BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator
2
Topics to Discuss: Federal Endangered Species Act (ESA) Fish passage plan approval In-water work timing Hydroacoustic impacts from pile driving Questions & Answers
3
Mandate of the Federal Endangered Species Act (ESA) 1900+ listed species in the US. Under Section 7 of the ESA, all Federal agencies must ensure that any actions they authorize, fund, or carry out are not likely to jeopardize the continued existence of a listed species, or destroy or adversely modify its designated critical habitat.
4
Federal Nexus → Triggers ESA Federal Funds (FHWA) Federal Property (Forest Service, BLM) Federal Permit (USCOE) Section 7 requires consultation with National Marine Fisheries Service (NMFS) and/or US Fish and Wildlife Service (USFWS) (ODOT is FHWA’s non-federal representative) Consultation is Required Before a Project is Authorized
5
‘Take’ is Prohibited by the ESA, unless a permit has been issued through consultation with the NMFS or USFWS Take = “harm, harass, pursue, hunt, shoot, wound, kill, trap, capture, or collect” Harm = “significant habitat modification or degradation that results in death or injury” Harass = “significantly disrupts normal behavior patterns” including “breeding, feeding or sheltering”
6
Consultation: 1. Biological Assessment (BA) A document written by a biologist to determine the project impacts on listed species. Describes the project, baseline conditions, and includes an analysis of effect. Includes a “Finding of Effect” for listed species & designated critical habitat
7
Finding of Effect: No Effect (must document, but no BA needed) Not Likely Adverse Affect (NLAA) Likely Adverse Affect (LAA) Adverse modification of critical habitat
8
2. Biological Opinion (BiOp) Jeopardy Analysis Incidental Take Statement Terms and Conditions
9
Think of the Biological Opinion (permit) as a fishing license, you must have it to be legal!Think of the Biological Opinion (permit) as a fishing license, you must have it to be legal! Any form of ‘take’ is illegal without a BiOp and accompanying Incidental Take Statement.Any form of ‘take’ is illegal without a BiOp and accompanying Incidental Take Statement.
10
Magnuson-Stevens Act Essential Fish Habitat (EFH) = waters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity Covers:coastal pelagics, ground fish Pacific salmon Appended to the ESA BA
11
Federal ESA Permits Letter of Concurrence (LOC) Biological Opinion (BiOp) Jeopardy Opinion - Bad News The Permit Must be on Site During Construction
12
Do I Have to Write a New BA for Each Project? No… your project may fit a programmatic. Standard Local Operating Procedures for Endangered Species (SLOPES) Programmatic Biological Opinion
13
ODOT’s BA Qualification Training July 8-9, 2009 2-Day Training & Test Must Be Qualified to Write or Review BA’s for ODOT under contract Must Maintain Qualification and renew every 3 years To Register: Lorrie Schaefer at 503-986-3840 By E-mail: ODOT.HR.Training@odot.state.or.us ODOT.HR.Training@odot.state.or.us
14
Location of BA Template and Guidance Electronic versions ODOT NRU Biology Publication Internet site: http://www.oregon.gov/ODOT/HWY/GE OENVIRONMENTAL/biology.shtml This web location has the latest versions of the ODOT BA Template, Writing Guidance, and BA Checklist to download
15
ESA Documentation Timeline For Construction Projects Bid Let Preliminary Plans (30 %) Advanced Plans (90 %) Plans, Specification and Estimate (PS&E) 10 mo. 9 8 7 6 5 4 3 2 1 Project Footprint Submit Formal BA (LAA) Receive Biological Opinion/Take Statement (LAA) or Letter of Concurrence (NLAA) Pre-consultation
16
Transmittal Process & Timeline BA goes to ODOT Environmental, then Action Agency (e.g., FHWA) transmits directly to Services (135 Days) NOTE: allow an additional 2 weeks for Action Agency to transmit to Regulatory Agency Must Program at least 150 Days into Project Schedule (from PSE Date) to Allow for ESA Timelines
17
When You Receive the Permit(s) Read & review all permits Assure all BMP’s and T&C’s of permit get into final project contract documents -ODFW In-water work period -ID no work zones on plan sheets -Include OHW elevation on plan sheets Work with specification writer and appropriate designer to develop final contract documents (plans & specs)
18
Implementation and Construction The process does not stop once the permit is received Terms & Conditions from the permit must be reflected in the construction documents and contract (plans & specifications) Long-term maintenance & reporting (typically 5-years) Responsibility of the Local Agency
19
Re-Initiation of Consultation All ESA permits include a standard re-initiation clause Triggers for re-initiation may be listed
20
Re-Initiation Incidental take is exceeded New information, the action may affect a listed species in a manner not previously considered The action is modified in a manner that causes an effect not previously considered New species listing or critical habitat designation Permit expiration
21
Successful Projects Involve… Effective scoping - ID critical natural resource elements - ID construction alternatives and associated costs - ID mitigation opportunities and strategies Understanding of the action Early coordination and pre-consultation with NMFS/USFWS liaisons
22
Fish Passage
23
ORS 509.585 ODFW Fish PassageODFW Fish Passage http://www.dfw.state.or.us/fish/passage/ “Must Provide Fish Passage” Applies to streams with native, migratory fish (present & historically present) ODFW State Fish Passage Statute
24
At artificial obstructions (culvert, bridge, tide gate) Where native migratory fish are currently or were historically present, and When a "trigger event" will occur OR When the OFWC identifies an emergency location, condemns a passage site, or identifies a "priority" location Fish Passage Must Be Addressed...
25
ODFW Statute Triggers “Culvert Triggers”: culvert extensions or repairs, slip-lining, new aprons, 50% or greater repairs, 50% removal of roadbed, extension of roadbed, new wingwalls, etc… “Bridge Triggers”: new bridge, replacement bridge, over 50% of existing bridge elements are cumulatively removed, replaced, filled, or added through time Waiver & Exceptions (through ODFW)
26
Waivers –Passage would currently benefit native migratory fish –Mitigation which provides a net benefit is required –In effect until next trigger Exemptions –If passage would currently provide “no appreciable benefit” –No mitigation required –Can be revoked, in which case passage is required immediately Waivers and Exemptions
27
Fish Passage Plan Fish passage plan approval: ODFW NMFS Discuss early in project development
29
Fish Passage Design Considerations State Statute via. ODFW web site ODOT Hydraulics Manual ODFW Fish Passage Coordinator ODOT–ODFW Liaisons Where do I go for more information?
30
In-water Work Timing Know the in-water work window How will the in-water window effect the construction timeline? Applying for a variance
33
Hydroacoustic Impacts Pile Driving impacts Vibratory hammer versus impact hammer Pile size Substrate Attenuation technology Bubble curtains Monitoring Cost to the project
34
Bubble Curtain
35
Questions?