project WBS Project Schedule Project Budget Project Aging PDIS & PDIS Reports Project Control & Reporting Guide Earned Value Management Current Project Management Plan Management Reports Recovery Plans INPUT TOOLS PRODUCTS
10
WORK THE PLAN Managing Scope, Schedule, & Budget Project includes all work required and quality is consistent with the expectations (Scope) Timely completion of the project (Schedule) The project is completed within the approved budget (Budget)
11
WORK THE PLAN Project Performance Baseline Project Work Breakdown Structure (WBS) Project Baseline Schedule Project Budget Serves three critical functions in managing the project S $
12
WORK THE PLAN Project Performance Baseline Critical Functions “Score-keeping” It provides the target metrics and measures that we use to gauge actual performance against the plan
13
WORK THE PLAN Project Performance Baseline Critical Functions “Attention-directing” It provides the basis for identifying and understanding the potential impact of performance problems
14
WORK THE PLAN Project Performance Baseline Critical Functions “Problem-solving” It provides the background and basis for “testing” solutions to performance problems
15
WORK THE PLAN Project Scope Management Scope Change Control Identifies when a change has occurred Manages change when and if it occurs Influence those factors that create change Ensure they are beneficial and endorsed
16
WORK THE PLAN Project Schedule Management Schedule Change Control Identifies schedule changes Analyze planned vs. actual and manage the required schedule adjustments Influence those factors that create change Ensure they are beneficial and endorsed
17
WORK THE PLAN Project Schedule Management A project schedule that is not kept current is likely to be more “dangerous” than having no schedule at all. A non-current schedule can easily deceive you into thinking the project is at a certain point of evolution when in reality it is not.
18
WORK THE PLAN Project Budget Management Budget Change Control Identify cost baseline changes Analyze planned vs. actual and manage the required budget adjustments Influence the factors that create budget changes
19
WORK THE PLAN Project Budget Management Budget Change Control (cont.) Prevent incorrect, inappropriate, or unauthorized changes from being included in the cost baseline Ensure cost baseline changes are agreed upon and endorsed
20
WORK THE PLAN Managing Scope, Schedule, & Budget A cardinal rule in project management is that, whenever scope, schedule, or assigned project resources change – a corresponding budget review / change is mandatory. The application of this rule often requires involvement and assistance from others who will be expected to endorse the resulting updated plan.
21
WORK THE PLAN Earned Value Management (EVM) What is Earned Value Management? A method of integrating scope, schedule, and resources for measuring project performance PMBOK Guide 2000
22
WORK THE PLAN Earned Value Management (EVM) What is Earned Value Management? It compares the amount of work that was actually earned with what was planned and what was actually spent to determine if schedule and cost performance are as planned PMBOK Guide 2000
23
WORK THE PLAN Earned Value Management (EVM) What is needed for EVM? A baseline plan A project budget A project end date
24
WORK THE PLAN Earned Value Management (EVM) What is needed for EVM? Tasks are identified & scheduled Each task has a budget or effort (resource loaded/weighted) Actuals tracked
25
WORK THE PLAN EVM Definitions What are the budgeted costs of the work scheduled? Time phased based on baseline budget Only changes when baseline is changed (endorsement) Also referred as “BCWS” Planned Value (PV)
26
WORK THE PLAN EVM Definitions What are the actual costs of the work performed? Based on the actual completion of work packages Actual costs for reported work Also referred as “ACWP” Actual Costs (AC)
27
WORK THE PLAN EVM Definitions What are the budgeted costs of the work performed? Based on the actual completion of work packages Baseline value of the reported work Also referred as “BCWP” Earned Value (EV)
28
WORK THE PLAN EVM Formulas Cost Variance (CV) CV = EV – AC If CV value is positive, the project is currently under budget If CV value is negative, the project is currently over budget
29
WORK THE PLAN EVM Formulas Schedule Variance (SV) SV = EV – PV If SV value is positive, the project is ahead of schedule If SV value is negative, the project is behind schedule
30
WORK THE PLAN EVM Formulas Cost Performance Index (CPI) CPI = EV / AC If CV value is > 1.0, the project is currently at/under budget If CV value is < 1.0, the project is currently over budget
31
WORK THE PLAN EVM Formulas Schedule Performance Index (SPI) SPI = EV / PV If SPI value is > 1.0, the project is at/ahead of schedule If SV value is <1.0, the project is behind schedule
32
WORK THE PLAN EVM Formulas Cost Variance % (CV%) CV% = CV / EV If CV value is positive, the project is under budget by % If CV value is negative, the project is over budget by %
33
WORK THE PLAN EVM Formulas Schedule Variance % (SV%) SV% = SV / PV If SV value is positive, the project is ahead of schedule by % If SV value is negative, the project is behind schedule by %
34
WORK THE PLAN EVM Formulas Estimate at Completion (EAC) EAC = AC + ETC This method is used when replanning and endorsement is required. ETC is the Estimate to Complete for the work to be completed.
35
WORK THE PLAN EVM Formulas Estimate at Completion (EAC) EAC = AC + BAC – EV This method is used when variances are viewed as atypical of future performance. (i.e. equipment breakdown causing delay)
36
WORK THE PLAN EVM Formulas Estimate at Completion (EAC) EAC = BAC / CPI This method is used when variances are viewed as typical of future performance.
37
WORK THE PLAN Manage Risks Risk Management is an integral component of day-to-day management of the project Project teams implement and continuously update the Project Risk Management Plan throughout the life of the project
38
WORK THE PLAN Manage Risks Primary Risk Management Functions: Monitoring identified risk events Identifying new risk events Evaluating/revising probability & impact estimates
39
WORK THE PLAN Manage Risks Primary Risk Management Functions: Devising & implementing response plans Evaluate/document effectiveness of responses Reporting
40
WORK THE PLAN Manage Risks Endorsed Project Management Plan Risk Management Plan WSDOT Cost Risk Estimating & Management (CREM) Risk Register Progress Reports Response Strategies INPUTS TOOLS PRODUCTS
41
WORK THE PLAN Manage Risks Implement & Manage the Risk Management Plan Report Agenda Maintain
42
WORK THE PLAN Manage Risks Track and Monitor Potential Risk Events AssignReport Additional Analysis
43
WORK THE PLAN Manage Risks Identify and Evaluate New Risk Elements New Risk Identify triggers If… …then ATMAATMA Response strategy
44
WORK THE PLAN Manage Risks Implement Risk Management Plan when risk event occurs Review Implement Track Monitor Document
45
WORK THE PLAN Manage Risks Manage Risk Response Resources % complete = % risk
46
WORK THE PLAN Change Management Project teams implement the Change Management Plan (CMP) from the Project Management Plan (PMP) and actively identify and manage potential change issues.
47
WORK THE PLAN Change Management A CMP provides the framework for decision making when change occurs
48
WORK THE PLAN Change Management Endorsed Project Management Plan Change Management Plan Project Performance Baseline PDIS & PDIS Reports Project Control & Reporting Guide Management Reports Response Strategies INPUTS TOOLS PRODUCTS
49
WORK THE PLAN Change Management Review Project Change Management Plan Brief team members and other participants on process and procedures
50
WORK THE PLAN Change Management Identify and Manage Change Issues Identify and quantify the variance from the Project Performance Baseline
51
WORK THE PLAN Change Management Administer the Change Process Per the Project CMP, begin the process to address the change issue
52
WORK THE PLAN Change Management Develop Mitigation/Recovery Plans Per the Project CMP, develop plans to recover or mitigate the impacts of change
53
WORK THE PLAN Change Management Obtain Endorsement Project Management iterative process. Obtain endorsement for recovery/mitigation plan
54
WORK THE PLAN Change Management Update Project Performance Baseline After endorsement of the recovery/mitigation plan, update the project Performance Baseline to reflect the current endorsed plan.
55
WORK THE PLAN Change Management Communicate Per the Project Communication Plan, update project team on the changes made.
56
WORK THE PLAN Change Management Project Control Form WSDOT has adopted a standardized change management procedures for Highway Construction projects (CIPP) http://wwwi.wsdot.wa.gov/ProjectReporting/PCR_Proj_Mgmt.htm
57
WORK THE PLAN Communication & Team Building Customer Relationships Know and manage customer expectations Communicate progress Resolve conflict as necessary
58
WORK THE PLAN Communication & Team Building Communication Appropriate frequency and quality is essential for project delivery
59
WORK THE PLAN Communication & Team Building Team Building: Teams are dynamic Teams must be built Teams must be sustained
60
WORK THE PLAN Communication Project teams implement the Communication Plan from the Project Management Plan (PMP).
61
WORK THE PLAN Communication Endorsed Project Management Plan Communication Plan Project Performance Baseline PDIS & PDIS Reports Lessons Learned Website and Database Progress/Status Reports Quarterly Project Reports (QPR) Lessons Learned INPUTS TOOLS PRODUCTS
62
WORK THE PLAN Communication Implementing the Communication Plan
63
WORK THE PLAN Communication Progress Reporting
64
WORK THE PLAN Communication Issues & Issues Reporting
65
WORK THE PLAN Communication Lessons Learned http://wwwi.wsdot.wa.gov/IPD/WSDOT+Lessons+Learned.htm
66
WORK THE PLAN Communication – Lessons Learned
67
WORK THE PLAN Project Management On-Line Guide (PMOG)
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.