Presentation is loading. Please wait.

Presentation is loading. Please wait.

o Existing pipe designed for gravity outfall flow – peak storm flows raise pressures above design pressure o Single gasket joint every 12’ subject to.

Similar presentations


Presentation on theme: "o Existing pipe designed for gravity outfall flow – peak storm flows raise pressures above design pressure o Single gasket joint every 12’ subject to."— Presentation transcript:

1

2 o Existing pipe designed for gravity outfall flow – peak storm flows raise pressures above design pressure o Single gasket joint every 12’ subject to leaks with movement of ground o Vertically pulled (angled) joints that pull further apart and leak with young bay mud movement or vertical loading o Hydrogen sulfide gas from sewage eating away at unlined pipe - concrete and steel decaying o Leaks would spill into commercial and residential areas – potential damage associated with spill is very high o Upstream sewer system improvements (to reduce upstream spills) will increase flows and therefore pressures in force main o Events that increase likelihood of leaks:  Earthquakes  Surge from sudden power outage Need for Project

3 Likely scenarios for leaks: Earthquakes Earthquake induced young bay mud movement  Earthquake causes young bay mud to move as earthquake forces act on loads near pipe  Pipe joints move when young bay mud moves  Single gasket joints open and concrete pipe at joints crack  Sewage then leaks to surface in commercial or residential area  Standard response when a leak is noticed is to turn on the SBSA influent pumps to reduce pressures in the pipe  Turning on SBSA influent pumps does not stop the leak during high flow events when the influent pumps are already on – the combination of booster pumps and influent pumps are needed to carry high flows

4 Likely scenarios for leaks: Power Outage Sudden surge caused by power outage during storm event  During storm events with high flow a sudden power outage may occur  Pumps suddenly turn off when power cut (before generator can come on)  Flow continues to move down pipe with no new flow following creating a vacuum in the pipe pulling the decaying concrete pipe inward  The vacuum then reverses the sewage flow and sewage flow slams back into the pump station  Extremely high outward pressure is created which bursts the decaying pipe resulting in a sewage spill (the pipe in the worst condition has been replaced)  During a storm event (with huge sewage flows) the normal process to address a leak of turning on the influent pumps at the treatment plant will not be enough to prevent an ongoing spill (the influent pumps will likely already be on)  The spill will continue through the break in the pipe or if the pumps are turned down the spill will occur upstream in the system as flows back up

5 Proposed Pipe: HDPE  High density polyethylene pipe  At least 3 inches thick  Continuous pipe with no joints – pieces are fusion welded to each other  Not affected by corrosion  Pipe sections when accidently crushed flat go back to original shape with no cracking or failure  Pipe sections pressure tested to failure reach five times the design pressure before getting a small hole (no catastrophic failures)  Most impacts from digging equipment to outside glance off pipe  Risk of cutting into pipe very low when pipe is in a location with minimal construction activity (like a levee)

6 Break after surge due to power outage

7 Leak near Governors Bay Dr. – leaked at joint which was broken – took weeks to fix

8 Leak near Governors Bay Dr. – more


Download ppt "o Existing pipe designed for gravity outfall flow – peak storm flows raise pressures above design pressure o Single gasket joint every 12’ subject to."

Similar presentations


Ads by Google